Denton 2026 Spot Striping
6492-62-001 · let Feb 11, 2026 · Denton, Dallas · Routine Maintenance Project - Sealed
$199,700Low bid: TRP INFRASTRUCTURE SERVICES, LLC-18.3% vs estimate $244,440
$42,834Left on the table21.4% gap to the second bid
4BiddersSpread 95% low to high
38Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TRP INFRASTRUCTURE SERVICES, LLC | $199,700 | -18.3% | $42,834 | 0 | 3-$15,937 | |
| 2 | THE CONFIDENCE GROUP, INC | $242,533 | +21.4% | -0.8% | $89,158 | 2+$24,541 | 0 |
| 3 | STRIPE-A-ZONE, LLC | $331,691 | +66.1% | 35.7% | $58,630 | 4+$66,885 | 1-$5,789 |
| 4 | GREY SKY CONSTRUCTION LLC | $390,320 | +95.5% | 59.7% | 13+$143,641 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
TRP INFRASTRUCTURE SERVICES, LLC vs THE CONFIDENCE GROUP, INC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 678-7002 PAV SURF PREP FOR MRK (6") | 103,000 LF | $0.0100 | $0.2500 | $0.0662 | $24,720 |
| 677-7002 ELIM EXT PM & MRKS (6") | 103,000 LF | $0.2900 | $0.1500 | $0.2755 | -$14,420 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 50 DAY | $22.00 | $200.00 | $87.82 | $8,900 |
| 505-7003 TMA (MOBILE OPERATION) | 30 DAY | $1.00 | $200.00 | $229.60 | $5,970 |
| 666-7248 RE PM TY III (Y)(6")(SLD) | 43,000 LF | $0.5400 | $0.6000 | $0.7409 | $2,580 |
| 666-7175 RE PM TY II (W) 6" (SLD) | 80,000 LF | $0.1700 | $0.2000 | $0.1701 | $2,400 |
| 672-7006 REFL PAV MRKR TY II-C-R | 15,000 EA | $3.85 | $4.00 | $4.19 | $2,250 |
| 666-7213 RE PM TY II (Y) 6" (SLD) | 70,000 LF | $0.1700 | $0.2000 | $0.1749 | $2,100 |
| 666-7244 RE PM TY III (W)(24")(SLD) | 500 LF | $7.10 | $3.00 | $7.96 | -$2,050 |
| 672-7008 TRAFFIC BUTTON TY Y | 300 EA | $3.25 | $10.00 | $2.19 | $2,025 |
| 533-7002 MILL RUMBLE STRIPS (ASPH) (CENTERLINE) | 200 LF | $0.4000 | $10.00 | $0.2394 | $1,920 |
| 678-7004 PAV SURF PREP FOR MRK (8") | 1,500 LF | $0.0600 | $1.00 | $0.1162 | $1,410 |
| 500-7002 MOBILIZATION (CALLOUT) | 12 EA | $700.00 | $800.00 | $600.85 | $1,200 |
| 666-7066 REFL PAV MRK TY I (W)(WORD)(100MIL) | 10 EA | $132.00 | $250.00 | $184.78 | $1,180 |
| 666-7042 REFL PAV MRK TY I (W)(ARROW)(100MIL) | 25 EA | $109.00 | $150.00 | $156.95 | $1,025 |
| 666-7242 RE PM TY III (W)(12")(SLD) | 500 LF | $3.55 | $1.50 | $2.62 | -$1,025 |
| 677-7004 ELIM EXT PM & MRKS (8") | 1,500 LF | $0.5800 | $1.00 | $0.6468 | $630 |
| 677-7008 ELIM EXT PM & MRKS (24") | 500 LF | $2.25 | $1.00 | $2.87 | -$625 |
| 677-7015 ELIM EXT PM & MRKS (WORD) | 10 EA | $38.00 | $100.00 | $53.95 | $620 |
| 666-7045 REFL PAV MRK TY I(W)(DBL ARROW)(100MIL) | 4 EA | $156.00 | $300.00 | $240.06 | $576 |
Positive: the low bidder was cheaper on that item. These 20 items account for $41,386 of the $42,834 gap.
TRP INFRASTRUCTURE SERVICES, LLC: unbalanced items
Placed 1THE CONFIDENCE GROUP, INC: unbalanced items
Placed 2STRIPE-A-ZONE, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 677-7002 ELIM EXT PM & MRKS (6") | 103,000 LF | $0.5000 | $0.2755 | 1.81x | $23,124 |
| 505-7003 TMA (MOBILE OPERATION) | 30 DAY | $800.00 | $229.60 | 3.48x | $17,112 |
| 666-7175 RE PM TY II (W) 6" (SLD) | 80,000 LF | $0.3500 | $0.1701 | 2.06x | $14,392 |
| 666-7213 RE PM TY II (Y) 6" (SLD) | 70,000 LF | $0.3500 | $0.1749 | 2.00x | $12,257 |
| 678-7002 PAV SURF PREP FOR MRK (6") | 103,000 LF | $0.0100 | $0.0662 | 0.15x | -$5,789 |
GREY SKY CONSTRUCTION LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 678-7002 PAV SURF PREP FOR MRK (6") | 103,000 LF | $0.4500 | $0.0662 | 6.80x | $39,531 |
| 500-7002 MOBILIZATION (CALLOUT) | 12 EA | $2,500.00 | $600.85 | 4.16x | $22,790 |
| 666-7175 RE PM TY II (W) 6" (SLD) | 80,000 LF | $0.4500 | $0.1701 | 2.65x | $22,392 |
| 666-7213 RE PM TY II (Y) 6" (SLD) | 70,000 LF | $0.4500 | $0.1749 | 2.57x | $19,257 |
| 505-7003 TMA (MOBILE OPERATION) | 30 DAY | $550.00 | $229.60 | 2.40x | $9,612 |
| 678-7008 PAV SURF PREP FOR MRK (24") | 500 LF | $12.00 | $0.9416 | 12.74x | $5,529 |
| 677-7008 ELIM EXT PM & MRKS (24") | 500 LF | $12.00 | $2.87 | 4.18x | $4,565 |
| 678-7004 PAV SURF PREP FOR MRK (8") | 1,500 LF | $3.00 | $0.1162 | 25.82x | $4,326 |
| 677-7004 ELIM EXT PM & MRKS (8") | 1,500 LF | $3.00 | $0.6468 | 4.64x | $3,530 |
| 678-7009 PAV SURF PREP FOR MRK (ARROW) | 25 EA | $150.00 | $16.69 | 8.99x | $3,333 |