FY26 - Washington Tree Removal - 01
6495-41-001 · let Jan 13, 2026 · Washington, Bryan · Routine Maintenance Project
$91,131Low bid: ORTEGA'S LAWN AND LANDSCAPING, LLC-10.7% vs estimate $102,000
$20Left on the table0.0% gap to the second bid
5BiddersSpread 39% low to high
13Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ORTEGA'S LAWN AND LANDSCAPING, LLC | $91,131 | -10.7% | $20 | 5+$46,012 | 1-$16,243 | |
| 2 | RHINO EQUITY, LLC | $91,151 | +0.0% | -10.6% | $7,578 | 1+$32,979 | 1-$8,818 |
| 3 | WASTE SOLUTIONS USA LLC | $98,729 | +8.3% | -3.2% | $9,946 | 2+$33,749 | 1-$8,818 |
| 4 | M&D CONSTRUCTION SERVICES | $108,675 | +19.3% | 6.5% | $18,136 | 3+$37,049 | 0 |
| 5 | PREMIER CONTRACTORS LLC | $126,810 | +39.2% | 24.3% | 6+$53,679 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
ORTEGA'S LAWN AND LANDSCAPING, LLC vs RHINO EQUITY, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 752-7005 TREE REMOVAL (4" - 12" DIA) | 350 EA | $120.00 | $155.00 | $60.77 | $12,250 |
| 505-7001 TMA (STATIONARY) | 75 DAY | $1.00 | $100.00 | $217.57 | $7,425 |
| 752-7006 TREE REMOVAL (12" - 18" DIA) | 100 EA | $220.00 | $150.00 | $100.44 | -$7,000 |
| 752-7008 TREE REMOVAL (24" - 30" DIA) | 15 EA | $600.00 | $140.00 | $208.61 | -$6,900 |
| 752-7007 TREE REMOVAL (18" - 24" DIA) | 30 EA | $300.00 | $140.00 | $141.37 | -$4,800 |
| 752-7009 TREE REMOVAL (30" - 36" DIA) | 10 EA | $400.00 | $140.00 | $293.05 | -$2,600 |
| 500-7002 MOBILIZATION (CALLOUT) | 3 EA | $1,500.00 | $1,000.00 | $600.85 | -$1,500 |
| 752-7004 STUMP REMOVAL | 5 EA | $1.00 | $300.00 | $157.73 | $1,495 |
| 752-7010 TREE REMOVAL (36" - 42" DIA) | 5 EA | $50.00 | $140.00 | $334.81 | $450 |
| 752-7011 TREE REMOVAL (42" - 48" DIA) | 2 EA | $50.00 | $250.00 | $436.67 | $400 |
| 752-7012 TREE REMOVAL (48" - 60" DIA) | 2 EA | $50.00 | $250.00 | $450.06 | $400 |
| 752-7013 TREE REMOVAL (60" - 72" DIA) | 2 EA | $50.00 | $250.00 | $529.99 | $400 |
| 500-7033 MOBILIZATION (EMERGENCY) | 1 EA | $1.00 | $1.00 | $844.81 | $0 |
Positive: the low bidder was cheaper on that item. These 13 items account for $20 of the $20 gap.
ORTEGA'S LAWN AND LANDSCAPING, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 752-7005 TREE REMOVAL (4" - 12" DIA) | 350 EA | $120.00 | $60.77 | 1.97x | $20,729 |
| 752-7006 TREE REMOVAL (12" - 18" DIA) | 100 EA | $220.00 | $100.44 | 2.19x | $11,956 |
| 752-7008 TREE REMOVAL (24" - 30" DIA) | 15 EA | $600.00 | $208.61 | 2.88x | $5,871 |
| 752-7007 TREE REMOVAL (18" - 24" DIA) | 30 EA | $300.00 | $141.37 | 2.12x | $4,759 |
| 500-7002 MOBILIZATION (CALLOUT) | 3 EA | $1,500.00 | $600.85 | 2.50x | $2,697 |
| 505-7001 TMA (STATIONARY) | 75 DAY | $1.00 | $217.57 | 0.00x | -$16,243 |
RHINO EQUITY, LLC: unbalanced items
Placed 2WASTE SOLUTIONS USA LLC: unbalanced items
Placed 3M&D CONSTRUCTION SERVICES: unbalanced items
Placed 4PREMIER CONTRACTORS LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 752-7009 TREE REMOVAL (30" - 36" DIA) | 10 EA | $1,500.00 | $293.05 | 5.12x | $12,070 |
| 752-7008 TREE REMOVAL (24" - 30" DIA) | 15 EA | $1,000.00 | $208.61 | 4.79x | $11,871 |
| 752-7010 TREE REMOVAL (36" - 42" DIA) | 5 EA | $2,500.00 | $334.81 | 7.47x | $10,826 |
| 752-7006 TREE REMOVAL (12" - 18" DIA) | 100 EA | $200.00 | $100.44 | 1.99x | $9,956 |
| 752-7007 TREE REMOVAL (18" - 24" DIA) | 30 EA | $300.00 | $141.37 | 2.12x | $4,759 |
| 500-7002 MOBILIZATION (CALLOUT) | 3 EA | $2,000.00 | $600.85 | 3.33x | $4,197 |