ROW Mowing Hopkins Co. FY26
6493-56-001 · let Feb 19, 2026 · Hopkins, Paris · Routine Maintenance Project - Sealed
$207,295Low bid: EASTGATE SERVICES-9.9% vs estimate $229,957
$9,562Left on the table4.6% gap to the second bid
4BiddersSpread 11% low to high
4Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | EASTGATE SERVICES | $207,295 | -9.9% | $9,562 | 0 | 2-$20,166 | |
| 2 | ABESCAPE GROUP LLC | $216,857 | +4.6% | -5.7% | $4,149 | 0 | 1-$2,927 |
| 3 | CEHAND SERVICES LLC | $221,006 | +6.6% | -3.9% | $8,559 | 0 | 1-$2,927 |
| 4 | SKYLINE CONSTRUCTION PAVING & STRIPING | $229,565 | +10.7% | -0.2% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
EASTGATE SERVICES vs ABESCAPE GROUP LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 730-7020 STRIP MOWING | 1,001 AC | $15.00 | $20.00 | $32.12 | $5,005 |
| 730-7022 FULL - WIDTH MOWING | 5,060 AC | $38.00 | $38.88 | $38.53 | $4,453 |
| 730-7021 SPOT MOWING | 100 AC | $0.0010 | $1.00 | $30.27 | $100 |
| 500-7002 MOBILIZATION (CALLOUT) | 4 EA | $0.0010 | $1.00 | $600.85 | $4 |
Positive: the low bidder was cheaper on that item. These 4 items account for $9,562 of the $9,562 gap.
EASTGATE SERVICES: unbalanced items
Placed 1ABESCAPE GROUP LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 730-7021 SPOT MOWING | 100 AC | $1.00 | $30.27 | 0.03x | -$2,927 |
CEHAND SERVICES LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 730-7021 SPOT MOWING | 100 AC | $1.00 | $30.27 | 0.03x | -$2,927 |