SH 31W, E.Med. Malakoff-Navarro CL, SC26
0163-03-053 · let Dec 2, 2025 · Henderson, Tyler · Seal Coat
$19,658,258Low bid: RONALD R. WAGNER & CO., LP+0.4% vs estimate $19,578,203
$1,227,493Left on the table6.2% gap to the second bid
4BiddersSpread 14% low to high
1,024Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | RONALD R. WAGNER & CO., LP | $19,658,258 | 0.4% | $1,227,493 | 2+$3,054,328 | 0 | |
| 2 | D. I. J. CONSTRUCTION, INC. | $20,885,751 | +6.2% | 6.7% | $1,004,245 | 3+$1,830,440 | 1-$483,269 |
| 3 | CDM HOLDINGS | $21,889,996 | +11.4% | 11.8% | $463,991 | 2+$3,506,639 | 1-$483,269 |
| 4 | CK NEWBERRY, LLC | $22,353,987 | +13.7% | 14.2% | 2+$1,506,639 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
RONALD R. WAGNER & CO., LP vs D. I. J. CONSTRUCTION, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $3,407,689.00 | $2,000,000.00 | $523,850.32 | -$1,407,689 |
| 316-7146 AGGR (TY-PD, GR-3)(SAC-A) | 17,241 CY | $165.06 | $211.00 | $160.83 | $792,052 |
| 316-7257 AGGR (TY-PD OR PL, GR-3) | 13,434 CY | $127.77 | $180.00 | $141.71 | $701,658 |
| 316-7084 ASPH (AC-20-5TR OR AC-20XP) | 8,476.25 TON | $542.07 | $600.00 | $650.02 | $491,029 |
| 666-7274 RE PROFILE PM TY I(Y)6"(BRK)(100MIL) | 922,622 LF | $0.6400 | $0.1500 | $0.6738 | -$452,085 |
| 316-7148 AGGR (TY-PD, GR-4)(SAC-A) | 8,756 CY | $161.65 | $206.00 | $145.44 | $388,329 |
| 505-7003 TMA (MOBILE OPERATION) | 125 DAY | $0.0100 | $1,940.00 | $229.60 | $242,499 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 2,243,545 LF | $0.4400 | $0.5400 | $0.4986 | $224,355 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 864,913 LF | $0.4400 | $0.5400 | $0.4757 | $86,491 |
| 666-7213 RE PM TY II (Y) 6" (SLD) | 1,911,651 LF | $0.1300 | $0.1600 | $0.1749 | $57,350 |
| 677-7030 ELIM EXT PM & MRKS (RUMBLE STRIP) | 895,182 LF | $0.2000 | $0.1400 | $0.1262 | -$53,711 |
| 666-7175 RE PM TY II (W) 6" (SLD) | 2,092,543 LF | $0.1300 | $0.1500 | $0.1701 | $41,851 |
| 672-7004 REFL PAV MRKR TY II-A-A | 80,205 EA | $4.00 | $3.50 | $3.97 | -$40,103 |
| 666-7036 REFL PAV MRK TY I (W)24"(SLD)(100MIL) | 8,609 LF | $4.00 | $8.00 | $7.19 | $34,436 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $40,000.00 | $35,000.00 | $11,585.04 | -$30,000 |
| 666-7184 RE PM TY II (W) 24" (SLD) | 14,393 LF | $4.00 | $6.00 | $3.83 | $28,786 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 73 DAY | $0.0100 | $300.00 | $87.82 | $21,899 |
| 666-7270 RE PROFILE PM TY I(Y)6"(SLD)(100MIL) | 47,957 LF | $0.6400 | $1.05 | $0.6629 | $19,662 |
| 666-7420 REFL PAV MRK TY I (Y)6"(BRK)(100MIL) | 152,468 LF | $0.4400 | $0.5500 | $0.4829 | $16,771 |
| 666-7408 REFL PAV MRK TY I (W)6"(BRK)(100MIL) | 125,052 LF | $0.4400 | $0.5500 | $0.5627 | $13,756 |
Positive: the low bidder was cheaper on that item. These 20 items account for $1,177,336 of the $1,227,493 gap.
RONALD R. WAGNER & CO., LP: unbalanced items
Placed 1D. I. J. CONSTRUCTION, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,000,000.00 | $523,850.32 | 3.82x | $1,476,150 |
| 505-7003 TMA (MOBILE OPERATION) | 125 DAY | $1,940.00 | $229.60 | 8.45x | $213,800 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $35,000.00 | $11,585.04 | 3.02x | $140,490 |
| 666-7274 RE PROFILE PM TY I(Y)6"(BRK)(100MIL) | 922,622 LF | $0.1500 | $0.6738 | 0.22x | -$483,269 |