$9.97Avg low bid / SY
$17.04Avg of all bids
$10.83Avg engineer's estimate
5Jobs · 42,241 SY
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2024 | 1 | 7,447 | $8.60 | $21.90 |
| 2021 | 2 | 30,558 | $8.96 | $13.86 |
| 2019 | 1 | 485 | $20.00 | $28.33 |
| 2018 | 1 | 3,751 | $19.60 | $22.27 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jan 4, 2024 | 0168-05-043 | Deaf SmithAmarillo | 7,447 SY | $8.60 | L A FULLER & SONS CONSTRUCTION, LTD. |
| Dec 1, 2021 | 0226-02-038 | OldhamAmarillo | 10,535 SY | $16.00 | J. LEE MILLIGAN, INC. |
| Apr 8, 2021 | 0041-02-016 | HartleyAmarillo | 20,023 SY | $5.25 | J. LEE MILLIGAN, INC. |
| May 8, 2019 | 1690-01-120 | LamarParis | 485 SY | $20.00 | EAST TEXAS BRIDGE, INC. |
| Dec 6, 2018 | 2635-02-035 | RandallAmarillo | 3,751 SY | $19.60 | J. LEE MILLIGAN, INC. |