On Call RPM 07 02.26
6492-85-001 · let Feb 11, 2026 · Collin, Dallas · Routine Maintenance Project - Sealed
$184,935Low bid: THE CONFIDENCE GROUP, INC-11.1% vs estimate $208,015
$38,708Left on the table20.9% gap to the second bid
4BiddersSpread 129% low to high
42Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | THE CONFIDENCE GROUP, INC | $184,935 | -11.1% | $38,708 | 4+$28,314 | 3-$32,930 | |
| 2 | TRP INFRASTRUCTURE SERVICES, LLC | $223,642 | +20.9% | 7.5% | $37,787 | 2+$60,506 | 2-$12,123 |
| 3 | STRIPE-A-ZONE, LLC | $261,429 | +41.4% | 25.7% | $162,934 | 5+$49,251 | 0 |
| 4 | GREY SKY CONSTRUCTION LLC | $424,363 | +129.5% | 104.0% | 20+$226,811 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
THE CONFIDENCE GROUP, INC vs TRP INFRASTRUCTURE SERVICES, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 23 EA | $1,000.00 | $3,000.00 | $600.85 | $46,000 |
| 666-7182 RE PM TY II (W) 12" (SLD) | 10,150 LF | $0.3100 | $1.40 | $2.13 | $11,064 |
| 666-7236 RE PM TY III (W)(6")(SLD) | 900 LF | $10.00 | $0.7000 | $0.6919 | -$8,370 |
| 666-7248 RE PM TY III (Y)(6")(SLD) | 900 LF | $10.00 | $0.7000 | $0.7409 | -$8,370 |
| 666-7184 RE PM TY II (W) 24" (SLD) | 2,900 LF | $0.5400 | $2.55 | $3.83 | $5,829 |
| 666-7194 RE PM TY II (W) (WORD) | 75 EA | $200.00 | $125.00 | $104.92 | -$5,625 |
| 677-7008 ELIM EXT PM & MRKS (24") | 2,000 LF | $0.4000 | $2.90 | $2.87 | $5,000 |
| 666-7239 RE PM TY III (W)(8")(SLD) | 500 LF | $10.00 | $1.20 | $1.06 | -$4,400 |
| 666-7213 RE PM TY II (Y) 6" (SLD) | 42,000 LF | $0.2000 | $0.3000 | $0.1749 | $4,200 |
| 666-7175 RE PM TY II (W) 6" (SLD) | 41,000 LF | $0.2000 | $0.3000 | $0.1701 | $4,100 |
| 666-7186 RE PM TY II (W) (ARROW) | 75 EA | $150.00 | $100.00 | $86.49 | -$3,750 |
| 505-7003 TMA (MOBILE OPERATION) | 50 DAY | $150.00 | $100.00 | $229.60 | -$2,500 |
| 505-7001 TMA (STATIONARY) | 48 DAY | $150.00 | $100.00 | $217.57 | -$2,400 |
| 677-7006 ELIM EXT PM & MRKS (12") | 1,500 LF | $0.3500 | $1.75 | $1.27 | $2,100 |
| 666-7238 RE PM TY III (W)(6")(DOT) | 200 LF | $10.00 | $1.75 | $1.31 | -$1,650 |
| 677-7023 ELIM EXT PM & MRKS (18")(YLD TRI) | 18 EA | $100.00 | $25.00 | $23.57 | -$1,350 |
| 666-7169 RE PM TY II (W) 4" (DOT) | 1,400 LF | $0.2000 | $1.15 | $0.2921 | $1,330 |
| 677-7004 ELIM EXT PM & MRKS (8") | 2,700 LF | $0.3000 | $0.7500 | $0.6468 | $1,215 |
| 666-7242 RE PM TY III (W)(12")(SLD) | 200 LF | $10.00 | $4.60 | $2.62 | -$1,080 |
| 666-7172 RE PM TY II (W) 6" (BRK) | 10,290 LF | $0.2000 | $0.3000 | $0.2347 | $1,029 |
Positive: the low bidder was cheaper on that item. These 20 items account for $42,372 of the $38,708 gap.
THE CONFIDENCE GROUP, INC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 666-7236 RE PM TY III (W)(6")(SLD) | 900 LF | $10.00 | $0.6919 | 14.45x | $8,377 |
| 666-7248 RE PM TY III (Y)(6")(SLD) | 900 LF | $10.00 | $0.7409 | 13.50x | $8,333 |
| 666-7194 RE PM TY II (W) (WORD) | 75 EA | $200.00 | $104.92 | 1.91x | $7,131 |
| 666-7239 RE PM TY III (W)(8")(SLD) | 500 LF | $10.00 | $1.06 | 9.47x | $4,472 |
| 666-7182 RE PM TY II (W) 12" (SLD) | 10,150 LF | $0.3100 | $2.13 | 0.15x | -$18,451 |
| 666-7184 RE PM TY II (W) 24" (SLD) | 2,900 LF | $0.5400 | $3.83 | 0.14x | -$9,538 |
| 677-7008 ELIM EXT PM & MRKS (24") | 2,000 LF | $0.4000 | $2.87 | 0.14x | -$4,941 |
TRP INFRASTRUCTURE SERVICES, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 23 EA | $3,000.00 | $600.85 | 4.99x | $55,180 |
| 666-7175 RE PM TY II (W) 6" (SLD) | 41,000 LF | $0.3000 | $0.1701 | 1.76x | $5,326 |
| 505-7003 TMA (MOBILE OPERATION) | 50 DAY | $100.00 | $229.60 | 0.44x | -$6,480 |
| 505-7001 TMA (STATIONARY) | 48 DAY | $100.00 | $217.57 | 0.46x | -$5,643 |
STRIPE-A-ZONE, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 666-7213 RE PM TY II (Y) 6" (SLD) | 42,000 LF | $0.5000 | $0.1749 | 2.86x | $13,654 |
| 666-7175 RE PM TY II (W) 6" (SLD) | 41,000 LF | $0.5000 | $0.1701 | 2.94x | $13,526 |
| 505-7003 TMA (MOBILE OPERATION) | 50 DAY | $500.00 | $229.60 | 2.18x | $13,520 |
| 666-7210 RE PM TY II (Y) 4" (SLD) | 42,240 LF | $0.3200 | $0.1822 | 1.76x | $5,821 |
| 666-7172 RE PM TY II (W) 6" (BRK) | 10,290 LF | $0.5000 | $0.2347 | 2.13x | $2,730 |
GREY SKY CONSTRUCTION LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 23 EA | $2,500.00 | $600.85 | 4.16x | $43,680 |
| 666-7182 RE PM TY II (W) 12" (SLD) | 10,150 LF | $4.00 | $2.13 | 1.88x | $19,003 |
| 677-7008 ELIM EXT PM & MRKS (24") | 2,000 LF | $12.00 | $2.87 | 4.18x | $18,259 |
| 505-7003 TMA (MOBILE OPERATION) | 50 DAY | $550.00 | $229.60 | 2.40x | $16,020 |
| 677-7004 ELIM EXT PM & MRKS (8") | 2,700 LF | $6.00 | $0.6468 | 9.28x | $14,454 |
| 666-7213 RE PM TY II (Y) 6" (SLD) | 42,000 LF | $0.5000 | $0.1749 | 2.86x | $13,654 |
| 666-7210 RE PM TY II (Y) 4" (SLD) | 42,240 LF | $0.5000 | $0.1822 | 2.74x | $13,424 |
| 666-7186 RE PM TY II (W) (ARROW) | 75 EA | $250.00 | $86.49 | 2.89x | $12,263 |
| 666-7184 RE PM TY II (W) 24" (SLD) | 2,900 LF | $8.00 | $3.83 | 2.09x | $12,096 |
| 666-7175 RE PM TY II (W) 6" (SLD) | 41,000 LF | $0.4500 | $0.1701 | 2.65x | $11,476 |