FY26 Lubbock Southeast ROW Mowing
6492-59-001 · let Feb 26, 2026 · Lubbock, Lubbock · Routine Maintenance Project - Sealed
$174,349Low bid: ABESCAPE GROUP LLC-14.3% vs estimate $203,520
$101,255Left on the table58.1% gap to the second bid
2BiddersSpread 58% low to high
4Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ABESCAPE GROUP LLC | $174,349 | -14.3% | $101,255 | 0 | 1-$6,401 | |
| 2 | GORMAN OUTDOOR, INC. | $275,604 | +58.1% | 35.4% | 1+$18,771 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
ABESCAPE GROUP LLC vs GORMAN OUTDOOR, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 730-7022 FULL - WIDTH MOWING | 4,508 AC | $36.45 | $50.00 | $38.53 | $61,083 |
| 505-7003 TMA (MOBILE OPERATION) | 28 DAY | $1.00 | $900.00 | $229.60 | $25,172 |
| 730-7021 SPOT MOWING | 500 AC | $20.00 | $50.00 | $30.27 | $15,000 |
| 500-7002 MOBILIZATION (CALLOUT) | 4 EA | $1.00 | $1.00 | $600.85 | $0 |
Positive: the low bidder was cheaper on that item. These 4 items account for $101,255 of the $101,255 gap.
ABESCAPE GROUP LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 28 DAY | $1.00 | $229.60 | 0.00x | -$6,401 |
GORMAN OUTDOOR, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 28 DAY | $900.00 | $229.60 | 3.92x | $18,771 |