SH64,CR4133-SL571,HSIP2025
0245-08-054 · let Jan 6, 2026 · Rusk, Tyler · Safety Improvement Projects
$13,629,478Low bid: LONGVIEW BRIDGE AND ROAD, LTD.+1.6% vs estimate $13,420,245
$504,024Left on the table3.7% gap to the second bid
5BiddersSpread 11% low to high
141Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | LONGVIEW BRIDGE AND ROAD, LTD. | $13,629,478 | 1.6% | $504,024 | 2+$1,037,169 | 1-$81,677 | |
| 2 | PINTO CONSTRUCTION CO., INC. | $14,133,502 | +3.7% | 5.3% | $69,770 | 3+$805,624 | 2-$877,351 |
| 3 | EAST TEXAS BRIDGE, INC. | $14,203,271 | +4.2% | 5.8% | $146,095 | 3+$1,080,523 | 1-$673,230 |
| 4 | A. L. HELMCAMP, INC. | $14,349,366 | +5.3% | 6.9% | $754,343 | 10+$2,447,772 | 1-$734,070 |
| 5 | L. S. EQUIPMENT CO., INC. | $15,103,709 | +10.8% | 12.5% | 6+$2,064,131 | 1-$729,725 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
LONGVIEW BRIDGE AND ROAD, LTD. vs PINTO CONSTRUCTION CO., INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 247-7113 FL BS (CMP IN PLC)(TY A GR 1-2) (12") | 39,838 SY | $48.00 | $56.18 | $34.64 | $325,875 |
| 100-7002 PREPARING ROW | 173.83 STA | $3,500.00 | $1,850.00 | $6,072.92 | -$286,820 |
| 500-7001 MOBILIZATION | 1 LS | $1,250,000.00 | $1,000,000.00 | $523,850.32 | -$250,000 |
| 344-7019 SP MIXES SP-C PG70-22 | 12,368 TON | $160.00 | $177.68 | $142.22 | $218,666 |
| 275-7015 CEMENT TRT (SUBGRADE)(12") | 44,757 SY | $2.50 | $7.02 | $2.55 | $202,302 |
| 403-7001 TEMPORARY SPL SHORING | 7,886 SF | $65.00 | $42.00 | $25.56 | -$181,378 |
| 508-7001 CONSTRUCTING DETOURS | 2,361 SY | $82.00 | $133.37 | $83.58 | $121,285 |
| 104-7001 REMOV CONC (PAV) | 5,463 SY | $17.00 | $35.54 | $11.85 | $101,284 |
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 3,158 CY | $210.00 | $236.25 | $190.61 | $82,898 |
| 110-7001 EXCAV (ROADWAY) | 34,832 CY | $10.50 | $12.82 | $11.68 | $80,810 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $55,000.00 | $131,250.00 | $136,676.66 | $76,250 |
| 464-7003 RC PIPE (CL III)(18 IN) | 4,068 LF | $50.00 | $65.10 | $83.08 | $61,427 |
| 416-7006 DRILL SHAFT (36 IN) | 744 LF | $420.00 | $341.25 | $280.58 | -$58,590 |
| 512-7017 PORT CTB (DES SOURCE)(F-SHAPE)(TY 1) | 540 LF | $45.00 | $151.48 | $25.07 | $57,499 |
| 545-7018 CCA (INSTL)(N)(TL3)(WORK ZONE) | 2 EA | $35,500.00 | $8,206.00 | $7,875.52 | -$54,588 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 16 MO | $6,000.00 | $2,630.00 | $11,585.04 | -$53,920 |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 843 CY | $210.00 | $267.75 | $184.74 | $48,683 |
| 425-7001 PRESTR CONC GIRDER (TX28) | 794.5 LF | $300.00 | $357.00 | $217.69 | $45,287 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 111,150 SY | $2.50 | $2.10 | $1.43 | -$44,460 |
| 275-7001 CEMENT | 1,209 TON | $295.00 | $259.66 | $224.93 | -$42,726 |
Positive: the low bidder was cheaper on that item. These 20 items account for $449,783 of the $504,024 gap.
LONGVIEW BRIDGE AND ROAD, LTD.: unbalanced items
Placed 1PINTO CONSTRUCTION CO., INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,000,000.00 | $523,850.32 | 1.91x | $476,150 |
| 275-7015 CEMENT TRT (SUBGRADE)(12") | 44,757 SY | $7.02 | $2.55 | 2.75x | $200,046 |
| 104-7001 REMOV CONC (PAV) | 5,463 SY | $35.54 | $11.85 | 3.00x | $129,428 |
| 100-7002 PREPARING ROW | 173.83 STA | $1,850.00 | $6,072.92 | 0.30x | -$734,070 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 16 MO | $2,630.00 | $11,585.04 | 0.23x | -$143,281 |
EAST TEXAS BRIDGE, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,200,000.00 | $523,850.32 | 2.29x | $676,150 |
| 403-7001 TEMPORARY SPL SHORING | 7,886 SF | $65.00 | $25.56 | 2.54x | $311,019 |
| 105-7001 RMV (0"-4") TRT/UNTRT BASE & ASPH PAV | 17,239 SY | $8.00 | $2.58 | 3.10x | $93,354 |
| 100-7002 PREPARING ROW | 173.83 STA | $2,200.00 | $6,072.92 | 0.36x | -$673,230 |
A. L. HELMCAMP, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,300,000.00 | $523,850.32 | 2.48x | $776,150 |
| 110-7001 EXCAV (ROADWAY) | 34,832 CY | $24.00 | $11.68 | 2.05x | $429,054 |
| 275-7015 CEMENT TRT (SUBGRADE)(12") | 44,757 SY | $11.00 | $2.55 | 4.31x | $378,179 |
| 105-7001 RMV (0"-4") TRT/UNTRT BASE & ASPH PAV | 17,239 SY | $12.00 | $2.58 | 4.64x | $162,310 |
| 105-7013 RMV (13"-17") TRT/UNTRT BASE & ASPH PAV | 10,283 SY | $25.00 | $9.68 | 2.58x | $157,573 |
| 422-7002 REINF CONC SLAB (HPC) | 6,900 SF | $49.00 | $26.91 | 1.82x | $152,429 |
| 316-7257 AGGR (TY-PD OR PL, GR-3) | 922 CY | $280.00 | $141.71 | 1.98x | $127,508 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 301 DAY | $408.00 | $87.82 | 4.65x | $96,375 |
| 420-7013 CL C CONC (ABUT)(HPC) | 64.6 CY | $2,715.00 | $1,329.26 | 2.04x | $89,519 |
| 420-7023 CL C CONC (CAP)(HPC) | 49.8 CY | $3,000.00 | $1,420.15 | 2.11x | $78,676 |
| 100-7002 PREPARING ROW | 173.83 STA | $1,850.00 | $6,072.92 | 0.30x | -$734,070 |
L. S. EQUIPMENT CO., INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,200,000.00 | $523,850.32 | 2.29x | $676,150 |
| 403-7001 TEMPORARY SPL SHORING | 7,886 SF | $88.00 | $25.56 | 3.44x | $492,397 |
| 104-7001 REMOV CONC (PAV) | 5,463 SY | $65.00 | $11.85 | 5.49x | $290,368 |
| 508-7001 CONSTRUCTING DETOURS | 2,361 SY | $195.00 | $83.58 | 2.33x | $263,051 |
| 275-7015 CEMENT TRT (SUBGRADE)(12") | 44,757 SY | $6.50 | $2.55 | 2.55x | $176,772 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 14,626 CY | $24.50 | $13.19 | 1.86x | $165,392 |
| 100-7002 PREPARING ROW | 173.83 STA | $1,875.00 | $6,072.92 | 0.31x | -$729,725 |