Signal Illumination & Camera
6472-26-001 · let Dec 2, 2025 · Bell, Waco · Routine Maintenance Project - Sealed
$1,401,798Low bid: STRIPING TECHNOLOGY, L.P.-1.1% vs estimate $1,417,711
$42,123Left on the table3.0% gap to the second bid
7BiddersSpread 31% low to high
84Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | STRIPING TECHNOLOGY, L.P. | $1,401,798 | -1.1% | $42,123 | 4+$104,293 | 1-$428,850 | |
| 2 | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., LLC | $1,443,921 | +3.0% | 1.8% | $153,365 | 4+$105,745 | 2-$414,538 |
| 3 | E-Z BEL CONSTRUCTION, LLC | $1,597,286 | +13.9% | 12.7% | $45,220 | 3+$109,886 | 1-$373,850 |
| 4 | VACA UNDERGROUND UTILITIES INC | $1,642,505 | +17.2% | 15.9% | $34,785 | 9+$169,428 | 2-$448,786 |
| 5 | HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLC | $1,677,290 | +19.7% | 18.3% | $24,373 | 4+$68,988 | 1-$384,438 |
| 6 | CROSS PLUS CONSTRUCTION, LLC | $1,701,664 | +21.4% | 20.0% | $137,000 | ||
| 7 | ELECNOR BELCO ELECTRIC, INC. | $1,838,664 | +31.2% | 29.7% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
STRIPING TECHNOLOGY, L.P. vs AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 11 MO | $6,250.00 | $11,115.00 | $11,585.04 | $53,515 |
| 6008-7003 RVDS (PRESENCE AND ADVANCE DETECTION) | 33 EA | $9,488.25 | $8,000.00 | $10,685.77 | -$49,112 |
| 618-7090 CONDUIT (PREPARE) | 9,929 LF | $5.55 | $1.00 | $3.08 | -$45,177 |
| 500-7001 MOBILIZATION | 1 LS | $95,000.00 | $130,000.00 | $523,850.32 | $35,000 |
| 624-7008 GROUND BOX TY D (162922)W/APRON | 23 EA | $1,545.50 | $3,000.00 | $1,715.49 | $33,454 |
| 6013-7006 GROUND BOX (PREPARE) | 51 EA | $384.00 | $900.00 | $385.19 | $26,316 |
| 618-7061 CONDT (PVC) (SCH 80) (3") (BORE) | 890 LF | $25.25 | $52.00 | $26.77 | $23,808 |
| 416-7007 DRILL SHAFT (42 IN) | 95 LF | $988.50 | $788.00 | $318.92 | -$19,048 |
| 684-7010 TRF SIG CBL (TY A)(12 AWG)(5 CONDR) | 9,333 LF | $4.00 | $2.20 | $2.99 | -$16,799 |
| 618-7060 CONDT (PVC) (SCH 80) (3") | 1,235 LF | $13.50 | $25.00 | $18.28 | $14,203 |
| 6018-7001 CCTV FIELD EQUIP (DIGITAL) (INSTL ONLY) | 5 EA | $2,868.90 | $394.00 | $1,302.20 | -$12,375 |
| 684-7021 TRF SIG CBL (TY A)(12 AWG)(16 CONDR) | 6,615 LF | $7.50 | $5.70 | $7.57 | -$11,907 |
| 684-7008 TRF SIG CBL (TY A)(12 AWG)(3 CONDR) | 9,213 LF | $3.25 | $2.00 | $3.11 | -$11,516 |
| 628-7121 ELC SRV TY D 120/240 060(NS)AL(E)SP(O) | 5 EA | $8,655.00 | $6,443.00 | $8,107.50 | -$11,060 |
| 688-7001 PED DETECT PUSH BUTTON (APS) | 46 EA | $787.00 | $1,022.00 | $1,056.39 | $10,810 |
| 624-7013 REMOVE GROUND BOX | 16 EA | $500.00 | $1,157.00 | $377.64 | $10,512 |
| 688-7003 PED DETECTOR CONTROLLER UNIT | 6 EA | $2,875.00 | $4,310.00 | $4,184.02 | $8,610 |
| 690-7030 REMOVAL OF PEDESTRIAN PUSH BUTTONS | 46 EA | $195.50 | $31.00 | $110.70 | -$7,567 |
| 684-7012 TRF SIG CBL (TY A)(12 AWG)(7 CONDR) | 3,526 LF | $4.75 | $2.65 | $3.81 | -$7,405 |
| 6011-7017 ITS POLE MNT CAB (TY 1)(CONF 2) | 5 EA | $7,597.00 | $9,000.00 | $7,082.95 | $7,015 |
Positive: the low bidder was cheaper on that item. These 20 items account for $31,276 of the $42,123 gap.
STRIPING TECHNOLOGY, L.P.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 416-7007 DRILL SHAFT (42 IN) | 95 LF | $988.50 | $318.92 | 3.10x | $63,610 |
| 618-7090 CONDUIT (PREPARE) | 9,929 LF | $5.55 | $3.08 | 1.80x | $24,489 |
| 680-7011 INSTALL HWY TRF SIG (UPGRADE) | 1 EA | $16,391.53 | $8,031.16 | 2.04x | $8,360 |
| 6018-7001 CCTV FIELD EQUIP (DIGITAL) (INSTL ONLY) | 5 EA | $2,868.90 | $1,302.20 | 2.20x | $7,833 |
| 500-7001 MOBILIZATION | 1 LS | $95,000.00 | $523,850.32 | 0.18x | -$428,850 |
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 416-7007 DRILL SHAFT (42 IN) | 95 LF | $788.00 | $318.92 | 2.47x | $44,563 |
| 6013-7006 GROUND BOX (PREPARE) | 51 EA | $900.00 | $385.19 | 2.34x | $26,255 |
| 618-7061 CONDT (PVC) (SCH 80) (3") (BORE) | 890 LF | $52.00 | $26.77 | 1.94x | $22,457 |
| 624-7013 REMOVE GROUND BOX | 16 EA | $1,157.00 | $377.64 | 3.06x | $12,470 |
| 500-7001 MOBILIZATION | 1 LS | $130,000.00 | $523,850.32 | 0.25x | -$393,850 |
| 618-7090 CONDUIT (PREPARE) | 9,929 LF | $1.00 | $3.08 | 0.32x | -$20,688 |
E-Z BEL CONSTRUCTION, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 618-7061 CONDT (PVC) (SCH 80) (3") (BORE) | 890 LF | $88.00 | $26.77 | 3.29x | $54,497 |
| 7010-7001 MAINTENANCE SPEED LIMIT SIGNING | 7 EA | $5,000.00 | $36.55 | 136.81x | $34,744 |
| 618-7060 CONDT (PVC) (SCH 80) (3") | 1,235 LF | $35.00 | $18.28 | 1.91x | $20,645 |
| 500-7001 MOBILIZATION | 1 LS | $150,000.00 | $523,850.32 | 0.29x | -$373,850 |
VACA UNDERGROUND UTILITIES INC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 690-7009 REMOVAL OF CABLES | 38,065 LF | $2.00 | $0.8964 | 2.23x | $42,009 |
| 505-7001 TMA (STATIONARY) | 86 DAY | $500.00 | $217.57 | 2.30x | $24,289 |
| 680-7011 INSTALL HWY TRF SIG (UPGRADE) | 1 EA | $30,000.00 | $8,031.16 | 3.74x | $21,969 |
| 690-7039 REPLACE OF CONTROL CABINET(GRND MNT) | 1 EA | $25,000.00 | $6,196.97 | 4.03x | $18,803 |
| 6013-7006 GROUND BOX (PREPARE) | 51 EA | $750.00 | $385.19 | 1.95x | $18,605 |
| 6018-7001 CCTV FIELD EQUIP (DIGITAL) (INSTL ONLY) | 5 EA | $4,500.00 | $1,302.20 | 3.46x | $15,989 |
| 5061-7001 SUBSURFACE UTIL LOCATE (NON-PAVED AREA) | 6 EA | $2,500.00 | $920.62 | 2.72x | $9,476 |
| 416-7040 DRILL SHAFT (RDWY ILL POLE) (30 IN) | 40 LF | $500.00 | $270.84 | 1.85x | $9,166 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 10 DAY | $1,000.00 | $87.82 | 11.39x | $9,122 |
| 500-7001 MOBILIZATION | 1 LS | $175,000.00 | $523,850.32 | 0.33x | -$348,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 11 MO | $2,500.00 | $11,585.04 | 0.22x | -$99,935 |
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 680-7011 INSTALL HWY TRF SIG (UPGRADE) | 1 EA | $40,575.22 | $8,031.16 | 5.05x | $32,544 |
| 6013-7006 GROUND BOX (PREPARE) | 51 EA | $715.00 | $385.19 | 1.86x | $16,820 |
| 690-7030 REMOVAL OF PEDESTRIAN PUSH BUTTONS | 46 EA | $325.00 | $110.70 | 2.94x | $9,858 |
| 624-7013 REMOVE GROUND BOX | 16 EA | $988.00 | $377.64 | 2.62x | $9,766 |
| 500-7001 MOBILIZATION | 1 LS | $139,412.14 | $523,850.32 | 0.27x | -$384,438 |