DW Spalling and Concrete Repairs 2609
0913-00-128 · let Feb 4, 2026 · De Witt, Yoakum · Bridge Maintenance
$2,343,182Low bid: BK FIELD OPERATIONS LLC+0.9% vs estimate $2,323,208
$72,273Left on the table3.1% gap to the second bid
12BiddersSpread 50% low to high
46Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BK FIELD OPERATIONS LLC | $2,343,182 | 0.9% | $72,273 | 7+$593,011 | 5-$703,583 | |
| 2 | RAGLE CONSTRUCTION, INC. | $2,415,455 | +3.1% | 4.0% | $131,785 | 8+$709,385 | 9-$634,296 |
| 3 | GARRET SHIELDS INFRASTRUCTURE | $2,547,240 | +8.7% | 9.6% | $55,710 | 6+$519,681 | 5-$456,599 |
| 4 | BLACKSMITH VENTURES LLC | $2,602,950 | +11.1% | 12.0% | $41,561 | 9+$614,105 | 5-$431,699 |
| 5 | ROY JORGENSEN ASSOCIATES, INC. | $2,644,511 | +12.9% | 13.8% | $101,454 | 7+$761,604 | 4-$503,713 |
| 6 | RELMCO, INC. | $2,745,965 | +17.2% | 18.2% | $102,312 | ||
| 7 | CEKRA INC. | $2,848,278 | +21.6% | 22.6% | $241,086 | ||
| 8 | SCR CIVIL CONSTRUCTION, LLC | $3,089,364 | +31.8% | 33.0% | $7,254 | ||
| 9 | STRUCTURAL INTEGRITY GROUP LLC | $3,096,618 | +32.2% | 33.3% | $137,766 | ||
| 10 | MB WESTERN INDUSTRIAL CONTRACTING CO. | $3,234,384 | +38.0% | 39.2% | $211,901 | ||
| 11 | BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC | $3,446,285 | +47.1% | 48.3% | $58,115 | ||
| 12 | OLYMPUS PAINTING CONTRACTORS, INC. | $3,504,400 | +49.6% | 50.8% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
BK FIELD OPERATIONS LLC vs RAGLE CONSTRUCTION, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 17 MO | $1.00 | $10,000.00 | $11,585.04 | $169,983 |
| 500-7001 MOBILIZATION | 1 LS | $125,000.00 | $240,000.00 | $523,850.32 | $115,000 |
| 787-7001 REPLACING ELASTOMERIC BEARING PADS | 13 EA | $2,500.00 | $7,500.00 | $2,783.49 | $65,000 |
| 4010-7017 STEEL BRIDGE ZONE PAINTING REF STR #15 | 1 EA | $147,375.00 | $100,000.00 | $54,343.75 | -$47,375 |
| 505-7003 TMA (MOBILE OPERATION) | 10 DAY | $1.00 | $4,500.00 | $229.60 | $44,990 |
| 4010-7008 STEEL BRIDGE ZONE PAINTING REF STR #7 | 1 EA | $63,000.00 | $20,000.00 | $55,416.98 | -$43,000 |
| 446-7002 CLEAN & PAINT EXIST STR (SYSTEM II) | 1 LS | $607,050.00 | $650,000.00 | $301,243.48 | $42,950 |
| 4010-7018 STEEL BRIDGE ZONE PAINTING REF STR #16 | 1 EA | $191,250.00 | $150,000.00 | $115,625.00 | -$41,250 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 1 EA | $10,000.00 | $50,000.00 | $9,253.78 | $40,000 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 1,680 LF | $40.00 | $17.00 | $12.08 | -$38,640 |
| 4010-7024 STEEL BRIDGE ZONE PAINTING REF STR #21 | 1 EA | $60,000.00 | $25,000.00 | $35,000.00 | -$35,000 |
| 4010-7025 STEEL BRIDGE ZONE PAINTING REF STR #22 | 1 EA | $60,000.00 | $25,000.00 | $35,000.00 | -$35,000 |
| 4010-7026 STEEL BRIDGE ZONE PAINTING REF STR #23 | 1 EA | $60,000.00 | $25,000.00 | $60,000.00 | -$35,000 |
| 4010-7027 STEEL BRIDGE ZONE PAINTING REF STR #24 | 1 EA | $60,000.00 | $25,000.00 | $60,000.00 | -$35,000 |
| 4010-7003 STEEL BRIDGE ZONE PAINTING REF STR #2 | 1 EA | $67,700.00 | $40,000.00 | $46,198.86 | -$27,700 |
| 449-7001 ANCHOR BOLTS | 32 EA | $950.00 | $135.00 | $1,198.19 | -$26,080 |
| 786-7001 CARBON FIBER REINF POLYMER PROTECTION | 300 SF | $40.00 | $125.00 | $72.02 | $25,500 |
| 780-7004 CNC CRACK REPAIR (DISCRETE)(SURF SEAL) | 400 LF | $20.00 | $80.00 | $49.91 | $24,000 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 1,680 LF | $80.00 | $66.00 | $52.29 | -$23,520 |
| 446-7008 CLEAN & PAINT EXIST PILING (SYSTEM II) | 1 LS | $180,000.00 | $200,000.00 | $88,566.67 | $20,000 |
Positive: the low bidder was cheaper on that item. These 20 items account for $159,858 of the $72,273 gap.
BK FIELD OPERATIONS LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 446-7002 CLEAN & PAINT EXIST STR (SYSTEM II) | 1 LS | $607,050.00 | $301,243.48 | 2.02x | $305,807 |
| 4010-7017 STEEL BRIDGE ZONE PAINTING REF STR #15 | 1 EA | $147,375.00 | $54,343.75 | 2.71x | $93,031 |
| 446-7008 CLEAN & PAINT EXIST PILING (SYSTEM II) | 1 LS | $180,000.00 | $88,566.67 | 2.03x | $91,433 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 1,680 LF | $40.00 | $12.08 | 3.31x | $46,900 |
| 505-7001 TMA (STATIONARY) | 10 DAY | $3,000.00 | $217.57 | 13.79x | $27,824 |
| 4010-7005 STEEL BRIDGE ZONE PAINTING REF STR #4 | 1 EA | $20,000.00 | $4,906.91 | 4.08x | $15,093 |
| 422-7020 SHEAR KEY | 5.5 CY | $3,000.00 | $650.48 | 4.61x | $12,922 |
| 500-7001 MOBILIZATION | 1 LS | $125,000.00 | $523,850.32 | 0.24x | -$398,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 17 MO | $1.00 | $11,585.04 | 0.00x | -$196,929 |
| 4010-7001 STEEL BRIDGE ZONE PAINTING REF STR #1 | 1 EA | $20,000.00 | $70,292.48 | 0.28x | -$50,292 |
| 4010-7004 STEEL BRIDGE ZONE PAINTING REF STR #3 | 1 EA | $20,000.00 | $65,547.71 | 0.31x | -$45,548 |
| 780-7004 CNC CRACK REPAIR (DISCRETE)(SURF SEAL) | 400 LF | $20.00 | $49.91 | 0.40x | -$11,964 |
RAGLE CONSTRUCTION, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 446-7002 CLEAN & PAINT EXIST STR (SYSTEM II) | 1 LS | $650,000.00 | $301,243.48 | 2.16x | $348,757 |
| 446-7008 CLEAN & PAINT EXIST PILING (SYSTEM II) | 1 LS | $200,000.00 | $88,566.67 | 2.26x | $111,433 |
| 787-7001 REPLACING ELASTOMERIC BEARING PADS | 13 EA | $7,500.00 | $2,783.49 | 2.69x | $61,315 |
| 4010-7017 STEEL BRIDGE ZONE PAINTING REF STR #15 | 1 EA | $100,000.00 | $54,343.75 | 1.84x | $45,656 |
| 505-7001 TMA (STATIONARY) | 10 DAY | $4,500.00 | $217.57 | 20.68x | $42,824 |
| 505-7003 TMA (MOBILE OPERATION) | 10 DAY | $4,500.00 | $229.60 | 19.60x | $42,704 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 1 EA | $50,000.00 | $9,253.78 | 5.40x | $40,746 |
| 442-7014 STR STEEL (SHEAR ANCHOR) | 555 LB | $35.00 | $6.26 | 5.59x | $15,950 |
| 500-7001 MOBILIZATION | 1 LS | $240,000.00 | $523,850.32 | 0.46x | -$283,850 |
| 4010-7001 STEEL BRIDGE ZONE PAINTING REF STR #1 | 1 EA | $5,000.00 | $70,292.48 | 0.07x | -$65,292 |
| 4010-7004 STEEL BRIDGE ZONE PAINTING REF STR #3 | 1 EA | $2,500.00 | $65,547.71 | 0.04x | -$63,048 |
| 4010-7015 STEEL BRIDGE ZONE PAINTING REF STR #13 | 1 EA | $18,000.00 | $69,666.67 | 0.26x | -$51,667 |
| 4010-7008 STEEL BRIDGE ZONE PAINTING REF STR #7 | 1 EA | $20,000.00 | $55,416.98 | 0.36x | -$35,417 |
| 4010-7026 STEEL BRIDGE ZONE PAINTING REF STR #23 | 1 EA | $25,000.00 | $60,000.00 | 0.42x | -$35,000 |
| 4010-7027 STEEL BRIDGE ZONE PAINTING REF STR #24 | 1 EA | $25,000.00 | $60,000.00 | 0.42x | -$35,000 |
| 449-7001 ANCHOR BOLTS | 32 EA | $135.00 | $1,198.19 | 0.11x | -$34,022 |
| 4010-7014 STEEL BRIDGE ZONE PAINTING REF STR #12 | 1 EA | $18,000.00 | $49,000.00 | 0.37x | -$31,000 |
GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 446-7002 CLEAN & PAINT EXIST STR (SYSTEM II) | 1 LS | $630,000.00 | $301,243.48 | 2.09x | $328,757 |
| 4010-7017 STEEL BRIDGE ZONE PAINTING REF STR #15 | 1 EA | $155,000.00 | $54,343.75 | 2.85x | $100,656 |
| 4010-7024 STEEL BRIDGE ZONE PAINTING REF STR #21 | 1 EA | $65,000.00 | $35,000.00 | 1.86x | $30,000 |
| 4010-7025 STEEL BRIDGE ZONE PAINTING REF STR #22 | 1 EA | $65,000.00 | $35,000.00 | 1.86x | $30,000 |
| 4010-7005 STEEL BRIDGE ZONE PAINTING REF STR #4 | 1 EA | $22,000.00 | $4,906.91 | 4.48x | $17,093 |
| 442-7014 STR STEEL (SHEAR ANCHOR) | 555 LB | $30.00 | $6.26 | 4.79x | $13,175 |
| 500-7001 MOBILIZATION | 1 LS | $250,000.00 | $523,850.32 | 0.48x | -$273,850 |
| 446-7008 CLEAN & PAINT EXIST PILING (SYSTEM II) | 1 LS | $20,000.00 | $88,566.67 | 0.23x | -$68,567 |
| 4010-7001 STEEL BRIDGE ZONE PAINTING REF STR #1 | 1 EA | $22,000.00 | $70,292.48 | 0.31x | -$48,292 |
| 4010-7004 STEEL BRIDGE ZONE PAINTING REF STR #3 | 1 EA | $22,000.00 | $65,547.71 | 0.34x | -$43,548 |
| 449-7001 ANCHOR BOLTS | 32 EA | $500.00 | $1,198.19 | 0.42x | -$22,342 |
BLACKSMITH VENTURES LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 446-7002 CLEAN & PAINT EXIST STR (SYSTEM II) | 1 LS | $560,000.00 | $301,243.48 | 1.86x | $258,757 |
| 787-7001 REPLACING ELASTOMERIC BEARING PADS | 13 EA | $11,000.00 | $2,783.49 | 3.95x | $106,815 |
| 446-7008 CLEAN & PAINT EXIST PILING (SYSTEM II) | 1 LS | $175,000.00 | $88,566.67 | 1.98x | $86,433 |
| 4010-7017 STEEL BRIDGE ZONE PAINTING REF STR #15 | 1 EA | $110,000.00 | $54,343.75 | 2.02x | $55,656 |
| 545-7014 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) | 2 EA | $24,000.00 | $8,780.51 | 2.73x | $30,439 |
| 442-7014 STR STEEL (SHEAR ANCHOR) | 555 LB | $50.00 | $6.26 | 7.99x | $24,275 |
| 505-7001 TMA (STATIONARY) | 10 DAY | $2,500.00 | $217.57 | 11.49x | $22,824 |
| 4010-7005 STEEL BRIDGE ZONE PAINTING REF STR #4 | 1 EA | $20,000.00 | $4,906.91 | 4.08x | $15,093 |
| 784-7022 REP STL BRIDGE MBR (WELD REPAIR) | 3 EA | $8,000.00 | $3,395.64 | 2.36x | $13,813 |
| 500-7001 MOBILIZATION | 1 LS | $250,000.00 | $523,850.32 | 0.48x | -$273,850 |
| 4010-7001 STEEL BRIDGE ZONE PAINTING REF STR #1 | 1 EA | $20,000.00 | $70,292.48 | 0.28x | -$50,292 |
| 4010-7004 STEEL BRIDGE ZONE PAINTING REF STR #3 | 1 EA | $20,000.00 | $65,547.71 | 0.31x | -$45,548 |
| 4010-7015 STEEL BRIDGE ZONE PAINTING REF STR #13 | 1 EA | $30,000.00 | $69,666.67 | 0.43x | -$39,667 |
| 449-7001 ANCHOR BOLTS | 32 EA | $500.00 | $1,198.19 | 0.42x | -$22,342 |
ROY JORGENSEN ASSOCIATES, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 446-7002 CLEAN & PAINT EXIST STR (SYSTEM II) | 1 LS | $698,107.50 | $301,243.48 | 2.32x | $396,864 |
| 446-7008 CLEAN & PAINT EXIST PILING (SYSTEM II) | 1 LS | $189,000.00 | $88,566.67 | 2.13x | $100,433 |
| 4010-7017 STEEL BRIDGE ZONE PAINTING REF STR #15 | 1 EA | $154,743.00 | $54,343.75 | 2.85x | $100,399 |
| 787-7001 REPLACING ELASTOMERIC BEARING PADS | 13 EA | $8,000.00 | $2,783.49 | 2.87x | $67,815 |
| 4010-7024 STEEL BRIDGE ZONE PAINTING REF STR #21 | 1 EA | $69,000.00 | $35,000.00 | 1.97x | $34,000 |
| 4010-7025 STEEL BRIDGE ZONE PAINTING REF STR #22 | 1 EA | $69,000.00 | $35,000.00 | 1.97x | $34,000 |
| 4010-7005 STEEL BRIDGE ZONE PAINTING REF STR #4 | 1 EA | $33,000.00 | $4,906.91 | 6.73x | $28,093 |
| 500-7001 MOBILIZATION | 1 LS | $150,000.00 | $523,850.32 | 0.29x | -$373,850 |
| 4010-7001 STEEL BRIDGE ZONE PAINTING REF STR #1 | 1 EA | $21,000.00 | $70,292.48 | 0.30x | -$49,292 |
| 4010-7004 STEEL BRIDGE ZONE PAINTING REF STR #3 | 1 EA | $23,000.00 | $65,547.71 | 0.35x | -$42,548 |
| 449-7001 ANCHOR BOLTS | 32 EA | $10.00 | $1,198.19 | 0.01x | -$38,022 |