AAO MBGF
6491-63-001 · let Jan 7, 2026 · Presidio, El Paso · Routine Maintenance Project - Sealed
$1,198,026Low bid: E.V.G. ENTERPRISE-31.9% vs estimate $1,760,250
$1,333Left on the table0.1% gap to the second bid
4BiddersSpread 71% low to high
29Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | E.V.G. ENTERPRISE | $1,198,026 | -31.9% | $1,333 | 6+$614,689 | 2-$529,932 | |
| 2 | APACHE BARRICADE & SIGN | $1,199,359 | +0.1% | -31.9% | $88,291 | 6+$373,772 | 0 |
| 3 | BLACKSMITH VENTURES LLC | $1,287,650 | +7.5% | -26.8% | $766,255 | 4+$696,233 | 1-$423,850 |
| 4 | DAN WILLIAMS COMPANY | $2,053,905 | +71.4% | 16.7% | 15+$1,348,777 | 1-$323,850 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
E.V.G. ENTERPRISE vs APACHE BARRICADE & SIGN, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1.00 | $300,000.00 | $523,850.32 | $299,999 |
| 505-7001 TMA (STATIONARY) | 160 DAY | $3,000.00 | $1,300.00 | $217.57 | -$272,000 |
| 542-7001 REMOVE METAL BEAM GUARD FENCE | 3,300 LF | $1.00 | $35.00 | $2.84 | $112,200 |
| 770-7017 REPLACE SINGLE GDRAIL TERMINAL POST | 325 EA | $300.00 | $59.00 | $67.59 | -$78,325 |
| 770-7013 REM OBSOLETE GET & REPL W/ SGT | 35 EA | $5,000.00 | $3,400.00 | $2,869.78 | -$56,000 |
| 770-7006 REPLACE TIMBER POST W/O CONC FND | 220 EA | $250.00 | $49.00 | $89.82 | -$44,220 |
| 531-7001 CONC SIDEWALKS (4") | 90 SY | $98.00 | $525.00 | $70.57 | $38,430 |
| 770-7018 REPLACE BLOCKOUT | 500 EA | $100.00 | $24.00 | $44.95 | -$38,000 |
| 529-7002 CONC CURB (TY II) | 100 LF | $45.00 | $375.00 | $26.45 | $33,000 |
| 770-7007 REPLACE STEEL POST W/O CONC FND | 120 EA | $250.00 | $89.00 | $46.70 | -$19,320 |
| 770-7003 REPL RAIL ELMNT(THRIE-BM TRANS TO W-BM) | 60 EA | $30.00 | $265.00 | $65.99 | $14,100 |
| 770-7001 REPLACE RAIL ELEMENT (W-BEAM) | 2,100 LF | $25.00 | $29.00 | $22.03 | $8,400 |
| 770-7016 REPLACE SINGLE GDRAIL TERMINAL RAIL | 1,900 LF | $35.00 | $39.00 | $31.82 | $7,600 |
| 770-7027 REPAIR RAIL ELEMENT (CURVED RAIL) | 25 LF | $30.00 | $295.00 | $24.16 | $6,625 |
| 770-7010 REALIGN POSTS | 90 EA | $100.00 | $28.00 | $24.32 | -$6,480 |
| 658-7019 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) | 50 EA | $100.00 | $10.00 | $26.51 | -$4,500 |
| 770-7020 RESET SGT IMPACT HEAD | 5 EA | $1,000.00 | $190.00 | $142.42 | -$4,050 |
| 104-7016 REMOV CONC (CURB) | 100 LF | $17.00 | $49.00 | $6.82 | $3,200 |
| 542-7003 REMOVE DOWNSTREAM ANCHOR TERMINAL | 10 EA | $1.00 | $275.00 | $216.49 | $2,740 |
| 770-7024 REPLACE SGT STRUT | 20 EA | $250.00 | $125.00 | $96.41 | -$2,500 |
Positive: the low bidder was cheaper on that item. These 20 items account for $899 of the $1,333 gap.
E.V.G. ENTERPRISE: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 160 DAY | $3,000.00 | $217.57 | 13.79x | $445,189 |
| 770-7017 REPLACE SINGLE GDRAIL TERMINAL POST | 325 EA | $300.00 | $67.59 | 4.44x | $75,532 |
| 770-7006 REPLACE TIMBER POST W/O CONC FND | 220 EA | $250.00 | $89.82 | 2.78x | $35,239 |
| 770-7018 REPLACE BLOCKOUT | 500 EA | $100.00 | $44.95 | 2.22x | $27,523 |
| 770-7007 REPLACE STEEL POST W/O CONC FND | 120 EA | $250.00 | $46.70 | 5.35x | $24,396 |
| 770-7010 REALIGN POSTS | 90 EA | $100.00 | $24.32 | 4.11x | $6,811 |
| 500-7001 MOBILIZATION | 1 LS | $1.00 | $523,850.32 | 0.00x | -$523,849 |
| 542-7001 REMOVE METAL BEAM GUARD FENCE | 3,300 LF | $1.00 | $2.84 | 0.35x | -$6,082 |
APACHE BARRICADE & SIGN: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 160 DAY | $1,300.00 | $217.57 | 5.98x | $173,189 |
| 542-7001 REMOVE METAL BEAM GUARD FENCE | 3,300 LF | $35.00 | $2.84 | 12.31x | $106,118 |
| 531-7001 CONC SIDEWALKS (4") | 90 SY | $525.00 | $70.57 | 7.44x | $40,899 |
| 529-7002 CONC CURB (TY II) | 100 LF | $375.00 | $26.45 | 14.18x | $34,855 |
| 770-7003 REPL RAIL ELMNT(THRIE-BM TRANS TO W-BM) | 60 EA | $265.00 | $65.99 | 4.02x | $11,941 |
| 770-7027 REPAIR RAIL ELEMENT (CURVED RAIL) | 25 LF | $295.00 | $24.16 | 12.21x | $6,771 |
BLACKSMITH VENTURES LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 160 DAY | $4,400.00 | $217.57 | 20.22x | $669,189 |
| 531-7001 CONC SIDEWALKS (4") | 90 SY | $200.00 | $70.57 | 2.83x | $11,649 |
| 770-7003 REPL RAIL ELMNT(THRIE-BM TRANS TO W-BM) | 60 EA | $200.00 | $65.99 | 3.03x | $8,041 |
| 529-7002 CONC CURB (TY II) | 100 LF | $100.00 | $26.45 | 3.78x | $7,355 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $523,850.32 | 0.19x | -$423,850 |
DAN WILLIAMS COMPANY: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 770-7013 REM OBSOLETE GET & REPL W/ SGT | 35 EA | $12,500.00 | $2,869.78 | 4.36x | $337,058 |
| 432-7005 RIPRAP (CONC)(CL B) | 170 CY | $2,200.00 | $556.52 | 3.95x | $279,391 |
| 770-7017 REPLACE SINGLE GDRAIL TERMINAL POST | 325 EA | $725.00 | $67.59 | 10.73x | $213,657 |
| 770-7001 REPLACE RAIL ELEMENT (W-BEAM) | 2,100 LF | $65.00 | $22.03 | 2.95x | $90,242 |
| 770-7016 REPLACE SINGLE GDRAIL TERMINAL RAIL | 1,900 LF | $70.00 | $31.82 | 2.20x | $72,546 |
| 505-7001 TMA (STATIONARY) | 160 DAY | $650.00 | $217.57 | 2.99x | $69,189 |
| 770-7006 REPLACE TIMBER POST W/O CONC FND | 220 EA | $350.00 | $89.82 | 3.90x | $57,239 |
| 770-7003 REPL RAIL ELMNT(THRIE-BM TRANS TO W-BM) | 60 EA | $950.00 | $65.99 | 14.40x | $53,041 |
| 770-7007 REPLACE STEEL POST W/O CONC FND | 120 EA | $420.00 | $46.70 | 8.99x | $44,796 |
| 542-7001 REMOVE METAL BEAM GUARD FENCE | 3,300 LF | $15.00 | $2.84 | 5.28x | $40,118 |
| 500-7001 MOBILIZATION | 1 LS | $200,000.00 | $523,850.32 | 0.38x | -$323,850 |