$15.05Avg low bid / SY
$14.88Avg of all bids
$13.91Avg engineer's estimate
3Jobs · 91,217 SY
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2024 | 1 | 13,113 | $29.79 | $21.73 |
| 2022 | 1 | 437 | $25.76 | $44.03 |
| 2021 | 1 | 77,667 | $12.50 | $13.40 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Aug 2, 2024 | 0521-06-155 | BexarSan Antonio | 13,113 SY | $29.79 | ZACHRY CONSTRUCTION CORPORATION |
| Jun 30, 2022 | 0017-13-012 | AtascosaSan Antonio | 437 SY | $25.76 | HUNTER INDUSTRIES, LTD. |
| Dec 2, 2021 | 0849-01-055 | BexarSan Antonio | 77,667 SY | $12.50 | HARPER BROTHERS CONSTRUCTION LLC |