RPM FY 2026
6495-74-001 · let Mar 18, 2026 · Potter, Amarillo · Routine Maintenance Project - Sealed
$640,394Low bid: L&L COMPANY+4.2% vs estimate $614,855
$23,331Left on the table3.6% gap to the second bid
3BiddersSpread 15% low to high
6Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | L&L COMPANY | $640,394 | 4.2% | $23,331 | 0 | 3-$586,033 | |
| 2 | TRP INFRASTRUCTURE SERVICES, LLC | $663,725 | +3.6% | 7.9% | $72,709 | 1+$41,448 | 2-$553,602 |
| 3 | CENTERLINE TECHNOLOGIES, LLC | $736,434 | +15.0% | 19.8% | 0 | 3-$586,033 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
L&L COMPANY vs TRP INFRASTRUCTURE SERVICES, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 120 DAY | $1.00 | $575.00 | $229.60 | $68,880 |
| 672-7004 REFL PAV MRKR TY II-A-A | 112,637 EA | $3.80 | $3.50 | $3.97 | -$33,791 |
| 672-7006 REFL PAV MRKR TY II-C-R | 36,803 EA | $3.80 | $3.50 | $4.19 | -$11,041 |
| 672-7002 REFL PAV MRKR TY I-C | 19,052 EA | $3.80 | $3.50 | $4.04 | -$5,716 |
| 500-7001 MOBILIZATION | 1 LS | $1.00 | $5,000.00 | $523,850.32 | $4,999 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $1.00 | $1.00 | $11,585.04 | $0 |
Positive: the low bidder was cheaper on that item. These 6 items account for $23,331 of the $23,331 gap.