FM 521 BRIDGE REPLACEMENT 2205
0847-01-016 · let Jan 6, 2026 · Matagorda, Yoakum · Bridge Replacement
$3,770,670Low bid: STX CIVIL-3.7% vs estimate $3,915,110
$311,510Left on the table8.3% gap to the second bid
7BiddersSpread 35% low to high
89Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | STX CIVIL | $3,770,670 | -3.7% | $311,510 | 5+$165,618 | 5-$597,365 | |
| 2 | E-Z BEL CONSTRUCTION, LLC | $4,082,180 | +8.3% | 4.3% | $5,982 | 2+$54,888 | 3-$269,354 |
| 3 | FORDE CONSTRUCTION COMPANY, INC. | $4,088,161 | +8.4% | 4.4% | $53,488 | 6+$268,606 | 2-$159,452 |
| 4 | TEXAS STEEL INDUSTRIAL PLACING, LLC | $4,141,649 | +9.8% | 5.8% | $255,334 | 4+$209,226 | 2-$156,102 |
| 5 | HUNTER INDUSTRIES, LTD. | $4,396,983 | +16.6% | 12.3% | $391,167 | 5+$586,960 | 4-$301,454 |
| 6 | RAGLE CONSTRUCTION, INC. | $4,788,150 | +27.0% | 22.3% | $311,223 | ||
| 7 | MC2 CIVIL, LLC | $5,099,373 | +35.2% | 30.2% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
STX CIVIL vs E-Z BEL CONSTRUCTION, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 2,194 CY | $170.00 | $226.00 | $184.74 | $122,864 |
| 500-7001 MOBILIZATION | 1 LS | $230,000.00 | $351,000.00 | $523,850.32 | $121,000 |
| 247-7196 FL BS (CMP IN PLC)(TY E GR 5)(FNAL POS) | 2,008 CY | $99.00 | $140.00 | $88.48 | $82,328 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 5,551 CY | $10.00 | $22.00 | $13.19 | $66,612 |
| 100-7002 PREPARING ROW | 19.5 STA | $360.00 | $3,400.00 | $6,072.92 | $59,280 |
| 110-7001 EXCAV (ROADWAY) | 5,291 CY | $5.00 | $16.00 | $11.68 | $58,201 |
| 316-7232 AGGR (TY-PE, GR-4)(SAC-B) | 233 CY | $350.00 | $160.00 | $111.76 | -$44,270 |
| 160-7001 FURN & PLACE TOPSOIL (3") | 24,225 SY | $3.00 | $1.20 | $4.46 | -$43,605 |
| 530-7016 DRIVEWAYS (SURF TREAT) | 707 SY | $15.00 | $74.00 | $34.56 | $41,713 |
| 422-7005 REINF CONC SLAB (BOX BEAM) | 7,659 SF | $25.00 | $20.00 | $35.96 | -$38,295 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 510 LF | $95.00 | $25.00 | $52.29 | -$35,700 |
| 420-7022 CL C CONC (CAP) | 33 CY | $2,500.00 | $1,550.00 | $1,543.38 | -$31,350 |
| 316-7194 AGGR (TY-E, GR-5)(SAC-B) | 66 CY | $550.00 | $175.00 | $156.13 | -$24,750 |
| 403-7001 TEMPORARY SPL SHORING | 387 SF | $1.00 | $60.00 | $25.56 | $22,833 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $60.00 | $265.00 | $217.57 | $20,500 |
| 425-7027 PRESTR CONC BOX BEAM (5B20) | 981 LF | $285.00 | $304.00 | $294.26 | $18,639 |
| 450-7024 RAIL (TY SSTR) | 362 LF | $160.00 | $110.00 | $69.92 | -$18,100 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $51,000.00 | $33,000.00 | $136,676.66 | -$18,000 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $2,700.00 | $735.00 | $11,585.04 | -$15,720 |
| 275-7017 CEMENT TREAT (SUBGRADE) (8") | 9,301 SY | $3.50 | $2.00 | $3.23 | -$13,952 |
Positive: the low bidder was cheaper on that item. These 20 items account for $330,229 of the $311,510 gap.
STX CIVIL: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 316-7232 AGGR (TY-PE, GR-4)(SAC-B) | 233 CY | $350.00 | $111.76 | 3.13x | $55,511 |
| 450-7024 RAIL (TY SSTR) | 362 LF | $160.00 | $69.92 | 2.29x | $32,608 |
| 341-7051 D-GR HMA TY-D PG70-22 (LEVEL-UP) | 272 TON | $230.00 | $120.73 | 1.91x | $29,721 |
| 316-7194 AGGR (TY-E, GR-5)(SAC-B) | 66 CY | $550.00 | $156.13 | 3.52x | $25,995 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 510 LF | $95.00 | $52.29 | 1.82x | $21,783 |
| 500-7001 MOBILIZATION | 1 LS | $230,000.00 | $523,850.32 | 0.44x | -$293,850 |
| 100-7002 PREPARING ROW | 19.5 STA | $360.00 | $6,072.92 | 0.06x | -$111,402 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $51,000.00 | $136,676.66 | 0.37x | -$85,677 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $2,700.00 | $11,585.04 | 0.23x | -$71,080 |
| 110-7001 EXCAV (ROADWAY) | 5,291 CY | $5.00 | $11.68 | 0.43x | -$35,356 |
E-Z BEL CONSTRUCTION, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 530-7016 DRIVEWAYS (SURF TREAT) | 707 SY | $74.00 | $34.56 | 2.14x | $27,887 |
| 341-7051 D-GR HMA TY-D PG70-22 (LEVEL-UP) | 272 TON | $220.00 | $120.73 | 1.82x | $27,001 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $33,000.00 | $136,676.66 | 0.24x | -$103,677 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $735.00 | $11,585.04 | 0.06x | -$86,800 |
| 160-7001 FURN & PLACE TOPSOIL (3") | 24,225 SY | $1.20 | $4.46 | 0.27x | -$78,877 |
FORDE CONSTRUCTION COMPANY, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 420-7012 CL C CONC (ABUT) | 37.4 CY | $3,600.00 | $1,307.98 | 2.75x | $85,722 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 5,551 CY | $28.00 | $13.19 | 2.12x | $82,200 |
| 450-7024 RAIL (TY SSTR) | 362 LF | $148.00 | $69.92 | 2.12x | $28,264 |
| 316-7232 AGGR (TY-PE, GR-4)(SAC-B) | 233 CY | $221.00 | $111.76 | 1.98x | $25,454 |
| 403-7001 TEMPORARY SPL SHORING | 387 SF | $88.00 | $25.56 | 3.44x | $24,164 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 510 LF | $97.00 | $52.29 | 1.86x | $22,803 |
| 100-7002 PREPARING ROW | 19.5 STA | $1,500.00 | $6,072.92 | 0.25x | -$89,172 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $2,800.00 | $11,585.04 | 0.24x | -$70,280 |
TEXAS STEEL INDUSTRIAL PLACING, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 316-7232 AGGR (TY-PE, GR-4)(SAC-B) | 233 CY | $400.00 | $111.76 | 3.58x | $67,161 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 5,551 CY | $25.00 | $13.19 | 1.90x | $65,547 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $30,000.00 | $9,253.78 | 3.24x | $41,492 |
| 275-7017 CEMENT TREAT (SUBGRADE) (8") | 9,301 SY | $7.00 | $3.23 | 2.16x | $35,026 |
| 100-7002 PREPARING ROW | 19.5 STA | $2,000.00 | $6,072.92 | 0.33x | -$79,422 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $2,000.00 | $11,585.04 | 0.17x | -$76,680 |
HUNTER INDUSTRIES, LTD.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 409-7002 PRESTR CONC PIL (18 IN SQ) | 2,108 LF | $368.00 | $160.33 | 2.30x | $437,769 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 5,551 CY | $23.10 | $13.19 | 1.75x | $55,000 |
| 450-7024 RAIL (TY SSTR) | 362 LF | $180.00 | $69.92 | 2.57x | $39,848 |
| 467-7328 SET (TY II) (24 IN) (RCP) (6: 1) (P) | 12 EA | $4,500.00 | $1,883.43 | 2.39x | $31,399 |
| 316-7232 AGGR (TY-PE, GR-4)(SAC-B) | 233 CY | $210.23 | $111.76 | 1.88x | $22,944 |
| 100-7002 PREPARING ROW | 19.5 STA | $1,098.98 | $6,072.92 | 0.18x | -$96,992 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $55,000.00 | $136,676.66 | 0.40x | -$81,677 |
| 160-7001 FURN & PLACE TOPSOIL (3") | 24,225 SY | $1.43 | $4.46 | 0.32x | -$73,305 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $5,400.00 | $11,585.04 | 0.47x | -$49,480 |