WIDEN FM 600 FROM US 380 TO FM 618
0985-02-011 · let Jan 6, 2026 · Haskell, Abilene · Widen Non-Freeway
$5,128,777Low bid: ZACK BURKETT CO.-6.5% vs estimate $5,488,052
$347,137Left on the table6.8% gap to the second bid
4BiddersSpread 21% low to high
56Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ZACK BURKETT CO. | $5,128,777 | -6.5% | $347,137 | 2+$172,329 | 1-$49,802 | |
| 2 | J. H. STRAIN & SONS, INC. | $5,475,914 | +6.8% | -0.2% | $622,624 | 1+$38,439 | 1-$323,850 |
| 3 | CK NEWBERRY, LLC | $6,098,537 | +18.9% | 11.1% | $104,137 | 0 | 2-$122,367 |
| 4 | A. L. HELMCAMP, INC. | $6,202,675 | +20.9% | 13.0% | 5+$385,907 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
ZACK BURKETT CO. vs J. H. STRAIN & SONS, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 344-7051 SP MIXES SP-D PG70-22 | 12,349 TON | $116.00 | $153.75 | $139.43 | $466,175 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 5,000 CY | $44.00 | $14.00 | $16.96 | -$150,000 |
| 500-7001 MOBILIZATION | 1 LS | $350,000.00 | $200,000.00 | $523,850.32 | -$150,000 |
| 341-7001 D-GR HMA TY-B PG64-22 | 7,051 TON | $109.50 | $124.02 | $97.82 | $102,381 |
| 530-7015 DRIVEWAYS (BASE) | 5,570 SY | $32.50 | $18.00 | $27.85 | -$80,765 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 13 MO | $6,800.00 | $12,000.00 | $11,585.04 | $67,600 |
| 510-7003 ONE-WAY TRAF CONT (PORT TRAF SIG) | 10 MO | $0.0100 | $5,500.00 | $4,980.23 | $55,000 |
| 260-7001 LIME (COM OR QK)(SLURRY) OR QK(DRY) | 1,301 TON | $351.00 | $390.00 | $345.77 | $50,739 |
| 530-7006 DRIVEWAYS (CONC) | 402 SY | $201.60 | $115.00 | $109.20 | -$34,813 |
| 134-7002 BACKFILL (TY B) | 466 STA | $185.00 | $250.00 | $206.94 | $30,290 |
| 105-7058 RMV (7"-13") TRT/UNTRT BASE & ASPH PAV | 5,184 SY | $7.50 | $13.25 | $5.84 | $29,808 |
| 505-7003 TMA (MOBILE OPERATION) | 90 DAY | $0.0100 | $250.00 | $229.60 | $22,499 |
| 662-7068 WK ZN PAV MRK REMOV (W)6"(SLD) | 91,560 LF | $0.6200 | $0.4300 | $0.8015 | -$17,396 |
| 310-7004 PRIME COAT (MC-30) | 11,286 GAL | $4.60 | $5.75 | $5.35 | $12,979 |
| 104-7011 REMOV CONC (DRIVEWAYS) | 402 SY | $56.00 | $25.00 | $19.70 | -$12,462 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 91,467 LF | $0.6900 | $0.5600 | $0.4757 | -$11,891 |
| 401-7001 FLOWABLE BACKFILL | 107 CY | $336.00 | $235.00 | $298.77 | -$10,807 |
| 260-7008 LIME TRT (EXIST MATL)(10") | 53,430 SY | $8.70 | $8.50 | $5.92 | -$10,686 |
| 112-7001 SUBGR WIDEN (OC) | 466 STA | $330.00 | $350.00 | $458.34 | $9,320 |
| 644-7001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) | 51 EA | $952.00 | $785.00 | $696.14 | -$8,517 |
Positive: the low bidder was cheaper on that item. These 20 items account for $359,453 of the $347,137 gap.
ZACK BURKETT CO.: unbalanced items
Placed 1J. H. STRAIN & SONS, INC.: unbalanced items
Placed 2CK NEWBERRY, LLC: unbalanced items
Placed 3A. L. HELMCAMP, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 530-7015 DRIVEWAYS (BASE) | 5,570 SY | $50.00 | $27.85 | 1.80x | $123,391 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 5,000 CY | $35.00 | $16.96 | 2.06x | $90,184 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 2,000 SY | $75.00 | $35.01 | 2.14x | $79,970 |
| 310-7004 PRIME COAT (MC-30) | 11,286 GAL | $10.00 | $5.35 | 1.87x | $52,514 |
| 496-7007 REMOV STR (PIPE) | 240 LF | $190.00 | $23.96 | 7.93x | $39,849 |