US 67; BU 67M OVERPASS TO FM 2280
0259-06-011 · let Nov 5, 2025 · Johnson, Fort Worth · Freeway Operational Improvements
$4,249,844Low bid: ED BELL CONSTRUCTION COMPANY-16.7% vs estimate $5,101,277
$156,821Left on the table3.7% gap to the second bid
5BiddersSpread 30% low to high
172Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ED BELL CONSTRUCTION COMPANY | $4,249,844 | -16.7% | $156,821 | 1+$25,735 | 3-$357,868 | |
| 2 | JAY MILLS CONTRACTING, INCORPORATED | $4,406,665 | +3.7% | -13.6% | $344,182 | 2+$106,712 | 1-$92,191 |
| 3 | RPM XCONSTRUCTION, LLC | $4,750,847 | +11.8% | -6.9% | $108,440 | 4+$169,852 | 0 |
| 4 | GARRET SHIELDS INFRASTRUCTURE | $4,859,287 | +14.3% | -4.7% | $659,759 | 7+$506,056 | 3-$466,773 |
| 5 | GREY SKY CONSTRUCTION LLC | $5,519,046 | +29.9% | 8.2% | 6+$409,604 | 1-$67,542 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
ED BELL CONSTRUCTION COMPANY vs JAY MILLS CONTRACTING, INCORPORATED, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 512-7005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) | 2,550 LF | $10.00 | $72.00 | $40.65 | $158,100 |
| 432-7033 RIPRAP (STONE COMMON)(DRY)(18 IN) | 848 CY | $250.00 | $125.00 | $187.68 | -$106,000 |
| 100-7002 PREPARING ROW | 75 STA | $2,787.00 | $4,000.00 | $6,072.92 | $90,975 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $10,500.00 | $5,000.00 | $11,585.04 | -$77,000 |
| 344-7024 SP MIXES SP-C SAC-A PG70-28 | 2,659 TON | $165.00 | $184.80 | $156.36 | $52,648 |
| 247-7044 FL BS (CMP IN PLC)(TY A GR 1-2) (6") | 24,362 SY | $15.00 | $13.00 | $12.30 | -$48,724 |
| 500-7001 MOBILIZATION | 1 LS | $397,000.00 | $440,000.00 | $523,850.32 | $43,000 |
| 432-7001 RIPRAP (CONC)(4 IN) | 191 CY | $500.00 | $670.00 | $573.24 | $32,470 |
| 360-7005 CONC PVMT (CRCP) (11") | 2,865 SY | $136.00 | $125.00 | $94.72 | -$31,515 |
| 505-7001 TMA (STATIONARY) | 283 DAY | $100.00 | $205.00 | $217.57 | $29,715 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 3 EA | $5,000.00 | $13,200.00 | $9,253.78 | $24,600 |
| 341-7001 D-GR HMA TY-B PG64-22 | 702 TON | $133.00 | $165.00 | $97.82 | $22,464 |
| 466-7175 WINGWALL (PW - 1) (HW=5 FT) | 4 EA | $18,000.00 | $13,000.00 | $23,385.57 | -$20,000 |
| 168-7001 VEGETATIVE WATERING | 1,040 TGL | $2.10 | $21.00 | $8.43 | $19,656 |
| 432-7002 RIPRAP (CONC)(5 IN) | 105 CY | $500.00 | $670.00 | $585.15 | $17,850 |
| 496-7007 REMOV STR (PIPE) | 200 LF | $100.00 | $17.00 | $23.96 | -$16,600 |
| 512-7053 PORT CTB (REMOVE)(F-SHAPE)(TY 1) | 2,550 LF | $8.00 | $14.00 | $13.39 | $15,300 |
| 275-7018 CEMENT TRT (SUBGRADE) (8") | 10,611 SY | $2.25 | $3.50 | $4.28 | $13,264 |
| 260-7001 LIME (COM OR QK)(SLURRY) OR QK(DRY) | 400 TON | $308.00 | $340.00 | $345.77 | $12,800 |
| 506-7011 ROCK FILTER DAMS (REMOVE) | 324 LF | $52.50 | $14.30 | $12.47 | -$12,377 |
Positive: the low bidder was cheaper on that item. These 20 items account for $220,626 of the $156,821 gap.
ED BELL CONSTRUCTION COMPANY: unbalanced items
Placed 1JAY MILLS CONTRACTING, INCORPORATED: unbalanced items
Placed 2RPM XCONSTRUCTION, LLC: unbalanced items
Placed 3GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 275-7018 CEMENT TRT (SUBGRADE) (8") | 10,611 SY | $20.00 | $4.28 | 4.67x | $166,777 |
| 260-7020 LIME TRT (SUBGRADE) (8") | 13,711 SY | $10.00 | $3.93 | 2.55x | $83,287 |
| 341-7001 D-GR HMA TY-B PG64-22 | 702 TON | $200.00 | $97.82 | 2.04x | $71,727 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 2,420 CY | $40.00 | $12.93 | 3.09x | $65,520 |
| 310-7004 PRIME COAT (MC-30) | 10,452 GAL | $10.00 | $5.35 | 1.87x | $48,633 |
| 260-7021 LIME TRT (SUBGRADE) (18") | 4,554 SY | $20.00 | $11.00 | 1.82x | $40,986 |
| 105-7032 RMV (12") TRT/UNTRT BASE & ASPH PAV | 686 SY | $50.00 | $7.54 | 6.63x | $29,126 |
| 100-7002 PREPARING ROW | 75 STA | $1,000.00 | $6,072.92 | 0.16x | -$380,469 |
| 466-7175 WINGWALL (PW - 1) (HW=5 FT) | 4 EA | $8,000.00 | $23,385.57 | 0.34x | -$61,542 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 3 EA | $1,000.00 | $9,253.78 | 0.11x | -$24,761 |
GREY SKY CONSTRUCTION LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 512-7005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) | 2,550 LF | $100.00 | $40.65 | 2.46x | $151,349 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 2,420 CY | $50.00 | $12.93 | 3.87x | $89,720 |
| 260-7020 LIME TRT (SUBGRADE) (8") | 13,711 SY | $8.00 | $3.93 | 2.04x | $55,865 |
| 260-7021 LIME TRT (SUBGRADE) (18") | 4,554 SY | $20.00 | $11.00 | 1.82x | $40,986 |
| 275-7018 CEMENT TRT (SUBGRADE) (8") | 10,611 SY | $8.00 | $4.28 | 1.87x | $39,445 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 3 EA | $20,000.00 | $9,253.78 | 2.16x | $32,239 |
| 466-7175 WINGWALL (PW - 1) (HW=5 FT) | 4 EA | $6,500.00 | $23,385.57 | 0.28x | -$67,542 |