US 67 at Pecan Bayou
0054-07-094 · let Feb 5, 2026 · Brown, Brownwood · Bridge Maintenance
$3,023,121Low bid: STRUCTURAL INTEGRITY GROUP LLC-5.3% vs estimate $3,190,794
$121,985Left on the table4.0% gap to the second bid
9BiddersSpread 73% low to high
225Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | STRUCTURAL INTEGRITY GROUP LLC | $3,023,121 | -5.3% | $121,985 | 5+$227,516 | 1-$36,294 | |
| 2 | SCOTT TUCKER CONSTRUCTION COMPANY, LLC | $3,145,106 | +4.0% | -1.4% | $78,117 | 8+$246,770 | 2-$402,773 |
| 3 | THE TRUESDELL CORPORATION | $3,223,223 | +6.6% | 1.0% | $6,496 | 5+$246,514 | 2-$384,530 |
| 4 | GIBSON & ASSOCIATES, INC. | $3,229,719 | +6.8% | 1.2% | $136,685 | 7+$378,103 | 0 |
| 5 | GARRET SHIELDS INFRASTRUCTURE | $3,366,404 | +11.4% | 5.5% | $13,595 | 8+$910,813 | 3-$676,360 |
| 6 | MPB, INC. | $3,379,998 | +11.8% | 5.9% | $32,936 | ||
| 7 | BLACKSMITH VENTURES LLC | $3,412,934 | +12.9% | 7.0% | $778,310 | ||
| 8 | TI-ZACK CONCRETE, LLC | $4,191,244 | +38.6% | 31.4% | $1,041,487 | ||
| 9 | BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC | $5,232,730 | +73.1% | 64.0% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
STRUCTURAL INTEGRITY GROUP LLC vs SCOTT TUCKER CONSTRUCTION COMPANY, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 451-7008 RETROFIT RAIL (TY T223) | 1,496 LF | $405.00 | $155.74 | $404.82 | -$372,893 |
| 439-7014 MULTI-LAYER POLYMER OVERLAY | 8,116 SY | $30.00 | $42.80 | $40.32 | $103,885 |
| 439-7025 POLYESTER POLYMER CONC OVERLAY | 85.4 CY | $4,208.00 | $5,302.18 | $3,291.39 | $93,443 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 1,330 LF | $25.00 | $83.04 | $52.29 | $77,193 |
| 439-7016 POLYESTER POLYMER CONC OVERLAY (1-1/2") | 800 SY | $213.00 | $281.94 | $186.40 | $55,152 |
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 299 CY | $168.00 | $326.00 | $190.61 | $47,242 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 789 SF | $177.50 | $118.75 | $150.68 | -$46,354 |
| 354-7005 PLANE & TEXT ASPH CONC PAV(0" TO 6") | 3,476 SY | $1.00 | $12.08 | $4.63 | $38,514 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $9,500.00 | $14,726.51 | $11,585.04 | $36,586 |
| 344-7031 SP MIXES SP-C SAC-B PG76-22 | 358 TON | $398.00 | $301.23 | $97.84 | -$34,644 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 1,100 SF | $102.00 | $80.45 | $95.74 | -$23,705 |
| 428-7001 PENETRATING CONCRETE SURFACE TREATMENT | 4,676 SY | $18.00 | $13.24 | $10.07 | -$22,258 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 172 DAY | $1.00 | $127.36 | $87.82 | $21,734 |
| 429-7010 CONC STR REPAIR (PAN GIRDER HOLE REPR) | 100 EA | $1.00 | $202.94 | $131.64 | $20,194 |
| 735-7060 DRIFTWOOD REMOVAL | 115 CY | $40.00 | $210.60 | $72.46 | $19,619 |
| 505-7001 TMA (STATIONARY) | 92 DAY | $200.00 | $400.04 | $217.57 | $18,404 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 1,330 LF | $20.00 | $33.81 | $12.08 | $18,367 |
| 438-7007 CLEANING AND SEALING EXIST JOINTS (CL7) | 2,711 LF | $40.00 | $33.41 | $38.57 | -$17,865 |
| 500-7001 MOBILIZATION | 1 LS | $298,000.00 | $314,478.00 | $523,850.32 | $16,478 |
| 677-7002 ELIM EXT PM & MRKS (6") | 1,040 LF | $19.00 | $4.43 | $0.2755 | -$15,153 |
Positive: the low bidder was cheaper on that item. These 20 items account for $33,939 of the $121,985 gap.
STRUCTURAL INTEGRITY GROUP LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 344-7031 SP MIXES SP-C SAC-B PG76-22 | 358 TON | $398.00 | $97.84 | 4.07x | $107,457 |
| 428-7001 PENETRATING CONCRETE SURFACE TREATMENT | 4,676 SY | $18.00 | $10.07 | 1.79x | $37,069 |
| 354-7002 PLANE & TEXT ASPH CONC PAV(0" TO 2") | 4,700 SY | $9.20 | $2.24 | 4.11x | $32,727 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 2,470 LF | $20.00 | $7.54 | 2.65x | $30,789 |
| 677-7002 ELIM EXT PM & MRKS (6") | 1,040 LF | $19.00 | $0.2755 | 68.97x | $19,473 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 1,330 LF | $25.00 | $52.29 | 0.48x | -$36,294 |
SCOTT TUCKER CONSTRUCTION COMPANY, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 344-7031 SP MIXES SP-C SAC-B PG76-22 | 358 TON | $301.23 | $97.84 | 3.08x | $72,814 |
| 354-7002 PLANE & TEXT ASPH CONC PAV(0" TO 2") | 4,700 SY | $9.45 | $2.24 | 4.22x | $33,902 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 2,470 LF | $20.99 | $7.54 | 2.79x | $33,234 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 1,330 LF | $33.81 | $12.08 | 2.80x | $28,896 |
| 354-7005 PLANE & TEXT ASPH CONC PAV(0" TO 6") | 3,476 SY | $12.08 | $4.63 | 2.61x | $25,888 |
| 354-7004 PLANE & TEXT ASPH CONC PAV(0" TO 4") | 2,000 SY | $14.42 | $4.74 | 3.04x | $19,364 |
| 505-7001 TMA (STATIONARY) | 92 DAY | $400.04 | $217.57 | 1.84x | $16,787 |
| 735-7060 DRIFTWOOD REMOVAL | 115 CY | $210.60 | $72.46 | 2.91x | $15,886 |
| 451-7008 RETROFIT RAIL (TY T223) | 1,496 LF | $155.74 | $404.82 | 0.38x | -$372,628 |
| 4010-7002 STEEL BRIDGE ZONE PAINTING REF STR #1 | 1 EA | $28,354.87 | $58,500.00 | 0.48x | -$30,145 |
THE TRUESDELL CORPORATION: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 344-7031 SP MIXES SP-C SAC-B PG76-22 | 358 TON | $455.00 | $97.84 | 4.65x | $127,863 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 2,470 LF | $22.00 | $7.54 | 2.92x | $35,729 |
| 354-7002 PLANE & TEXT ASPH CONC PAV(0" TO 2") | 4,700 SY | $9.00 | $2.24 | 4.02x | $31,787 |
| 505-7001 TMA (STATIONARY) | 92 DAY | $535.00 | $217.57 | 2.46x | $29,203 |
| 540-7039 TL-3 31" SHORT RADIUS (COMPLETE) | 1 EA | $35,000.00 | $13,068.91 | 2.68x | $21,931 |
| 451-7008 RETROFIT RAIL (TY T223) | 1,496 LF | $180.00 | $404.82 | 0.44x | -$336,335 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $4,700.00 | $11,585.04 | 0.41x | -$48,195 |
GIBSON & ASSOCIATES, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $29,500.00 | $11,585.04 | 2.55x | $125,405 |
| 344-7031 SP MIXES SP-C SAC-B PG76-22 | 358 TON | $330.00 | $97.84 | 3.37x | $83,113 |
| 735-7060 DRIFTWOOD REMOVAL | 115 CY | $478.50 | $72.46 | 6.60x | $46,695 |
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 299 CY | $346.50 | $190.61 | 1.82x | $46,610 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 49 CY | $1,161.60 | $616.83 | 1.88x | $26,694 |
| 540-7020 MTL THRIE-BEAM GD FEN (STEEL POST) | 12 EA | $4,482.50 | $2,274.69 | 1.97x | $26,494 |
| 354-7002 PLANE & TEXT ASPH CONC PAV(0" TO 2") | 4,700 SY | $7.15 | $2.24 | 3.20x | $23,092 |
GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 439-7016 POLYESTER POLYMER CONC OVERLAY (1-1/2") | 800 SY | $600.00 | $186.40 | 3.22x | $330,881 |
| 439-7025 POLYESTER POLYMER CONC OVERLAY | 85.4 CY | $6,000.00 | $3,291.39 | 1.82x | $231,315 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 1,100 SF | $200.00 | $95.74 | 2.09x | $114,682 |
| 344-7031 SP MIXES SP-C SAC-B PG76-22 | 358 TON | $400.00 | $97.84 | 4.09x | $108,173 |
| 428-7001 PENETRATING CONCRETE SURFACE TREATMENT | 4,676 SY | $20.00 | $10.07 | 1.99x | $46,421 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 2,470 LF | $20.00 | $7.54 | 2.65x | $30,789 |
| 354-7002 PLANE & TEXT ASPH CONC PAV(0" TO 2") | 4,700 SY | $7.50 | $2.24 | 3.35x | $24,737 |
| 666-7213 RE PM TY II (Y) 6" (SLD) | 3,920 LF | $6.25 | $0.1749 | 35.73x | $23,814 |
| 500-7001 MOBILIZATION | 1 LS | $200,000.00 | $523,850.32 | 0.38x | -$323,850 |
| 451-7008 RETROFIT RAIL (TY T223) | 1,496 LF | $200.00 | $404.82 | 0.49x | -$306,415 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $5,000.00 | $11,585.04 | 0.43x | -$46,095 |