$11.86Avg low bid / SY
$12.82Avg of all bids
$13.14Avg engineer's estimate
10Jobs · 476,165 SY
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2024 | 1 | 13,467 | $14.00 | $17.18 |
| 2022 | 1 | 101,703 | $8.00 | $9.17 |
| 2021 | 2 | 151,728 | $13.19 | $15.41 |
| 2020 | 2 | 58,336 | $13.05 | $12.10 |
| 2019 | 2 | 96,168 | $15.18 | $15.45 |
| 2018 | 1 | 267 | $25.00 | $24.30 |
| 2017 | 1 | 54,496 | $7.60 | $6.95 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| May 3, 2024 | 2121-01-104 | El PasoEl Paso | 13,467 SY | $14.00 | SUNDT CONSTRUCTION, INC. |
| Feb 4, 2022 | 2121-01-094 | El PasoEl Paso | 101,703 SY | $8.00 | SUNDT CONSTRUCTION, INC. |
| Oct 8, 2021 | 2121-01-094 | El PasoEl Paso | 77,334 SY | $10.00 | JORDAN FOSTER CONSTRUCTION, LLC |
| Aug 4, 2021 | 0050-03-096 | GrimesBryan | 74,394 SY | $16.50 | LARRY YOUNG PAVING, INC. |
| Sep 3, 2020 | 0265-02-036 | TravisAustin | 58,332 SY | $13.00 | ZACHRY CONSTRUCTION CORPORATION |
| Feb 6, 2020 | 0275-01-199 | PotterAmarillo | 4 SY | $772.71 | ALLEN BUTLER CONSTRUCTION, INC. |
| Mar 6, 2019 | 6343-03-001 | MenardSan Angelo | 48,084 SY | $15.36 | SALINAS CONSTRUCTION TECHNOLOGIES, LTD. |
| Jan 9, 2019 | 6337-64-001 | MenardSan Angelo | 48,084 SY | $15.00 | ALLEN KELLER COMPANY |
| Aug 8, 2018 | 0002-01-095 | El PasoEl Paso | 267 SY | $25.00 | MARIL ENTERPRISES LLC |
| Dec 6, 2017 | 2121-01-091 | El PasoEl Paso | 54,496 SY | $7.60 | INTERNATIONAL EAGLE ENTERPRISES, INC. |