SH 75 AT CANEY CREEK - BR
0166-02-047 · let Jan 7, 2026 · Freestone, Bryan · Bridge Maintenance
$2,822,101Low bid: GIBSON & ASSOCIATES, INC.+8.2% vs estimate $2,607,253
$29,388Left on the table1.0% gap to the second bid
4BiddersSpread 12% low to high
207Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | GIBSON & ASSOCIATES, INC. | $2,822,101 | 8.2% | $29,388 | 8+$407,424 | 4-$449,593 | |
| 2 | RAGLE CONSTRUCTION, INC. | $2,851,489 | +1.0% | 9.4% | $236,537 | 7+$460,365 | 4-$410,443 |
| 3 | STRUCTURAL INTEGRITY GROUP LLC | $3,088,026 | +9.4% | 18.4% | $64,647 | 8+$375,515 | 0 |
| 4 | BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC | $3,152,673 | +11.7% | 20.9% | 13+$695,808 | 3-$628,282 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
GIBSON & ASSOCIATES, INC. vs RAGLE CONSTRUCTION, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 2 STA | $2,200.00 | $100,000.00 | $6,072.92 | $195,600 |
| 4010-7013 STEEL BRIDGE ZONE PAINTING | 1 LS | $132,550.00 | $81,000.00 | $126,860.25 | -$51,550 |
| 786-7002 CARBON FIBER REINF POLYMER STRENGTHNING | 454 SF | $182.00 | $75.00 | $50.56 | -$48,578 |
| 451-7004 RETROFIT RAIL (TY T221) | 228 LF | $408.00 | $200.00 | $210.47 | -$47,424 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 450 LF | $66.00 | $150.00 | $52.29 | $37,800 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 1,050 LF | $45.00 | $10.00 | $7.54 | -$36,750 |
| 677-7001 ELIM EXT PM & MRKS (4") | 39,670 LF | $0.5800 | $1.25 | $0.2643 | $26,579 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 5,802 SY | $6.00 | $1.75 | $1.43 | -$24,659 |
| 505-7001 TMA (STATIONARY) | 90 DAY | $500.00 | $250.00 | $217.57 | -$22,500 |
| 344-7020 SP MIXES SP-C SAC-A PG70-22 | 1,022 TON | $198.00 | $220.00 | $137.95 | $22,484 |
| 429-7004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 740 SF | $10.00 | $40.00 | $85.28 | $22,200 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $38,500.00 | $35,000.00 | $11,585.04 | -$21,000 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 151 CY | $627.00 | $520.00 | $616.83 | -$16,157 |
| 420-7059 CL C CONC(PILE ENCASEMENT) | 115 LF | $500.00 | $365.00 | $435.92 | -$15,525 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 293 SF | $176.00 | $125.00 | $150.68 | -$14,943 |
| 506-7021 CONSTRUCTION EXITS (INSTALL) (TY 2) | 624 SY | $22.00 | $45.00 | $26.75 | $14,352 |
| 540-7005 MTL BEAM GD FEN TRANS (THRIE-BEAM) | 12 EA | $1,677.50 | $2,750.00 | $2,218.70 | $12,870 |
| 666-7175 RE PM TY II (W) 6" (SLD) | 21,680 LF | $0.4400 | $1.00 | $0.1701 | $12,141 |
| 540-7001 MTL W-BEAM GD FEN (TIM POST) | 1,462.5 LF | $22.55 | $30.50 | $25.60 | $11,627 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 450 LF | $45.00 | $20.00 | $12.08 | -$11,250 |
Positive: the low bidder was cheaper on that item. These 20 items account for $45,317 of the $29,388 gap.
GIBSON & ASSOCIATES, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $38,500.00 | $11,585.04 | 3.32x | $161,490 |
| 786-7002 CARBON FIBER REINF POLYMER STRENGTHNING | 454 SF | $182.00 | $50.56 | 3.60x | $59,673 |
| 451-7004 RETROFIT RAIL (TY T221) | 228 LF | $408.00 | $210.47 | 1.94x | $45,036 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 1,050 LF | $45.00 | $7.54 | 5.97x | $39,338 |
| 354-7036 PLANE ASPH CONC PAV(0" TO 8") | 8,401 SY | $8.80 | $4.62 | 1.91x | $35,136 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 5,802 SY | $6.00 | $1.43 | 4.20x | $26,519 |
| 505-7001 TMA (STATIONARY) | 90 DAY | $500.00 | $217.57 | 2.30x | $25,419 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 450 LF | $45.00 | $12.08 | 3.72x | $14,812 |
| 784-7020 REP STL BRIDGE MBR (STRAIGHTEN MEMB) | 23 EA | $1,600.00 | $13,366.16 | 0.12x | -$270,622 |
| 403-7002 TEMPORARY SPL SHORING (COFFERDAM) | 3,324 SF | $1.00 | $28.47 | 0.04x | -$91,313 |
| 429-7004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 740 SF | $10.00 | $85.28 | 0.12x | -$55,710 |
| 429-7006 CONC STR REPR(RAPID DECK REP(FULL DPT)) | 310 SF | $50.00 | $153.06 | 0.33x | -$31,948 |
RAGLE CONSTRUCTION, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 2 STA | $100,000.00 | $6,072.92 | 16.47x | $187,854 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $35,000.00 | $11,585.04 | 3.02x | $140,490 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 450 LF | $150.00 | $52.29 | 2.87x | $43,970 |
| 677-7001 ELIM EXT PM & MRKS (4") | 39,670 LF | $1.25 | $0.2643 | 4.73x | $39,103 |
| 666-7175 RE PM TY II (W) 6" (SLD) | 21,680 LF | $1.00 | $0.1701 | 5.88x | $17,992 |
| 678-7002 PAV SURF PREP FOR MRK (6") | 35,780 LF | $0.5000 | $0.0662 | 7.55x | $15,521 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 1,096 LF | $30.00 | $15.92 | 1.88x | $15,435 |
| 784-7020 REP STL BRIDGE MBR (STRAIGHTEN MEMB) | 23 EA | $2,000.00 | $13,366.16 | 0.15x | -$261,422 |
| 403-7002 TEMPORARY SPL SHORING (COFFERDAM) | 3,324 SF | $1.00 | $28.47 | 0.04x | -$91,313 |
| 429-7004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 740 SF | $40.00 | $85.28 | 0.47x | -$33,510 |
| 429-7006 CONC STR REPR(RAPID DECK REP(FULL DPT)) | 310 SF | $75.00 | $153.06 | 0.49x | -$24,198 |
STRUCTURAL INTEGRITY GROUP LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 354-7036 PLANE ASPH CONC PAV(0" TO 8") | 8,401 SY | $13.25 | $4.62 | 2.87x | $72,521 |
| 786-7002 CARBON FIBER REINF POLYMER STRENGTHNING | 454 SF | $203.00 | $50.56 | 4.01x | $69,207 |
| 442-7017 MISC NON-BRIDGE (NBIS) | 224 LB | $353.00 | $47.98 | 7.36x | $68,324 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 1,096 LF | $65.00 | $15.92 | 4.08x | $53,795 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 5,802 SY | $8.75 | $1.43 | 6.12x | $42,475 |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 178 CY | $325.00 | $184.74 | 1.76x | $24,966 |
| 354-7034 PLANE ASPH CONC PAV(0" TO 4") | 2,558 SY | $14.25 | $5.12 | 2.78x | $23,347 |
| 354-7035 PLANE ASPH CONC PAV(0" TO 6") | 1,391 SY | $19.50 | $4.49 | 4.34x | $20,880 |
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 429-7004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 740 SF | $325.00 | $85.28 | 3.81x | $177,390 |
| 420-7059 CL C CONC(PILE ENCASEMENT) | 115 LF | $1,500.00 | $435.92 | 3.44x | $122,370 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 5,802 SY | $12.50 | $1.43 | 8.75x | $64,232 |
| 429-7006 CONC STR REPR(RAPID DECK REP(FULL DPT)) | 310 SF | $325.00 | $153.06 | 2.12x | $53,302 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 1,096 LF | $60.00 | $15.92 | 3.77x | $48,315 |
| 354-7036 PLANE ASPH CONC PAV(0" TO 8") | 8,401 SY | $10.00 | $4.62 | 2.17x | $45,218 |
| 786-7002 CARBON FIBER REINF POLYMER STRENGTHNING | 454 SF | $135.00 | $50.56 | 2.67x | $38,335 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 293 SF | $275.00 | $150.68 | 1.83x | $36,426 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 450 LF | $110.00 | $52.29 | 2.10x | $25,970 |
| 666-7265 RE PROFILE PM TY I(W)6"(SLD)(090MIL) | 24,840 LF | $1.60 | $0.5887 | 2.72x | $25,121 |
| 500-7001 MOBILIZATION | 1 LS | $220,000.00 | $523,850.32 | 0.42x | -$303,850 |
| 784-7020 REP STL BRIDGE MBR (STRAIGHTEN MEMB) | 23 EA | $1,500.00 | $13,366.16 | 0.11x | -$272,922 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $3,000.00 | $11,585.04 | 0.26x | -$51,510 |