$661.27Avg low bid / TON
$707.13Avg of all bids
$662.63Avg engineer's estimate
5Jobs · 35,865.78 TON
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2023 | 2 | 13,710.52 | $890.47 | $1,008.79 |
| 2021 | 1 | 6,662.26 | $638.25 | $669.42 |
| 2017 | 1 | 8,629 | $500.25 | $502.63 |
| 2016 | 1 | 6,864 | $428.19 | $416.60 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Oct 6, 2023 | 0009-04-075 | RockwallDallas | 6,357.81 TON | $869.05 | BRANNAN PAVING CO., LTD. |
| Jan 5, 2023 | 0095-03-107 | KaufmanDallas | 7,352.71 TON | $909.00 | BRANNAN PAVING CO., LTD. |
| Oct 8, 2021 | 0047-04-036 | CollinDallas | 6,662.26 TON | $638.25 | BRANNAN PAVING CO., LTD. |
| Dec 5, 2017 | 0009-18-020 | HopkinsParis | 8,629 TON | $500.25 | BRANNAN PAVING CO., LTD. |
| Dec 1, 2016 | 0009-13-163 | HuntParis | 6,864 TON | $428.19 | BRANNAN PAVING CO., LTD. |