Bid Tab X-ray: 6492-96-001

Dec 10, 2025 · Aransas Sign up free
Set your company to personalize scores

6492-96-001 Mill & Fill

6492-96-001 · let Dec 10, 2025 · Aransas, Corpus Christi · Routine Maintenance Project - Sealed

$698,456Low bid: CK NEWBERRY, LLC-18.5% vs estimate $857,017
$45,518Left on the table6.5% gap to the second bid
4BiddersSpread 29% low to high
25Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1CK NEWBERRY, LLC $698,456-18.5% $45,518 1+$4,674 4-$568,956
2LCR TOTAL TRANSPORT LLC $743,974+6.5%-13.2% $133,837 2+$37,207 2-$502,605
3BAY LTD. $877,811+25.7%2.4% $20,981 4+$90,852 1-$495,351
4ANDERSON COLUMBIA CO., INC. $898,792+28.7%4.9% 2+$58,425 1-$490,850

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.

Where the job was won

CK NEWBERRY, LLC vs LCR TOTAL TRANSPORT LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
505-7001 TMA (STATIONARY)164 DAY $1.00$202.00$217.57 $32,964
354-7018 PLANE & TEXT ASPH CONC PAV(1.5")39,048 SY $0.5000$1.15$1.85 $25,381
316-7263 ASPH (MULTI OPTION)15,230 GAL $3.00$4.50$3.89 $22,845
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING3 MO $9,500.00$3,000.00$11,585.04 -$19,500
341-7050 D-GR HMA TY-D SAC-B PG70-223,220 TON $135.00$129.00$116.75 -$19,320
351-7001 FLEXIBLE PAVEMENT STRUCTURE REPAIR(2")600 SY $50.00$18.00$30.34 -$19,200
316-7209 AGGR (TY-PB, GR-3 OR 3S)(SAC-B)353 CY $135.00$180.00$88.78 $15,885
662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W2,068 EA $0.0100$1.72$1.03 $3,530
503-7001 PORTABLE CHANGEABLE MESSAGE SIGN78 DAY $1.00$44.00$87.82 $3,354
500-7001 MOBILIZATION1 LS $50,000.00$47,000.00$523,850.32 -$3,000
662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-21,262 EA $0.0100$1.74$0.5715 $2,178
662-7038 WK ZN PAV MRK NON-REMOV (Y)6"(SLD)14,472 LF $0.6000$0.6230$0.2770 $333
506-7044 BIODEG EROSN CONT LOGS (INSTL) (12")96 LF $10.00$7.00$5.23 -$288
506-7046 BIODEG EROSN CONT LOGS (REMOVE)96 LF $5.00$2.00$1.29 -$288
666-7407 REFL PAV MRK TY I (W)6"(BRK)(090MIL)3,458 LF $1.00$0.9460$0.5397 -$187
672-7006 REFL PAV MRKR TY II-C-R251 EA $7.50$8.06$4.19 $142
666-7422 REFL PAV MRK TY I (Y)6"(SLD)(090MIL)14,472 LF $0.7000$0.7090$0.5014 $130
666-7410 REFL PAV MRK TY I (W)6"(SLD)(090MIL)13,916 LF $0.7000$0.7090$0.4886 $125
668-7089 PREFAB PM TY C (W)(24")(SLD)93 LF $16.00$17.20$13.72 $112
672-7002 REFL PAV MRKR TY I-C188 EA $7.50$8.06$4.04 $106

Positive: the low bidder was cheaper on that item. These 20 items account for $45,303 of the $45,518 gap.

CK NEWBERRY, LLC: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
662-7038 WK ZN PAV MRK NON-REMOV (Y)6"(SLD)14,472 LF $0.6000$0.27702.17x$4,674
500-7001 MOBILIZATION1 LS $50,000.00$523,850.320.10x-$473,850
354-7018 PLANE & TEXT ASPH CONC PAV(1.5")39,048 SY $0.5000$1.850.27x-$52,816
505-7001 TMA (STATIONARY)164 DAY $1.00$217.570.00x-$35,518
503-7001 PORTABLE CHANGEABLE MESSAGE SIGN78 DAY $1.00$87.820.01x-$6,772

LCR TOTAL TRANSPORT LLC: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
316-7209 AGGR (TY-PB, GR-3 OR 3S)(SAC-B)353 CY $180.00$88.782.03x$32,200
662-7038 WK ZN PAV MRK NON-REMOV (Y)6"(SLD)14,472 LF $0.6230$0.27702.25x$5,007
500-7001 MOBILIZATION1 LS $47,000.00$523,850.320.09x-$476,850
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING3 MO $3,000.00$11,585.040.26x-$25,755

BAY LTD.: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
316-7209 AGGR (TY-PB, GR-3 OR 3S)(SAC-B)353 CY $210.00$88.782.37x$42,790
351-7001 FLEXIBLE PAVEMENT STRUCTURE REPAIR(2")600 SY $90.00$30.342.97x$35,794
662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W2,068 EA $4.00$1.033.89x$6,147
662-7038 WK ZN PAV MRK NON-REMOV (Y)6"(SLD)14,472 LF $0.7000$0.27702.53x$6,122
500-7001 MOBILIZATION1 LS $28,499.69$523,850.320.05x-$495,351

ANDERSON COLUMBIA CO., INC.: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
316-7209 AGGR (TY-PB, GR-3 OR 3S)(SAC-B)353 CY $239.00$88.782.69x$53,027
662-7038 WK ZN PAV MRK NON-REMOV (Y)6"(SLD)14,472 LF $0.6500$0.27702.35x$5,398