SL 360 AT COURTYARD DRIVE
0113-13-168 · let Nov 6, 2025 · Travis, Austin · Interchange (New or Reconstructed)
$68,389,116Low bid: WEBBER, LLC-1.4% vs estimate $69,364,953
$372,691Left on the table0.5% gap to the second bid
8BiddersSpread 20% low to high
617Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | WEBBER, LLC | $68,389,116 | -1.4% | $372,691 | 3+$12,070,076 | 1-$739,193 | |
| 2 | JAMES CONSTRUCTION GROUP, LLC | $68,761,807 | +0.5% | -0.9% | $555,964 | 6+$11,407,929 | 0 |
| 3 | JOE BLAND CONSTRUCTION LLC | $69,317,771 | +1.4% | -0.1% | $665,932 | 4+$2,866,338 | 1-$506,417 |
| 4 | RAGLE CONSTRUCTION, INC. | $69,983,703 | +2.3% | 0.9% | $265,505 | 3+$17,160,642 | 2-$1,073,090 |
| 5 | ALTUS CONSTRUCTION LLC | $70,249,208 | +2.7% | 1.3% | $2,743,670 | 7+$19,100,643 | 2-$1,525,593 |
| 6 | COPASA INC | $72,992,878 | +6.7% | 5.2% | $191,688 | ||
| 7 | PULICE CONSTRUCTION, INC. | $73,184,566 | +7.0% | 5.5% | $8,930,256 | ||
| 8 | JORDAN FOSTER CONSTRUCTION, LLC | $82,114,822 | +20.1% | 18.4% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
WEBBER, LLC vs JAMES CONSTRUCTION GROUP, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 69.17 STA | $83,097.33 | $39,000.00 | $6,072.92 | -$3,050,212 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 56,499 CY | $3.88 | $50.07 | $16.96 | $2,609,689 |
| 423-7001 RETAINING WALL (MSE) | 50,204 SF | $80.96 | $59.89 | $74.07 | -$1,057,798 |
| 411-7001 ROCK NAIL ANCHORS | 66,646 LF | $21.66 | $33.07 | $33.99 | $760,431 |
| 450-7008 RAIL (TY T223) | 10,563 LF | $75.43 | $132.35 | $141.07 | $601,246 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 33 MO | $13,836.96 | $30,595.50 | $11,585.04 | $553,032 |
| 500-7001 MOBILIZATION | 1 LS | $6,808,563.00 | $6,300,000.00 | $523,850.32 | -$508,563 |
| 450-7051 RAIL (TY T80PP) | 1,130 LF | $171.07 | $607.02 | $159.05 | $492,624 |
| 247-7179 FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS) | 14,648 CY | $61.76 | $92.19 | $63.96 | $445,739 |
| 464-7005 RC PIPE (CL III)(24 IN) | 2,884 LF | $267.00 | $145.79 | $108.34 | -$349,570 |
| 450-7034 RAIL (TY C223) | 3,877 LF | $100.71 | $185.62 | $168.43 | $329,196 |
| 619-7015 ITS MULTI-DUCT CND (HDPE) | 9,090 LF | $39.65 | $4.00 | $39.65 | -$324,059 |
| 476-7023 JACK BOR OR TUN PIPE(36 IN)(RC)(CL IV) | 211 LF | $1,095.00 | $2,512.49 | $852.92 | $299,090 |
| 423-7024 RETAINING WALL (ROCK NAIL) (FASCIA) | 50,831 SF | $70.98 | $76.29 | $58.51 | $269,913 |
| 432-7036 RIPRAP (STONE COMMON)(GROUT)(6 IN) | 670 CY | $700.85 | $304.39 | $481.86 | -$265,628 |
| 442-7001 STR STEEL (PLATE GIRDER) | 832,990 LB | $2.34 | $2.64 | $2.35 | $249,897 |
| 512-7089 PCTB (FUR&INST)(F-SHAPE OR SNGL SLP)TY1 | 10,860 LF | $60.32 | $37.38 | $32.87 | -$249,128 |
| 105-7015 RMV (15"-19") TRT/UNTRT BASE & ASPH PAV | 27,975 SY | $18.50 | $10.21 | $17.92 | -$231,913 |
| 619-7008 ITS MULTI-DUCT CND (RMC) | 3,140 LF | $75.00 | $4.00 | $100.25 | -$222,940 |
| 110-7003 EXCAV (SPECIAL) | 275,474 CY | $21.57 | $22.27 | $18.78 | $192,832 |
Positive: the low bidder was cheaper on that item. These 20 items account for $543,876 of the $372,691 gap.
WEBBER, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $6,808,563.00 | $523,850.32 | 13.00x | $6,284,713 |
| 100-7002 PREPARING ROW | 69.17 STA | $83,097.33 | $6,072.92 | 13.68x | $5,327,778 |
| 464-7005 RC PIPE (CL III)(24 IN) | 2,884 LF | $267.00 | $108.34 | 2.46x | $457,585 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 56,499 CY | $3.88 | $16.96 | 0.23x | -$739,193 |
JAMES CONSTRUCTION GROUP, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $6,300,000.00 | $523,850.32 | 12.03x | $5,776,150 |
| 100-7002 PREPARING ROW | 69.17 STA | $39,000.00 | $6,072.92 | 6.42x | $2,277,566 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 56,499 CY | $50.07 | $16.96 | 2.95x | $1,870,495 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 33 MO | $30,595.50 | $11,585.04 | 2.64x | $627,345 |
| 450-7051 RAIL (TY T80PP) | 1,130 LF | $607.02 | $159.05 | 3.82x | $506,205 |
| 476-7023 JACK BOR OR TUN PIPE(36 IN)(RC)(CL IV) | 211 LF | $2,512.49 | $852.92 | 2.95x | $350,168 |
JOE BLAND CONSTRUCTION LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,000,000.00 | $523,850.32 | 3.82x | $1,476,150 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 33 MO | $27,500.00 | $11,585.04 | 2.37x | $525,194 |
| 512-7089 PCTB (FUR&INST)(F-SHAPE OR SNGL SLP)TY1 | 10,860 LF | $75.00 | $32.87 | 2.28x | $457,580 |
| 619-7008 ITS MULTI-DUCT CND (RMC) | 3,140 LF | $230.00 | $100.25 | 2.29x | $407,415 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 56,499 CY | $8.00 | $16.96 | 0.47x | -$506,417 |
RAGLE CONSTRUCTION, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 69.17 STA | $121,250.00 | $6,072.92 | 19.97x | $7,966,799 |
| 500-7001 MOBILIZATION | 1 LS | $6,800,000.00 | $523,850.32 | 12.98x | $6,276,150 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 33 MO | $100,000.00 | $11,585.04 | 8.63x | $2,917,694 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 56,499 CY | $4.50 | $16.96 | 0.27x | -$704,164 |
| 431-7001 PNEUMATICALLY PLACED CONC (ENCASEMENT) | 8,536 SF | $8.00 | $51.22 | 0.16x | -$368,926 |
ALTUS CONSTRUCTION LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 69.17 STA | $100,546.19 | $6,072.92 | 16.56x | $6,534,716 |
| 500-7001 MOBILIZATION | 1 LS | $6,989,905.07 | $523,850.32 | 13.34x | $6,466,055 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 33 MO | $106,439.85 | $11,585.04 | 9.19x | $3,130,209 |
| 508-7001 CONSTRUCTING DETOURS | 7,041 SY | $261.85 | $83.58 | 3.13x | $1,255,143 |
| 531-7002 CONC SIDEWALKS (5") | 11,677 SY | $130.96 | $68.80 | 1.90x | $725,818 |
| 431-7001 PNEUMATICALLY PLACED CONC (ENCASEMENT) | 8,536 SF | $115.37 | $51.22 | 2.25x | $547,559 |
| 464-7005 RC PIPE (CL III)(24 IN) | 2,884 LF | $261.30 | $108.34 | 2.41x | $441,143 |
| 7008-7029 ENCASEMENT PIPE (54")STEEL(BORE) | 560 LF | $1,218.19 | $3,300.00 | 0.37x | -$1,165,816 |
| 7008-7019 AUTO COMBO AIR/VAC RELEASE VALVE AM 8" | 2 EA | $51,111.57 | $231,000.00 | 0.22x | -$359,777 |