IH 35 NEX South: 0017-10-292; WF.
0017-10-292 · let Dec 3, 2025 · Bexar, San Antonio · Widen Freeway
$221,480,420Low bid: WILLIAMS BROTHERS CONSTRUCTION CO., INC.-20.9% vs estimate $279,877,584
$58,214,596Left on the table26.3% gap to the second bid
6BiddersSpread 37% low to high
493Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. | $221,480,420 | -20.9% | $58,214,596 | 2+$44,780,586 | 3-$4,421,559 | |
| 2 | PULICE CONSTRUCTION, INC. | $279,695,015 | +26.3% | -0.1% | $3,600,794 | 5+$50,543,514 | 0 |
| 3 | ZACHRY CONSTRUCTION CORPORATION | $283,295,810 | +27.9% | 1.2% | $17,821,220 | 3+$56,096,164 | 0 |
| 4 | WEBBER, LLC | $301,117,030 | +36.0% | 7.6% | $1,742,970 | 4+$69,346,604 | 0 |
| 5 | AUSTIN BRIDGE & ROAD SERVICES, LP | $302,860,000 | +36.7% | 8.2% | $0 | 4+$67,587,207 | 0 |
| 5 | FLUOR HEAVY CIVIL, LLC | $302,860,000 | +36.7% | 8.2% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
WILLIAMS BROTHERS CONSTRUCTION CO., INC. vs PULICE CONSTRUCTION, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 425-7006 PRESTR CONC GIRDER (TX62) | 113,857.91 LF | $120.00 | $235.00 | $189.94 | $13,093,660 |
| 100-7002 PREPARING ROW | 186 STA | $119,000.00 | $85,250.00 | $6,072.92 | -$6,277,500 |
| 360-7007 CONC PVMT (CRCP) (13") | 74,516 SY | $50.00 | $105.00 | $97.71 | $4,098,380 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 52 MO | $15,000.00 | $93,158.36 | $11,585.04 | $4,064,235 |
| 403-7001 TEMPORARY SPL SHORING | 73,371 SF | $2.00 | $53.82 | $25.56 | $3,802,085 |
| 500-7001 MOBILIZATION | 1 LS | $24,300,000.00 | $27,969,501.53 | $523,850.32 | $3,669,502 |
| 420-7073 CL F CONC (CAP)(MASS) | 7,171.8 CY | $800.00 | $1,270.00 | $825.29 | $3,370,746 |
| 403-7003 TEMPORARY SPECIAL SHORING (SOIL NAIL) | 64,442 SF | $2.00 | $51.89 | $19.99 | $3,215,011 |
| 420-7105 CL F CONC (COLUMN)(MASS) | 9,983.7 CY | $816.10 | $1,125.00 | $897.17 | $3,083,965 |
| 442-7001 STR STEEL (PLATE GIRDER) | 9,177,400 LB | $2.00 | $2.25 | $2.35 | $2,294,350 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 32,430 LF | $5.00 | $71.91 | $52.29 | $2,169,891 |
| 432-7001 RIPRAP (CONC)(4 IN) | 11,040.1 CY | $575.00 | $390.00 | $573.24 | -$2,042,419 |
| 276-7117 CEM TRT(PLNT MX)(CL L)(TYA)(GR1-2)(6") | 77,134 SY | $14.00 | $37.76 | $20.33 | $1,832,704 |
| 132-7039 EMBANK (FNL)(OC)(TY C2)(DS) | 99,611 CY | $40.00 | $57.22 | $44.90 | $1,715,301 |
| 422-7001 REINF CONC SLAB | 1,034,880 SF | $17.00 | $18.50 | $24.45 | $1,552,320 |
| 423-7001 RETAINING WALL (MSE) | 152,370 SF | $40.00 | $50.00 | $74.07 | $1,523,700 |
| 508-7001 CONSTRUCTING DETOURS | 53,471 SY | $115.00 | $87.92 | $83.58 | -$1,447,995 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 4 EA | $50,000.00 | $382,425.84 | $136,676.66 | $1,329,703 |
| 400-7006 CUT & RESTORING PAV | 2,419 SY | $220.00 | $742.75 | $171.81 | $1,264,532 |
| 416-7008 DRILL SHAFT (48 IN) | 8,588 LF | $250.00 | $390.00 | $400.14 | $1,202,320 |
Positive: the low bidder was cheaper on that item. These 20 items account for $43,514,492 of the $58,214,596 gap.
WILLIAMS BROTHERS CONSTRUCTION CO., INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $24,300,000.00 | $523,850.32 | 46.39x | $23,776,150 |
| 100-7002 PREPARING ROW | 186 STA | $119,000.00 | $6,072.92 | 19.60x | $21,004,437 |
| 403-7001 TEMPORARY SPL SHORING | 73,371 SF | $2.00 | $25.56 | 0.08x | -$1,728,665 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 32,430 LF | $5.00 | $52.29 | 0.10x | -$1,533,576 |
| 403-7003 TEMPORARY SPECIAL SHORING (SOIL NAIL) | 64,442 SF | $2.00 | $19.99 | 0.10x | -$1,159,318 |
PULICE CONSTRUCTION, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $27,969,501.53 | $523,850.32 | 53.39x | $27,445,651 |
| 100-7002 PREPARING ROW | 186 STA | $85,250.00 | $6,072.92 | 14.04x | $14,726,937 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 52 MO | $93,158.36 | $11,585.04 | 8.04x | $4,241,813 |
| 403-7001 TEMPORARY SPL SHORING | 73,371 SF | $53.82 | $25.56 | 2.11x | $2,073,420 |
| 403-7003 TEMPORARY SPECIAL SHORING (SOIL NAIL) | 64,442 SF | $51.89 | $19.99 | 2.60x | $2,055,693 |
ZACHRY CONSTRUCTION CORPORATION: unbalanced items
Placed 3WEBBER, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $29,750,000.00 | $523,850.32 | 56.79x | $29,226,150 |
| 100-7002 PREPARING ROW | 186 STA | $142,875.12 | $6,072.92 | 23.53x | $25,445,209 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 52 MO | $195,000.00 | $11,585.04 | 16.83x | $9,537,578 |
| 420-7073 CL F CONC (CAP)(MASS) | 7,171.8 CY | $1,541.66 | $825.29 | 1.87x | $5,137,667 |
AUSTIN BRIDGE & ROAD SERVICES, LP: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $29,930,500.00 | $523,850.32 | 57.14x | $29,406,650 |
| 100-7002 PREPARING ROW | 186 STA | $163,040.32 | $6,072.92 | 26.85x | $29,195,936 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 52 MO | $147,175.87 | $11,585.04 | 12.70x | $7,050,723 |
| 403-7003 TEMPORARY SPECIAL SHORING (SOIL NAIL) | 64,442 SF | $50.00 | $19.99 | 2.50x | $1,933,898 |