On Call FDCR 07 02.26
6466-51-001 · let Feb 11, 2026 · Collin, Dallas · Routine Maintenance Project - Sealed
$278,461Low bid: PROFESSIONAL TRAFFIC CONTROL LLC-16.6% vs estimate $333,800
$137,669Left on the table49.4% gap to the second bid
4BiddersSpread 157% low to high
13Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | PROFESSIONAL TRAFFIC CONTROL LLC | $278,461 | -16.6% | $137,669 | 1+$9,065 | 2-$50,203 | |
| 2 | O. TREVINO CONSTRUCTION, LLC | $416,130 | +49.4% | 24.7% | $47,500 | 5+$18,126 | 1-$19,491 |
| 3 | GARRET SHIELDS INFRASTRUCTURE | $463,630 | +66.5% | 38.9% | $251,070 | 1+$19,415 | 1-$2,605 |
| 4 | ROY JORGENSEN ASSOCIATES, INC. | $714,700 | +156.7% | 114.1% | 10+$250,155 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
PROFESSIONAL TRAFFIC CONTROL LLC vs O. TREVINO CONSTRUCTION, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 361-7047 FULL-DEPTH REP(BR APPR SLAB)(9"-13") | 75 CY | $775.00 | $1,560.00 | $1,087.55 | $58,875 |
| 429-7006 CONC STR REPR(RAPID DECK REP(FULL DPT)) | 300 SF | $35.50 | $182.00 | $153.06 | $43,950 |
| 429-7004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 300 SF | $35.50 | $119.00 | $85.28 | $25,050 |
| 505-7001 TMA (STATIONARY) | 90 DAY | $250.00 | $1.00 | $217.57 | -$22,410 |
| 361-7044 FULL-DEPTH REPAIR CRCP (VAR DEPTH) | 90 CY | $825.00 | $995.00 | $1,211.78 | $15,300 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 30 DAY | $390.00 | $176.00 | $87.82 | -$6,420 |
| 361-7009 FULL - DEPTH REPAIR CRCP (14") | 6 CY | $810.00 | $1,705.00 | $895.70 | $5,370 |
| 361-7025 FULL - DEPTH REPAIR CPCD (14") | 6 CY | $865.00 | $1,655.00 | $892.43 | $4,740 |
| 361-7045 FULL-DEPTH REPAIR CPCD (VAR DEPTH) | 75 CY | $880.00 | $930.00 | $931.83 | $3,750 |
| 529-7009 CONC CURB & GUTTER (TY II) | 50 LF | $29.86 | $95.00 | $32.57 | $3,257 |
| 500-7002 MOBILIZATION (CALLOUT) | 12 EA | $750.00 | $1,000.00 | $600.85 | $3,000 |
| 529-7002 CONC CURB (TY II) | 50 LF | $29.86 | $85.00 | $26.45 | $2,757 |
| 500-7033 MOBILIZATION (EMERGENCY) | 3 EA | $850.00 | $1,000.00 | $844.81 | $450 |
Positive: the low bidder was cheaper on that item. These 13 items account for $137,669 of the $137,669 gap.
PROFESSIONAL TRAFFIC CONTROL LLC: unbalanced items
Placed 1O. TREVINO CONSTRUCTION, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 361-7009 FULL - DEPTH REPAIR CRCP (14") | 6 CY | $1,705.00 | $895.70 | 1.90x | $4,856 |
| 361-7025 FULL - DEPTH REPAIR CPCD (14") | 6 CY | $1,655.00 | $892.43 | 1.85x | $4,575 |
| 529-7009 CONC CURB & GUTTER (TY II) | 50 LF | $95.00 | $32.57 | 2.92x | $3,122 |
| 529-7002 CONC CURB (TY II) | 50 LF | $85.00 | $26.45 | 3.21x | $2,927 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 30 DAY | $176.00 | $87.82 | 2.00x | $2,645 |
| 505-7001 TMA (STATIONARY) | 90 DAY | $1.00 | $217.57 | 0.00x | -$19,491 |
GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 3ROY JORGENSEN ASSOCIATES, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 361-7047 FULL-DEPTH REP(BR APPR SLAB)(9"-13") | 75 CY | $2,100.00 | $1,087.55 | 1.93x | $75,934 |
| 361-7045 FULL-DEPTH REPAIR CPCD (VAR DEPTH) | 75 CY | $1,800.00 | $931.83 | 1.93x | $65,113 |
| 429-7004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 300 SF | $200.00 | $85.28 | 2.35x | $34,415 |
| 505-7001 TMA (STATIONARY) | 90 DAY | $500.00 | $217.57 | 2.30x | $25,419 |
| 500-7002 MOBILIZATION (CALLOUT) | 12 EA | $1,500.00 | $600.85 | 2.50x | $10,790 |
| 361-7009 FULL - DEPTH REPAIR CRCP (14") | 6 CY | $2,400.00 | $895.70 | 2.68x | $9,026 |
| 361-7025 FULL - DEPTH REPAIR CPCD (14") | 6 CY | $2,300.00 | $892.43 | 2.58x | $8,445 |
| 529-7009 CONC CURB & GUTTER (TY II) | 50 LF | $200.00 | $32.57 | 6.14x | $8,372 |
| 500-7033 MOBILIZATION (EMERGENCY) | 3 EA | $3,000.00 | $844.81 | 3.55x | $6,466 |
| 529-7002 CONC CURB (TY II) | 50 LF | $150.00 | $26.45 | 5.67x | $6,177 |