FY26 Buffalo Curb Repair
6488-63-001 · let Dec 9, 2025 · Leon, Bryan · Routine Maintenance Project
$79,658Low bid: CEDAR HILL SERVICES, LLC-0.9% vs estimate $80,417
$19,684Left on the table24.7% gap to the second bid
4BiddersSpread 183% low to high
12Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | CEDAR HILL SERVICES, LLC | $79,658 | -0.9% | $19,684 | 0 | 2-$509,839 | |
| 2 | STRUCTURAL INTEGRITY GROUP LLC | $99,342 | +24.7% | 23.5% | $30,698 | 2+$8,706 | 2-$519,631 |
| 3 | RARE EARTH LANDSCAPE SOLUTIONS LLC | $130,040 | +63.2% | 61.7% | $95,225 | 4+$35,589 | 2-$527,520 |
| 4 | O. TREVINO CONSTRUCTION, LLC | $225,265 | +182.8% | 180.1% | 8+$129,413 | 2-$512,020 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
CEDAR HILL SERVICES, LLC vs STRUCTURAL INTEGRITY GROUP LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $31,875.00 | $10,500.00 | $523,850.32 | -$21,375 |
| 361-7005 FULL - DEPTH REPAIR CRCP (10") | 18 CY | $210.23 | $1,300.00 | $1,202.68 | $19,616 |
| 529-7002 CONC CURB (TY II) | 348 LF | $20.20 | $44.00 | $26.45 | $8,282 |
| 505-7001 TMA (STATIONARY) | 29 DAY | $250.00 | $1.00 | $217.57 | -$7,221 |
| 465-7019 INLET (COMPL)(PCO)(4FT)(RIGHT) | 1 EA | $4,500.00 | $9,750.00 | $7,737.02 | $5,250 |
| 529-7006 CONC CURB (MONO) (TY I) | 125 LF | $20.20 | $60.00 | $13.85 | $4,975 |
| 531-7001 CONC SIDEWALKS (4") | 84 SY | $65.85 | $120.00 | $70.57 | $4,549 |
| 530-7006 DRIVEWAYS (CONC) | 15 SY | $75.25 | $305.00 | $109.20 | $3,446 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $6,500.00 | $8,000.00 | $11,585.04 | $3,000 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 16 DAY | $150.00 | $1.00 | $87.82 | -$2,384 |
| 536-7005 CONCRETE MEDIAN (NOSE) | 4 SY | $81.25 | $320.00 | $289.61 | $955 |
| 528-7003 REMOVE AND RELAY PAVERS | 5 SY | $61.75 | $180.00 | $63.66 | $591 |
Positive: the low bidder was cheaper on that item. These 12 items account for $19,684 of the $19,684 gap.
CEDAR HILL SERVICES, LLC: unbalanced items
Placed 1STRUCTURAL INTEGRITY GROUP LLC: unbalanced items
Placed 2RARE EARTH LANDSCAPE SOLUTIONS LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 529-7002 CONC CURB (TY II) | 348 LF | $80.00 | $26.45 | 3.02x | $18,635 |
| 529-7006 CONC CURB (MONO) (TY I) | 125 LF | $90.00 | $13.85 | 6.50x | $9,519 |
| 531-7001 CONC SIDEWALKS (4") | 84 SY | $125.00 | $70.57 | 1.77x | $4,572 |
| 530-7006 DRIVEWAYS (CONC) | 15 SY | $300.00 | $109.20 | 2.75x | $2,862 |
| 500-7001 MOBILIZATION | 1 LS | $12,500.00 | $523,850.32 | 0.02x | -$511,350 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $3,500.00 | $11,585.04 | 0.30x | -$16,170 |
O. TREVINO CONSTRUCTION, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 531-7001 CONC SIDEWALKS (4") | 84 SY | $600.00 | $70.57 | 8.50x | $44,472 |
| 529-7002 CONC CURB (TY II) | 348 LF | $125.00 | $26.45 | 4.73x | $34,295 |
| 465-7019 INLET (COMPL)(PCO)(4FT)(RIGHT) | 1 EA | $21,500.00 | $7,737.02 | 2.78x | $13,763 |
| 530-7006 DRIVEWAYS (CONC) | 15 SY | $900.00 | $109.20 | 8.24x | $11,862 |
| 536-7005 CONCRETE MEDIAN (NOSE) | 4 SY | $2,600.00 | $289.61 | 8.98x | $9,242 |
| 529-7006 CONC CURB (MONO) (TY I) | 125 LF | $77.00 | $13.85 | 5.56x | $7,894 |
| 505-7001 TMA (STATIONARY) | 29 DAY | $400.00 | $217.57 | 1.84x | $5,290 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 16 DAY | $250.00 | $87.82 | 2.85x | $2,595 |
| 500-7001 MOBILIZATION | 1 LS | $25,000.00 | $523,850.32 | 0.05x | -$498,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $5,000.00 | $11,585.04 | 0.43x | -$13,170 |