BPM
6493-60-001 · let Feb 4, 2026 · Montgomery, Houston · Bridge Preventative Maintenance - Sealed
$1,198,560Low bid: BK FIELD OPERATIONS LLC+3.9% vs estimate $1,153,575
$152,915Left on the table12.8% gap to the second bid
10BiddersSpread 127% low to high
19Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BK FIELD OPERATIONS LLC | $1,198,560 | 3.9% | $152,915 | 5+$128,064 | 2-$53,146 | |
| 2 | ROY JORGENSEN ASSOCIATES, INC. | $1,351,475 | +12.8% | 17.2% | $17,525 | 2+$80,593 | 1-$39,439 |
| 3 | GARRET SHIELDS INFRASTRUCTURE | $1,369,000 | +14.2% | 18.7% | $56,155 | 4+$98,685 | 0 |
| 4 | ISI CONTRACTING, INC. | $1,425,155 | +18.9% | 23.5% | $20,550 | 5+$122,234 | 0 |
| 5 | STRUCTURAL INTEGRITY GROUP LLC | $1,445,705 | +20.6% | 25.3% | $168,020 | 5+$209,349 | 1-$41,149 |
| 6 | PATHFIELD INVESTMENTS LLC | $1,613,725 | +34.6% | 39.9% | $20,110 | ||
| 7 | FORDE CONSTRUCTION COMPANY, INC. | $1,633,835 | +36.3% | 41.6% | $187,340 | ||
| 8 | CASTILLO ARANDA LLC | $1,821,175 | +51.9% | 57.9% | $512,750 | ||
| 9 | TAYLOR BRIDGE LLC | $2,333,925 | +94.7% | 102.3% | $389,525 | ||
| 10 | BLACKSMITH VENTURES LLC | $2,723,450 | +127.2% | 136.1% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
BK FIELD OPERATIONS LLC vs ROY JORGENSEN ASSOCIATES, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 2,620 CY | $190.00 | $210.00 | $184.74 | $52,400 |
| 401-7002 FLOWABLE FILL (EMBANKMENT) | 175 CY | $300.00 | $550.00 | $142.67 | $43,750 |
| 735-7060 DRIFTWOOD REMOVAL | 1,075 CY | $40.00 | $80.00 | $72.46 | $43,000 |
| 429-7004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 300 SF | $240.00 | $120.00 | $85.28 | -$36,000 |
| 785-7005 BRIDGE JOINT REPAIR (SEJ) | 200 LF | $300.00 | $440.00 | $385.82 | $28,000 |
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 705 CY | $190.00 | $225.00 | $190.61 | $24,675 |
| 110-7002 EXCAV (CHANNEL) | 1,500 CY | $35.00 | $25.00 | $16.69 | -$15,000 |
| 752-7003 TREE TRIMMING / BRUSH REMOVAL(CHANNELS) | 20 AC | $1,000.00 | $1,650.00 | $1,602.83 | $13,000 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 215 SF | $140.00 | $200.00 | $150.68 | $12,900 |
| 400-7010 CEM STABIL BKFL | 150 CY | $240.00 | $165.00 | $138.14 | -$11,250 |
| 500-7002 MOBILIZATION (CALLOUT) | 20 EA | $1.00 | $550.00 | $600.85 | $10,980 |
| 429-7006 CONC STR REPR(RAPID DECK REP(FULL DPT)) | 100 SF | $325.00 | $225.00 | $153.06 | -$10,000 |
| 132-7036 EMBANK (FNL)(DC)(TY E)(CSBE) | 10 CY | $1,000.00 | $100.00 | $53.65 | -$9,000 |
| 500-7033 MOBILIZATION (EMERGENCY) | 2 EA | $2,500.00 | $5,500.00 | $844.81 | $6,000 |
| 740-7003 GRAFFITI REMOVAL (PAINTING) | 400 SF | $10.00 | $2.50 | $2.98 | -$3,000 |
| 432-7055 RIPRAP (CONC)(CL B)(RR8&RR9) | 35 CY | $600.00 | $550.00 | $725.38 | -$1,750 |
| 505-7001 TMA (STATIONARY) | 190 DAY | $1.00 | $10.00 | $217.57 | $1,710 |
| 438-7007 CLEANING AND SEALING EXIST JOINTS (CL7) | 3,000 LF | $42.00 | $42.50 | $38.57 | $1,500 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 20 DAY | $100.00 | $150.00 | $87.82 | $1,000 |
Positive: the low bidder was cheaper on that item. These 19 items account for $152,915 of the $152,915 gap.
BK FIELD OPERATIONS LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 429-7004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 300 SF | $240.00 | $85.28 | 2.81x | $46,415 |
| 401-7002 FLOWABLE FILL (EMBANKMENT) | 175 CY | $300.00 | $142.67 | 2.10x | $27,533 |
| 110-7002 EXCAV (CHANNEL) | 1,500 CY | $35.00 | $16.69 | 2.10x | $27,459 |
| 429-7006 CONC STR REPR(RAPID DECK REP(FULL DPT)) | 100 SF | $325.00 | $153.06 | 2.12x | $17,194 |
| 132-7036 EMBANK (FNL)(DC)(TY E)(CSBE) | 10 CY | $1,000.00 | $53.65 | 18.64x | $9,464 |
| 505-7001 TMA (STATIONARY) | 190 DAY | $1.00 | $217.57 | 0.00x | -$41,149 |
| 500-7002 MOBILIZATION (CALLOUT) | 20 EA | $1.00 | $600.85 | 0.00x | -$11,997 |
ROY JORGENSEN ASSOCIATES, INC.: unbalanced items
Placed 2GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 110-7002 EXCAV (CHANNEL) | 1,500 CY | $40.00 | $16.69 | 2.40x | $34,959 |
| 401-7002 FLOWABLE FILL (EMBANKMENT) | 175 CY | $300.00 | $142.67 | 2.10x | $27,533 |
| 429-7004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 300 SF | $150.00 | $85.28 | 1.76x | $19,415 |
| 400-7010 CEM STABIL BKFL | 150 CY | $250.00 | $138.14 | 1.81x | $16,778 |
ISI CONTRACTING, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 401-7002 FLOWABLE FILL (EMBANKMENT) | 175 CY | $350.00 | $142.67 | 2.45x | $36,283 |
| 752-7003 TREE TRIMMING / BRUSH REMOVAL(CHANNELS) | 20 AC | $3,100.00 | $1,602.83 | 1.93x | $29,943 |
| 110-7002 EXCAV (CHANNEL) | 1,500 CY | $35.00 | $16.69 | 2.10x | $27,459 |
| 429-7004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 300 SF | $155.00 | $85.28 | 1.82x | $20,915 |
| 132-7036 EMBANK (FNL)(DC)(TY E)(CSBE) | 10 CY | $817.00 | $53.65 | 15.23x | $7,634 |
STRUCTURAL INTEGRITY GROUP LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 110-7002 EXCAV (CHANNEL) | 1,500 CY | $64.00 | $16.69 | 3.83x | $70,959 |
| 785-7005 BRIDGE JOINT REPAIR (SEJ) | 200 LF | $720.00 | $385.82 | 1.87x | $66,835 |
| 401-7002 FLOWABLE FILL (EMBANKMENT) | 175 CY | $370.00 | $142.67 | 2.59x | $39,783 |
| 400-7010 CEM STABIL BKFL | 150 CY | $295.00 | $138.14 | 2.14x | $23,528 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 20 DAY | $500.00 | $87.82 | 5.69x | $8,244 |
| 505-7001 TMA (STATIONARY) | 190 DAY | $1.00 | $217.57 | 0.00x | -$41,149 |