FM 1777 FROM FM 6 TO CR 677
1014-04-015 · let Nov 6, 2025 · Collin, Dallas · Rehabilitation of Existing Road
$6,601,558Low bid: D. L. LENNON INCORPORATED - CONTRACTOR-33.3% vs estimate $9,890,108
$1,593,058Left on the table24.1% gap to the second bid
5BiddersSpread 42% low to high
86Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | D. L. LENNON INCORPORATED - CONTRACTOR | $6,601,558 | -33.3% | $1,593,058 | 0 | 2-$1,264,870 | |
| 2 | ED BELL CONSTRUCTION COMPANY | $8,194,616 | +24.1% | -17.1% | $174,486 | 3+$418,617 | 2-$1,105,726 |
| 3 | OVERLAND CORPORATION | $8,369,102 | +26.8% | -15.4% | $79,469 | 3+$595,339 | 2-$823,781 |
| 4 | A. K. GILLIS & SONS, LLC | $8,448,572 | +28.0% | -14.6% | $949,879 | 4+$493,588 | 2-$1,206,308 |
| 5 | GREY SKY CONSTRUCTION LLC | $9,398,451 | +42.4% | -5.0% | 3+$455,197 | 1-$244,465 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
D. L. LENNON INCORPORATED - CONTRACTOR vs ED BELL CONSTRUCTION COMPANY, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $295,855.00 | $827,000.00 | $523,850.32 | $531,145 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $6,667.00 | $31,500.00 | $11,585.04 | $297,996 |
| 247-7125 FL BS (CMP IN PLC)(TY D GR 1-2) (12") | 63,050 SY | $29.00 | $33.50 | $29.90 | $283,725 |
| 100-7002 PREPARING ROW | 173.37 STA | $375.00 | $1,200.00 | $6,072.92 | $143,030 |
| 275-7006 CEMENT TRT (EXIST MATL & NEW BASE)(6") | 64,981 SY | $1.55 | $3.00 | $2.25 | $94,222 |
| 110-7001 EXCAV (ROADWAY) | 11,254 CY | $16.00 | $8.00 | $11.68 | -$90,032 |
| 150-7001 BLADING | 173.37 STA | $300.00 | $800.00 | $152.64 | $86,685 |
| 354-7005 PLANE & TEXT ASPH CONC PAV(0" TO 6") | 49,398 SY | $3.60 | $5.25 | $4.63 | $81,507 |
| 134-7004 BACKFILL (TY A OR B) | 173.37 STA | $268.00 | $600.00 | $211.21 | $57,559 |
| 316-7244 AGGR (TY-B OR L, GR-3)(SAC-B) | 404 CY | $136.78 | $272.64 | $157.65 | $54,887 |
| 247-7209 FL BS (RDWY DEL) (TY D GR 1-2) | 15,765 TON | $43.00 | $40.00 | $51.99 | -$47,295 |
| 464-7003 RC PIPE (CL III)(18 IN) | 2,064 LF | $52.00 | $70.00 | $83.08 | $37,152 |
| 251-7055 REWORK BS MTL (TY C)(12")(ORD COMP) | 49,398 SY | $2.40 | $3.00 | $2.69 | $29,639 |
| 533-7001 MILL RUMBLE STRIPS (ASPHALT) (SHLDR) | 26,477 LF | $1.16 | $0.1500 | $0.2040 | -$26,742 |
| 316-7251 AGGR (TY-B OR L, GR-5) | 171 CY | $125.00 | $276.90 | $136.70 | $25,975 |
| 344-7011 SP MIXES SP-C SAC-B PG64-22 | 7,610 TON | $139.30 | $136.00 | $130.31 | -$25,113 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $21,000.00 | $10,000.00 | $9,253.78 | -$22,000 |
| 530-7006 DRIVEWAYS (CONC) | 1,343 SY | $110.00 | $95.00 | $109.20 | -$20,145 |
| 467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P) | 126 EA | $800.00 | $650.00 | $1,176.76 | -$18,900 |
| 506-7011 ROCK FILTER DAMS (REMOVE) | 527 LF | $12.00 | $47.25 | $12.47 | $18,577 |
Positive: the low bidder was cheaper on that item. These 20 items account for $1,491,872 of the $1,593,058 gap.
D. L. LENNON INCORPORATED - CONTRACTOR: unbalanced items
Placed 1ED BELL CONSTRUCTION COMPANY: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $31,500.00 | $11,585.04 | 2.72x | $238,979 |
| 150-7001 BLADING | 173.37 STA | $800.00 | $152.64 | 5.24x | $112,233 |
| 134-7004 BACKFILL (TY A OR B) | 173.37 STA | $600.00 | $211.21 | 2.84x | $67,404 |
| 100-7002 PREPARING ROW | 173.37 STA | $1,200.00 | $6,072.92 | 0.20x | -$844,818 |
| 168-7001 VEGETATIVE WATERING | 32,886 TGL | $0.5000 | $8.43 | 0.06x | -$260,908 |
OVERLAND CORPORATION: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $34,000.00 | $11,585.04 | 2.93x | $268,979 |
| 275-7006 CEMENT TRT (EXIST MATL & NEW BASE)(6") | 64,981 SY | $4.95 | $2.25 | 2.20x | $175,767 |
| 530-7010 DRIVEWAYS (ACP) | 3,416 SY | $99.04 | $54.96 | 1.80x | $150,593 |
| 100-7002 PREPARING ROW | 173.37 STA | $2,500.00 | $6,072.92 | 0.41x | -$619,437 |
| 168-7001 VEGETATIVE WATERING | 32,886 TGL | $2.22 | $8.43 | 0.26x | -$204,344 |
A. K. GILLIS & SONS, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $31,036.67 | $11,585.04 | 2.68x | $233,419 |
| 110-7001 EXCAV (ROADWAY) | 11,254 CY | $25.00 | $11.68 | 2.14x | $149,879 |
| 150-7001 BLADING | 173.37 STA | $500.00 | $152.64 | 3.28x | $60,222 |
| 134-7004 BACKFILL (TY A OR B) | 173.37 STA | $500.00 | $211.21 | 2.37x | $50,067 |
| 100-7002 PREPARING ROW | 173.37 STA | $525.00 | $6,072.92 | 0.09x | -$961,843 |
| 168-7001 VEGETATIVE WATERING | 32,886 TGL | $1.00 | $8.43 | 0.12x | -$244,465 |
GREY SKY CONSTRUCTION LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 275-7006 CEMENT TRT (EXIST MATL & NEW BASE)(6") | 64,981 SY | $6.00 | $2.25 | 2.67x | $243,997 |
| 251-7055 REWORK BS MTL (TY C)(12")(ORD COMP) | 49,398 SY | $6.00 | $2.69 | 2.23x | $163,735 |
| 496-7007 REMOV STR (PIPE) | 1,823 LF | $50.00 | $23.96 | 2.09x | $47,465 |
| 168-7001 VEGETATIVE WATERING | 32,886 TGL | $1.00 | $8.43 | 0.12x | -$244,465 |