2026 Call Out TCP Abilene Area Office
6492-45-001 · let Jan 15, 2026 · Taylor, Abilene · Routine Maintenance Project - Sealed
$324,596Low bid: BARRICADES UNLIMITED-22.5% vs estimate $418,717
$72,830Left on the table22.4% gap to the second bid
2BiddersSpread 22% low to high
10Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BARRICADES UNLIMITED | $324,596 | -22.5% | $72,830 | 1+$4,569 | 1-$523,849 | |
| 2 | AWP SAFETY | $397,426 | +22.4% | -5.1% | 2+$10,825 | 1-$523,849 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
BARRICADES UNLIMITED vs AWP SAFETY, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 790-7020 LANE CLOSURE(MAINTENANCE)(TYP 1) | 966 HR | $100.00 | $130.00 | $104.45 | $28,980 |
| 505-7002 TMA (MOBILE OPERATION) | 1,794 HR | $60.00 | $70.00 | $64.00 | $17,940 |
| 790-7021 LANE CLOSURE(MAINTENANCE)(TYP 2) | 603 HR | $70.00 | $85.00 | $78.09 | $9,045 |
| 790-7058 ADDITIONAL LANE CLOSURE ITEM(TYPE 20) | 1,082 HR | $30.00 | $35.00 | $48.40 | $5,410 |
| 790-7026 LANE CLOSURE(MAINTENANCE)(TYP 7) | 71 HR | $70.00 | $140.00 | $75.83 | $4,970 |
| 790-7059 ADDITIONAL LANE CLOSURE ITEM(TYPE 21) | 741 HR | $40.00 | $45.00 | $58.00 | $3,705 |
| 7010-7001 MAINTENANCE SPEED LIMIT SIGNING | 20 EA | $265.00 | $350.00 | $36.55 | $1,700 |
| 790-7024 LANE CLOSURE(MAINTENANCE)(TYP 5) | 63 HR | $75.00 | $85.00 | $78.14 | $630 |
| 790-7030 LANE CLOSURE(MAINTENANCE)(TYP 11) | 15 HR | $70.00 | $100.00 | $71.51 | $450 |
| 500-7001 MOBILIZATION | 1 LS | $1.00 | $1.00 | $523,850.32 | $0 |
Positive: the low bidder was cheaper on that item. These 10 items account for $72,830 of the $72,830 gap.