FM 624 Nueces CR73 to Wildcat Add Lanes.
0989-02-057 · let Jan 6, 2026 · Nueces, Corpus Christi · Widen Non-Freeway
$30,814,865Low bid: J E CONSTRUCTION SERVICES, LLC-14.3% vs estimate $35,976,367
$5,439,773Left on the table17.7% gap to the second bid
4BiddersSpread 24% low to high
279Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | J E CONSTRUCTION SERVICES, LLC | $30,814,865 | -14.3% | $5,439,773 | 2+$2,435,626 | 6-$2,860,605 | |
| 2 | ANDERSON COLUMBIA CO., INC. | $36,254,638 | +17.7% | 0.8% | $130,568 | 3+$2,395,091 | 2-$1,078,918 |
| 3 | BAY LTD. | $36,385,206 | +18.1% | 1.1% | $1,741,159 | 4+$3,360,009 | 2-$1,042,994 |
| 4 | J. CARROLL WEAVER, INC. | $38,126,365 | +23.7% | 6.0% | 6+$3,813,415 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
J E CONSTRUCTION SERVICES, LLC vs ANDERSON COLUMBIA CO., INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 141 STA | $9,004.00 | $426.00 | $6,072.92 | -$1,209,498 |
| 400-7010 CEM STABIL BKFL | 16,675 CY | $52.00 | $110.00 | $138.14 | $967,150 |
| 423-7015 RETAINING WALL (SPREAD FOOTING) | 10,739 SF | $73.00 | $160.10 | $107.44 | $935,367 |
| 536-7002 CONC MEDIAN | 14,672 SY | $90.00 | $129.00 | $92.13 | $572,208 |
| 462-7015 CONC BOX CULV (7 FT X 3 FT) | 2,019 LF | $595.00 | $861.00 | $699.36 | $537,054 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 44 MO | $4,700.00 | $15,100.00 | $11,585.04 | $457,600 |
| 681-7001 TEMP TRAF SIGNALS | 7 EA | $15,000.00 | $72,100.00 | $62,461.14 | $399,700 |
| 462-7011 CONC BOX CULV (6 FT X 3 FT) | 1,232 LF | $495.00 | $718.99 | $511.04 | $275,956 |
| 6008-7003 RVDS (PRESENCE AND ADVANCE DETECTION) | 30 EA | $940.00 | $9,240.00 | $10,685.77 | $249,000 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 11,060 LF | $40.00 | $18.00 | $43.56 | -$243,320 |
| 531-7001 CONC SIDEWALKS (4") | 22,358 SY | $55.00 | $65.00 | $70.57 | $223,580 |
| 474-7022 PRE-CAST TRENCH DRAIN (IN CONC PAVEMNT) | 1,007 LF | $250.00 | $454.00 | $257.06 | $205,428 |
| 500-7001 MOBILIZATION | 1 LS | $2,675,200.00 | $2,475,000.00 | $523,850.32 | -$200,200 |
| 464-7011 RC PIPE (CL III)(48 IN) | 1,950 LF | $219.00 | $321.00 | $255.07 | $198,900 |
| 530-7006 DRIVEWAYS (CONC) | 13,319 SY | $82.00 | $96.00 | $109.20 | $186,466 |
| 341-7045 D-GR HMA TY-D SAC-B PG64-22 | 13,727 TON | $117.00 | $130.00 | $130.08 | $178,451 |
| 462-7007 CONC BOX CULV (5 FT X 3 FT) | 958 LF | $410.00 | $593.00 | $428.08 | $175,314 |
| 341-7002 D-GR HMA TY-B SAC-B PG64-22 | 15,670 TON | $129.00 | $118.00 | $109.80 | -$172,370 |
| 247-7113 FL BS (CMP IN PLC)(TY A GR 1-2) (12") | 34,429 SY | $39.00 | $34.00 | $34.64 | -$172,145 |
| 465-7308 INLET (COMPL)(CURB)(TY C)(BOTH)(HOU) | 38 EA | $5,200.00 | $9,700.00 | $5,200.00 | $171,000 |
Positive: the low bidder was cheaper on that item. These 20 items account for $3,735,641 of the $5,439,773 gap.
J E CONSTRUCTION SERVICES, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,675,200.00 | $523,850.32 | 5.11x | $2,151,350 |
| 3006-7001 UNDERSEAL COURSE | 38,655 GAL | $11.00 | $3.65 | 3.02x | $284,277 |
| 400-7010 CEM STABIL BKFL | 16,675 CY | $52.00 | $138.14 | 0.38x | -$1,436,446 |
| 681-7001 TEMP TRAF SIGNALS | 7 EA | $15,000.00 | $62,461.14 | 0.24x | -$332,228 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 34,518 CY | $4.00 | $13.19 | 0.30x | -$317,286 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 44 MO | $4,700.00 | $11,585.04 | 0.41x | -$302,942 |
| 6008-7003 RVDS (PRESENCE AND ADVANCE DETECTION) | 30 EA | $940.00 | $10,685.77 | 0.09x | -$292,373 |
| 104-7011 REMOV CONC (DRIVEWAYS) | 14,118 SY | $7.00 | $19.70 | 0.36x | -$179,330 |
ANDERSON COLUMBIA CO., INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,475,000.00 | $523,850.32 | 4.72x | $1,951,150 |
| 3006-7001 UNDERSEAL COURSE | 38,655 GAL | $10.00 | $3.65 | 2.74x | $245,622 |
| 474-7022 PRE-CAST TRENCH DRAIN (IN CONC PAVEMNT) | 1,007 LF | $454.00 | $257.06 | 1.77x | $198,320 |
| 100-7002 PREPARING ROW | 141 STA | $426.00 | $6,072.92 | 0.07x | -$796,216 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 11,060 LF | $18.00 | $43.56 | 0.41x | -$282,702 |
BAY LTD.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,893,000.00 | $523,850.32 | 5.52x | $2,369,150 |
| 512-7033 PORT CTB (MOVE)(LOW PROF)(TY 1) | 42,270 LF | $17.00 | $8.08 | 2.10x | $376,943 |
| 260-7020 LIME TRT (SUBGRADE) (8") | 34,429 SY | $13.50 | $3.93 | 3.44x | $329,640 |
| 3006-7001 UNDERSEAL COURSE | 38,655 GAL | $11.00 | $3.65 | 3.02x | $284,277 |
| 100-7002 PREPARING ROW | 141 STA | $720.00 | $6,072.92 | 0.12x | -$754,762 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 11,060 LF | $17.50 | $43.56 | 0.40x | -$288,232 |
J. CARROLL WEAVER, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,412,949.34 | $523,850.32 | 4.61x | $1,889,099 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 11,060 LF | $84.10 | $43.56 | 1.93x | $448,364 |
| 681-7001 TEMP TRAF SIGNALS | 7 EA | $123,210.00 | $62,461.14 | 1.97x | $425,242 |
| 105-7019 RMV (19"-23") TRT/UNTRT BASE & ASPH PAV | 19,109 SY | $27.48 | $6.35 | 4.33x | $403,804 |
| 110-7001 EXCAV (ROADWAY) | 25,115 CY | $26.91 | $11.68 | 2.30x | $382,446 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 53,097 SY | $6.41 | $1.43 | 4.48x | $264,460 |