On Call Pothole-Grayson FY26
6490-64-001 · let Dec 18, 2025 · Grayson, Paris · Routine Maintenance Project - Sealed
$379,000Low bid: UMD Construction+3.4% vs estimate $366,500
$3,000Left on the table0.8% gap to the second bid
4BiddersSpread 62% low to high
3Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | UMD Construction | $379,000 | 3.4% | $3,000 | 2+$119,994 | 0 | |
| 2 | GARRET SHIELDS INFRASTRUCTURE | $382,000 | +0.8% | 4.2% | $3,012 | 0 | 0 |
| 3 | PREMIER CONTRACTORS LLC | $385,012 | +1.6% | 5.1% | $228,488 | 1+$139,375 | 1-$7,198 |
| 4 | AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC | $613,500 | +61.9% | 67.4% | 2+$318,665 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
UMD Construction vs GARRET SHIELDS INFRASTRUCTURE, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 700-7005 POTHOLE REPAIR (STANDARD) | 500 TON | $350.00 | $500.00 | $371.25 | $75,000 |
| 505-7002 TMA (MOBILE OPERATION) | 1,200 HR | $150.00 | $100.00 | $64.00 | -$60,000 |
| 500-7002 MOBILIZATION (CALLOUT) | 12 EA | $2,000.00 | $1,000.00 | $600.85 | -$12,000 |
Positive: the low bidder was cheaper on that item. These 3 items account for $3,000 of the $3,000 gap.