FY26 Brazoria Mowing (South)
6483-37-001 · let Jan 13, 2026 · Brazoria, Houston · Routine Maintenance Project - Sealed
$504,756Low bid: YELLOWSTONE LANDSCAPE - CENTRAL, INC.+10.0% vs estimate $458,746
$62,413Left on the table12.4% gap to the second bid
3BiddersSpread 57% low to high
5Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | YELLOWSTONE LANDSCAPE - CENTRAL, INC. | $504,756 | 10.0% | $62,413 | 0 | 3-$21,852 | |
| 2 | SKYLINE CONSTRUCTION PAVING & STRIPING | $567,169 | +12.4% | 23.6% | $225,233 | 0 | 1-$3,005 |
| 3 | CENTRAL NORTH CONSTRUCTION, LLC | $792,402 | +57.0% | 72.7% | 2+$67,847 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
YELLOWSTONE LANDSCAPE - CENTRAL, INC. vs SKYLINE CONSTRUCTION PAVING & STRIPING, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 730-7022 FULL - WIDTH MOWING | 11,738.372 AC | $43.00 | $46.00 | $38.53 | $35,215 |
| 730-7020 STRIP MOWING | 474 AC | $0.0100 | $46.00 | $32.12 | $21,799 |
| 730-7021 SPOT MOWING | 100 AC | $0.0100 | $46.00 | $30.27 | $4,599 |
| 500-7002 MOBILIZATION (CALLOUT) | 6 EA | $0.0100 | $100.00 | $600.85 | $600 |
| 500-7033 MOBILIZATION (EMERGENCY) | 2 EA | $0.0100 | $100.00 | $844.81 | $200 |
Positive: the low bidder was cheaper on that item. These 5 items account for $62,413 of the $62,413 gap.
YELLOWSTONE LANDSCAPE - CENTRAL, INC.: unbalanced items
Placed 1SKYLINE CONSTRUCTION PAVING & STRIPING: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 6 EA | $100.00 | $600.85 | 0.17x | -$3,005 |