Traffic Control - Brownfield
6486-69-001 · let Jan 20, 2026 · Terry, Lubbock · Routine Maintenance Project - Sealed
$320,700Low bid: AWP SAFETY-43.4% vs estimate $566,250
$115,860Left on the table36.1% gap to the second bid
2BiddersSpread 36% low to high
13Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | AWP SAFETY | $320,700 | -43.4% | $115,860 | 1+$31,925 | 3-$54,646 | |
| 2 | BARRICADES UNLIMITED | $436,560 | +36.1% | -22.9% | 2+$72,025 | 4-$62,298 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
AWP SAFETY vs BARRICADES UNLIMITED, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 505-7002 TMA (MOBILE OPERATION) | 2,000 HR | $65.00 | $95.00 | $64.00 | $60,000 |
| 505-7001 TMA (STATIONARY) | 175 DAY | $400.00 | $600.00 | $217.57 | $35,000 |
| 790-7002 LANE CLOSURE(SETUP & REM)(TYP 2) | 85 EA | $150.00 | $500.00 | $414.16 | $29,750 |
| 790-7005 LANE CLOSURE(SETUP & REM)(TYP 5) | 45 EA | $170.00 | $500.00 | $478.42 | $14,850 |
| 790-7020 LANE CLOSURE(MAINTENANCE)(TYP 1) | 400 HR | $85.00 | $50.00 | $104.45 | -$14,000 |
| 790-7001 LANE CLOSURE(SETUP & REM)(TYP 1) | 90 EA | $150.00 | $10.00 | $353.49 | -$12,600 |
| 790-7021 LANE CLOSURE(MAINTENANCE)(TYP 2) | 200 HR | $85.00 | $125.00 | $78.09 | $8,000 |
| 790-7024 LANE CLOSURE(MAINTENANCE)(TYP 5) | 200 HR | $85.00 | $50.00 | $78.14 | -$7,000 |
| 790-7059 ADDITIONAL LANE CLOSURE ITEM(TYPE 21) | 50 HR | $60.00 | $160.00 | $58.00 | $5,000 |
| 790-7018 LANE CLOSURE(SETUP & REM)(TYP 18) | 15 EA | $170.00 | $10.00 | $334.85 | -$2,400 |
| 790-7058 ADDITIONAL LANE CLOSURE ITEM(TYPE 20) | 200 HR | $40.00 | $50.00 | $48.40 | $2,000 |
| 790-7037 LANE CLOSURE(MAINTENANCE)(TYP 18) | 50 HR | $85.00 | $50.00 | $144.65 | -$1,750 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 10 DAY | $100.00 | $1.00 | $87.82 | -$990 |
Positive: the low bidder was cheaper on that item. These 13 items account for $115,860 of the $115,860 gap.
AWP SAFETY: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 175 DAY | $400.00 | $217.57 | 1.84x | $31,925 |
| 790-7002 LANE CLOSURE(SETUP & REM)(TYP 2) | 85 EA | $150.00 | $414.16 | 0.36x | -$22,454 |
| 790-7001 LANE CLOSURE(SETUP & REM)(TYP 1) | 90 EA | $150.00 | $353.49 | 0.42x | -$18,314 |
| 790-7005 LANE CLOSURE(SETUP & REM)(TYP 5) | 45 EA | $170.00 | $478.42 | 0.36x | -$13,879 |
BARRICADES UNLIMITED: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 175 DAY | $600.00 | $217.57 | 2.76x | $66,925 |
| 790-7059 ADDITIONAL LANE CLOSURE ITEM(TYPE 21) | 50 HR | $160.00 | $58.00 | 2.76x | $5,100 |
| 790-7001 LANE CLOSURE(SETUP & REM)(TYP 1) | 90 EA | $10.00 | $353.49 | 0.03x | -$30,914 |
| 790-7020 LANE CLOSURE(MAINTENANCE)(TYP 1) | 400 HR | $50.00 | $104.45 | 0.48x | -$21,778 |
| 790-7018 LANE CLOSURE(SETUP & REM)(TYP 18) | 15 EA | $10.00 | $334.85 | 0.03x | -$4,873 |
| 790-7037 LANE CLOSURE(MAINTENANCE)(TYP 18) | 50 HR | $50.00 | $144.65 | 0.35x | -$4,733 |