US183 FM1032 TO EASTLAND CL FY26 SC
0257-01-051 · let Nov 5, 2025 · Stephens, Brownwood · Seal Coat
$4,216,099Low bid: CLARK CONSTRUCTION OF TEXAS, INC.-15.2% vs estimate $4,974,278
$234,819Left on the table5.6% gap to the second bid
6BiddersSpread 21% low to high
106Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | CLARK CONSTRUCTION OF TEXAS, INC. | $4,216,099 | -15.2% | $234,819 | 0 | 1-$32,601 | |
| 2 | D. I. J. CONSTRUCTION, INC. | $4,450,918 | +5.6% | -10.5% | $128,057 | 0 | 3-$330,486 |
| 3 | NORTHEASTERN PAVERS, LLC | $4,578,976 | +8.6% | -7.9% | $13,633 | 0 | 2-$221,782 |
| 4 | CK NEWBERRY, LLC | $4,592,609 | +8.9% | -7.7% | $133,407 | 1+$101,591 | 1-$32,461 |
| 5 | RONALD R. WAGNER & CO., LP | $4,726,016 | +12.1% | -5.0% | $396,512 | 1+$477,514 | 1-$32,601 |
| 6 | A. L. HELMCAMP, INC. | $5,122,528 | +21.5% | 3.0% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
CLARK CONSTRUCTION OF TEXAS, INC. vs D. I. J. CONSTRUCTION, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 354-7031 PLANE ASPH CONC PAV(0" TO 1") | 1,031,603 SY | $0.7700 | $1.24 | $1.08 | $484,853 |
| 500-7001 MOBILIZATION | 1 LS | $667,851.00 | $449,000.00 | $523,850.32 | -$218,851 |
| 316-7208 AGGR (TY-PB, GR-3)(SAC-B) | 9,994 CY | $102.80 | $115.00 | $110.18 | $121,927 |
| 316-7175 AGGR (TY-B, GR-5)(SAC-B) | 3,279 CY | $45.00 | $18.00 | $88.19 | -$88,533 |
| 316-7032 ASPH (RC-250) | 95 TON | $877.50 | $375.00 | $1,089.28 | -$47,738 |
| 316-7023 ASPH (AC-20-5TR) | 1,837 TON | $632.75 | $620.00 | $696.11 | -$23,422 |
| 316-7276 AGGR (TY-PB GR-4 MOD) | 1,525 CY | $91.38 | $105.00 | $103.27 | $20,771 |
| 502-7004 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 EA | $5,000.00 | $4,000.00 | $3,068.24 | -$6,000 |
| 672-7004 REFL PAV MRKR TY II-A-A | 7,004 EA | $5.00 | $4.25 | $3.97 | -$5,253 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 6,691 EA | $0.0100 | $0.6500 | $0.5715 | $4,282 |
| 666-7175 RE PM TY II (W) 6" (SLD) | 423,284 LF | $0.1700 | $0.1600 | $0.1701 | -$4,233 |
| 666-7192 RE PM TY II (W) (LN REDUCT ARW) | 14 EA | $450.00 | $230.00 | $230.02 | -$3,080 |
| 666-7184 RE PM TY II (W) 24" (SLD) | 792 LF | $5.00 | $3.35 | $3.83 | -$1,307 |
| 662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W | 615 EA | $0.0100 | $0.6500 | $1.03 | $394 |
| 666-7211 RE PM TY II (Y) 6" (BRK) | 39,024 LF | $0.1700 | $0.1800 | $0.1759 | $390 |
| 666-7177 RE PM TY II (W) 8" (DOT) | 511 LF | $0.2500 | $1.00 | $0.5160 | $383 |
| 672-7002 REFL PAV MRKR TY I-C | 161 EA | $7.00 | $5.00 | $4.04 | -$322 |
| 666-7179 RE PM TY II (W) 8" (SLD) | 887 LF | $0.2500 | $0.5000 | $0.4127 | $222 |
| 666-7172 RE PM TY II (W) 6" (BRK) | 9,735 LF | $0.1700 | $0.1900 | $0.2347 | $195 |
| 666-7217 RE PM TY II (Y) 24" (SLD) | 75 LF | $5.00 | $3.00 | $3.73 | -$150 |
Positive: the low bidder was cheaper on that item. These 20 items account for $234,529 of the $234,819 gap.
CLARK CONSTRUCTION OF TEXAS, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 142 DAY | $0.0100 | $229.60 | 0.00x | -$32,601 |