Bid Tab X-ray: 6492-85-001

Feb 11, 2026 · Collin Sign up free
Set your company to personalize scores

On Call RPM 07 02.26

6492-85-001 · let Feb 11, 2026 · Collin, Dallas · Routine Maintenance Project - Sealed

$184,935Low bid: THE CONFIDENCE GROUP, INC-11.1% vs estimate $208,015
$38,708Left on the table20.9% gap to the second bid
4BiddersSpread 129% low to high
42Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1THE CONFIDENCE GROUP, INC $184,935-11.1% $38,708 4+$28,314 3-$32,930
2TRP INFRASTRUCTURE SERVICES, LLC $223,642+20.9%7.5% $37,787 2+$60,506 2-$12,123
3STRIPE-A-ZONE, LLC $261,429+41.4%25.7% $162,934 5+$49,251 0
4GREY SKY CONSTRUCTION LLC $424,363+129.5%104.0% 20+$226,811 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.

Where the job was won

THE CONFIDENCE GROUP, INC vs TRP INFRASTRUCTURE SERVICES, LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
500-7002 MOBILIZATION (CALLOUT)23 EA $1,000.00$3,000.00$600.85 $46,000
666-7182 RE PM TY II (W) 12" (SLD)10,150 LF $0.3100$1.40$2.13 $11,064
666-7236 RE PM TY III (W)(6")(SLD)900 LF $10.00$0.7000$0.6919 -$8,370
666-7248 RE PM TY III (Y)(6")(SLD)900 LF $10.00$0.7000$0.7409 -$8,370
666-7184 RE PM TY II (W) 24" (SLD)2,900 LF $0.5400$2.55$3.83 $5,829
666-7194 RE PM TY II (W) (WORD)75 EA $200.00$125.00$104.92 -$5,625
677-7008 ELIM EXT PM & MRKS (24")2,000 LF $0.4000$2.90$2.87 $5,000
666-7239 RE PM TY III (W)(8")(SLD)500 LF $10.00$1.20$1.06 -$4,400
666-7213 RE PM TY II (Y) 6" (SLD)42,000 LF $0.2000$0.3000$0.1749 $4,200
666-7175 RE PM TY II (W) 6" (SLD)41,000 LF $0.2000$0.3000$0.1701 $4,100
666-7186 RE PM TY II (W) (ARROW)75 EA $150.00$100.00$86.49 -$3,750
505-7003 TMA (MOBILE OPERATION)50 DAY $150.00$100.00$229.60 -$2,500
505-7001 TMA (STATIONARY)48 DAY $150.00$100.00$217.57 -$2,400
677-7006 ELIM EXT PM & MRKS (12")1,500 LF $0.3500$1.75$1.27 $2,100
666-7238 RE PM TY III (W)(6")(DOT)200 LF $10.00$1.75$1.31 -$1,650
677-7023 ELIM EXT PM & MRKS (18")(YLD TRI)18 EA $100.00$25.00$23.57 -$1,350
666-7169 RE PM TY II (W) 4" (DOT)1,400 LF $0.2000$1.15$0.2921 $1,330
677-7004 ELIM EXT PM & MRKS (8")2,700 LF $0.3000$0.7500$0.6468 $1,215
666-7242 RE PM TY III (W)(12")(SLD)200 LF $10.00$4.60$2.62 -$1,080
666-7172 RE PM TY II (W) 6" (BRK)10,290 LF $0.2000$0.3000$0.2347 $1,029

Positive: the low bidder was cheaper on that item. These 20 items account for $42,372 of the $38,708 gap.

THE CONFIDENCE GROUP, INC: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
666-7236 RE PM TY III (W)(6")(SLD)900 LF $10.00$0.691914.45x$8,377
666-7248 RE PM TY III (Y)(6")(SLD)900 LF $10.00$0.740913.50x$8,333
666-7194 RE PM TY II (W) (WORD)75 EA $200.00$104.921.91x$7,131
666-7239 RE PM TY III (W)(8")(SLD)500 LF $10.00$1.069.47x$4,472
666-7182 RE PM TY II (W) 12" (SLD)10,150 LF $0.3100$2.130.15x-$18,451
666-7184 RE PM TY II (W) 24" (SLD)2,900 LF $0.5400$3.830.14x-$9,538
677-7008 ELIM EXT PM & MRKS (24")2,000 LF $0.4000$2.870.14x-$4,941

TRP INFRASTRUCTURE SERVICES, LLC: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
500-7002 MOBILIZATION (CALLOUT)23 EA $3,000.00$600.854.99x$55,180
666-7175 RE PM TY II (W) 6" (SLD)41,000 LF $0.3000$0.17011.76x$5,326
505-7003 TMA (MOBILE OPERATION)50 DAY $100.00$229.600.44x-$6,480
505-7001 TMA (STATIONARY)48 DAY $100.00$217.570.46x-$5,643

STRIPE-A-ZONE, LLC: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
666-7213 RE PM TY II (Y) 6" (SLD)42,000 LF $0.5000$0.17492.86x$13,654
666-7175 RE PM TY II (W) 6" (SLD)41,000 LF $0.5000$0.17012.94x$13,526
505-7003 TMA (MOBILE OPERATION)50 DAY $500.00$229.602.18x$13,520
666-7210 RE PM TY II (Y) 4" (SLD)42,240 LF $0.3200$0.18221.76x$5,821
666-7172 RE PM TY II (W) 6" (BRK)10,290 LF $0.5000$0.23472.13x$2,730

GREY SKY CONSTRUCTION LLC: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
500-7002 MOBILIZATION (CALLOUT)23 EA $2,500.00$600.854.16x$43,680
666-7182 RE PM TY II (W) 12" (SLD)10,150 LF $4.00$2.131.88x$19,003
677-7008 ELIM EXT PM & MRKS (24")2,000 LF $12.00$2.874.18x$18,259
505-7003 TMA (MOBILE OPERATION)50 DAY $550.00$229.602.40x$16,020
677-7004 ELIM EXT PM & MRKS (8")2,700 LF $6.00$0.64689.28x$14,454
666-7213 RE PM TY II (Y) 6" (SLD)42,000 LF $0.5000$0.17492.86x$13,654
666-7210 RE PM TY II (Y) 4" (SLD)42,240 LF $0.5000$0.18222.74x$13,424
666-7186 RE PM TY II (W) (ARROW)75 EA $250.00$86.492.89x$12,263
666-7184 RE PM TY II (W) 24" (SLD)2,900 LF $8.00$3.832.09x$12,096
666-7175 RE PM TY II (W) 6" (SLD)41,000 LF $0.4500$0.17012.65x$11,476