$74.96Avg low bid / TON
$75.50Avg of all bids
$76.03Avg engineer's estimate
17Jobs · 191,159.3 TON
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2020 | 1 | 520 | $122.00 | $121.00 |
| 2019 | 7 | 37,082 | $74.35 | $72.14 |
| 2018 | 4 | 31,367 | $68.15 | $70.21 |
| 2017 | 3 | 89,775.3 | $66.51 | $70.92 |
| 2016 | 2 | 32,415 | $104.89 | $105.78 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Apr 8, 2020 | 2073-01-009 | GreggTyler | 520 TON | $122.00 | EAST TEXAS BRIDGE, INC. |
| Dec 3, 2019 | 6347-43-001 | JeffersonBeaumont | 4,851 TON | $82.50 | PTSS INVESTMENTS, LLC |
| Aug 6, 2019 | 0016-16-030 | HaysAustin | 557 TON | $148.00 | LONE STAR SITEWORK, LLC |
| Mar 6, 2019 | 0150-04-047 | LlanoAustin | 10,093 TON | $77.60 | ACME BRIDGE COMPANY, INC. |
| Mar 5, 2019 | 2242-02-022 | ChambersBeaumont | 1,988 TON | $111.71 | COPASA, INC. |
| Feb 6, 2019 | 0016-05-119 | ComalSan Antonio | 1,411 TON | $59.40 | BRIDGES AND ROADS, LLC |
| Feb 5, 2019 | 0508-02-120 | ChambersBeaumont | 1,494 TON | $67.24 | COPASA, INC. |
| Feb 5, 2019 | 2452-04-016 | BexarSan Antonio | 16,688 TON | $65.00 | MARIO SINACOLA & SONS EXCAVATING, INC. |
| Dec 5, 2018 | 0015-01-243 | McLennanWaco | 17,580 TON | $72.00 | WEBBER, LLC |
| Oct 3, 2018 | 0374-02-097 | El PasoEl Paso | 3,595 TON | $70.00 | JORDAN FOSTER CONSTRUCTION, LLC |
| Sep 7, 2018 | 0143-01-055 | BexarSan Antonio | 1,096 TON | $68.00 | JORDAN FOSTER CONSTRUCTION, LLC |
| Jun 5, 2018 | 2452-03-112 | BexarSan Antonio | 9,096 TON | $60.00 | FLATIRON CONSTRUCTORS, INC. |
| Nov 3, 2017 | 0366-02-090 | GuadalupeSan Antonio | 832 TON | $71.00 | Curran Contracting Company |
| Jul 11, 2017 | 0162-02-031 | HillWaco | 60,563 TON | $56.40 | SUNDT CONSTRUCTION, INC. |
| Mar 8, 2017 | 0007-06-084 | EastlandBrownwood | 28,380.3 TON | $87.95 | ZACHRY CONSTRUCTION CORPORATION |
| Nov 4, 2016 | 6280-45-001 | HendersonTyler | 9,777 TON | $100.00 | DREWERY CONSTRUCTION COMPANY, INCORPORATED |
| Nov 3, 2016 | 6306-16-001 | SmithTyler | 22,638 TON | $107.00 | MADDEN CONTRACTING COMPANY, LLC. |