SL 281, N. US 80 - US 259
2642-01-050 · let Dec 3, 2025 · Gregg, Tyler · Overlay
$12,524,243Low bid: EAST TEXAS BRIDGE, INC.+31.3% vs estimate $9,540,392
$727,023Left on the table5.8% gap to the second bid
4BiddersSpread 18% low to high
44Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | EAST TEXAS BRIDGE, INC. | $12,524,243 | 31.3% | $727,023 | 0 | 0 | |
| 2 | LONGVIEW BRIDGE AND ROAD, LTD. | $13,251,267 | +5.8% | 38.9% | $113,968 | 1+$476,150 | 0 |
| 3 | MADDEN CONTRACTING COMPANY, LLC. | $13,365,234 | +6.7% | 40.1% | $1,452,533 | 1+$1,541,326 | 0 |
| 4 | DREWERY CONSTRUCTION COMPANY, INCORPORATED | $14,817,768 | +18.3% | 55.3% | 0 | 1-$284,227 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
EAST TEXAS BRIDGE, INC. vs LONGVIEW BRIDGE AND ROAD, LTD., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $645,000.00 | $1,000,000.00 | $523,850.32 | $355,000 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 6,000 SY | $55.00 | $90.00 | $60.19 | $210,000 |
| 346-7001 STONE-MTRX-ASPH SMA-C SAC-A PG76-22 | 39,701 TON | $230.00 | $234.00 | $156.93 | $158,804 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $10,000.00 | $5,500.00 | $11,585.04 | -$40,500 |
| 354-7092 PLANE ASPH CONC PAV 2 1/4" | 331,468 SY | $2.20 | $2.30 | $2.20 | $33,147 |
| 662-7065 WK ZN PAV MRK REMOV (W)6"(BRK) | 26,412 LF | $1.50 | $0.4500 | $1.02 | -$27,733 |
| 3005-7001 MEMBRANE UNDERSEAL | 59,812 GAL | $4.50 | $4.75 | $4.76 | $14,953 |
| 344-7020 SP MIXES SP-C SAC-A PG70-22 | 4,011 TON | $179.00 | $182.00 | $137.95 | $12,033 |
| 505-7001 TMA (STATIONARY) | 127 DAY | $150.00 | $200.00 | $217.57 | $6,350 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 28 DAY | $300.00 | $150.00 | $87.82 | -$4,200 |
| 505-7003 TMA (MOBILE OPERATION) | 26 DAY | $200.00 | $360.00 | $229.60 | $4,160 |
| 344-7077 TACK COAT | 6,482 GAL | $4.50 | $4.25 | $3.25 | -$1,621 |
| 666-7024 REFL PAV MRK TY I (W)8"(SLD)(100MIL) | 30,541 LF | $1.05 | $1.10 | $0.9489 | $1,527 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 54,722 LF | $0.7000 | $0.7200 | $0.4986 | $1,094 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 50,573 LF | $0.7000 | $0.7200 | $0.4757 | $1,011 |
| 644-7004 IN SM RD SN SUP&AM TY10BWG(1)SA(T) | 72 EA | $750.00 | $760.00 | $785.93 | $720 |
| 672-7006 REFL PAV MRKR TY II-C-R | 3,096 EA | $4.55 | $4.75 | $4.19 | $619 |
| 666-7036 REFL PAV MRK TY I (W)24"(SLD)(100MIL) | 4,962 LF | $6.75 | $6.85 | $7.19 | $496 |
| 666-7408 REFL PAV MRK TY I (W)6"(BRK)(100MIL) | 24,590 LF | $0.7800 | $0.8000 | $0.5627 | $492 |
| 644-7073 REMOVE SM RD SN SUP&AM | 158 EA | $90.00 | $87.00 | $108.47 | -$474 |
Positive: the low bidder was cheaper on that item. These 20 items account for $725,880 of the $727,023 gap.
LONGVIEW BRIDGE AND ROAD, LTD.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,000,000.00 | $523,850.32 | 1.91x | $476,150 |
MADDEN CONTRACTING COMPANY, LLC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 354-7092 PLANE ASPH CONC PAV 2 1/4" | 331,468 SY | $6.85 | $2.20 | 3.11x | $1,541,326 |
DREWERY CONSTRUCTION COMPANY, INCORPORATED: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 3005-7001 MEMBRANE UNDERSEAL | 59,812 GAL | $0.0100 | $4.76 | 0.00x | -$284,227 |