Bid Tab X-ray: 6492-59-001

Feb 26, 2026 · Lubbock Sign up free
Set your company to personalize scores

FY26 Lubbock Southeast ROW Mowing

6492-59-001 · let Feb 26, 2026 · Lubbock, Lubbock · Routine Maintenance Project - Sealed

$174,349Low bid: ABESCAPE GROUP LLC-14.3% vs estimate $203,520
$101,255Left on the table58.1% gap to the second bid
2BiddersSpread 58% low to high
4Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1ABESCAPE GROUP LLC $174,349-14.3% $101,255 0 1-$6,401
2GORMAN OUTDOOR, INC. $275,604+58.1%35.4% 1+$18,771 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.

Where the job was won

ABESCAPE GROUP LLC vs GORMAN OUTDOOR, INC., biggest item swings
ItemQtyLow2ndMarket2nd minus low
730-7022 FULL - WIDTH MOWING4,508 AC $36.45$50.00$38.53 $61,083
505-7003 TMA (MOBILE OPERATION)28 DAY $1.00$900.00$229.60 $25,172
730-7021 SPOT MOWING500 AC $20.00$50.00$30.27 $15,000
500-7002 MOBILIZATION (CALLOUT)4 EA $1.00$1.00$600.85 $0

Positive: the low bidder was cheaper on that item. These 4 items account for $101,255 of the $101,255 gap.

ABESCAPE GROUP LLC: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
505-7003 TMA (MOBILE OPERATION)28 DAY $1.00$229.600.00x-$6,401

GORMAN OUTDOOR, INC.: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
505-7003 TMA (MOBILE OPERATION)28 DAY $900.00$229.603.92x$18,771