SanPatIH37WFrontage234-Cooper
0074-05-104 · let Mar 4, 2026 · San Patricio, Corpus Christi · Rehabilitation of Existing Road
$2,258,368Low bid: ANDERSON COLUMBIA CO., INC.-4.6% vs estimate $2,366,695
$366,143Left on the table16.2% gap to the second bid
7BiddersSpread 59% low to high
64Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ANDERSON COLUMBIA CO., INC. | $2,258,368 | -4.6% | $366,143 | 2+$60,066 | 4-$1,215,214 | |
| 2 | HUNTER INDUSTRIES, LTD. | $2,624,511 | +16.2% | 10.9% | $15,140 | 0 | 5-$1,169,435 |
| 3 | J. CARROLL WEAVER, INC. | $2,639,651 | +16.9% | 11.5% | $388,421 | 0 | 6-$1,309,078 |
| 4 | J E CONSTRUCTION SERVICES, LLC | $3,028,072 | +34.1% | 27.9% | $237,274 | 1+$15,705 | 4-$1,020,936 |
| 5 | SALINAS CONSTRUCTION TECHNOLOGIES, LTD. | $3,265,346 | +44.6% | 38.0% | $4,885 | 2+$206,590 | 4-$1,059,234 |
| 6 | CK NEWBERRY, LLC | $3,270,231 | +44.8% | 38.2% | $315,815 | ||
| 7 | MATAGORDA CONSTRUCTION & MATERIALS | $3,586,046 | +58.8% | 51.5% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
ANDERSON COLUMBIA CO., INC. vs HUNTER INDUSTRIES, LTD., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 276-7121 CEM TRT(PLNT MX)(CL L)(TYA)(GR1-2)(8") | 28,726 SY | $22.00 | $31.01 | $21.95 | $258,821 |
| 500-7001 MOBILIZATION | 1 LS | $124,500.00 | $202,544.31 | $523,850.32 | $78,044 |
| 260-7005 LIME (COM OR QK)(SLURRY) | 604 TON | $260.00 | $363.80 | $295.18 | $62,695 |
| 276-7420 CEM TRT(PLNT MX)(CL L)(TYA)(GR1-2)(15") | 5,289 SY | $50.00 | $58.97 | $50.00 | $47,442 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 5 EA | $10,000.00 | $541.25 | $9,253.78 | -$47,294 |
| 316-7212 AGGR (TY-PB, GR-4S OR 4)(SAC-B) | 420 CY | $225.00 | $124.34 | $125.13 | -$42,277 |
| 530-7002 INTERSECTIONS (ACP) | 1,796 SY | $29.00 | $43.40 | $50.74 | $25,862 |
| 100-7002 PREPARING ROW | 118.36 STA | $100.00 | $303.05 | $6,072.92 | $24,033 |
| 260-7024 LIME TRT(SUBGRADE)(6") | 40,512 SY | $3.25 | $2.75 | $4.59 | -$20,256 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $5,040.00 | $2,018.58 | $11,585.04 | -$18,129 |
| 764-7011 STORM SEWER CLEANING (PIPE)(37"-42"DIA) | 1,492 LF | $20.00 | $10.42 | $7.86 | -$14,293 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 50 CY | $585.00 | $834.43 | $616.83 | $12,472 |
| 316-7263 ASPH (MULTI OPTION) | 25,012 GAL | $2.75 | $3.18 | $3.89 | $10,755 |
| 276-7117 CEM TRT(PLNT MX)(CL L)(TYA)(GR1-2)(6") | 2,244 SY | $19.00 | $23.11 | $20.33 | $9,223 |
| 316-7209 AGGR (TY-PB, GR-3 OR 3S)(SAC-B) | 1,191 CY | $95.00 | $88.47 | $88.78 | -$7,777 |
| 464-7003 RC PIPE (CL III)(18 IN) | 90 LF | $145.00 | $77.59 | $83.08 | -$6,067 |
| 480-7001 CLEAN EXIST CULVERTS | 6 EA | $707.00 | $1,687.68 | $1,712.97 | $5,884 |
| 134-7004 BACKFILL (TY A OR B) | 101 STA | $160.00 | $103.75 | $211.21 | -$5,681 |
| 112-7002 SUBGR WIDEN (DC) | 84 STA | $180.00 | $244.20 | $1,009.03 | $5,393 |
| 250-7002 GEOGRID BASE REINFORCEMENT (TYPE 2) | 39,856 SY | $0.9000 | $1.03 | $1.65 | $5,181 |
Positive: the low bidder was cheaper on that item. These 20 items account for $384,032 of the $366,143 gap.
ANDERSON COLUMBIA CO., INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 316-7212 AGGR (TY-PB, GR-4S OR 4)(SAC-B) | 420 CY | $225.00 | $125.13 | 1.80x | $41,947 |
| 764-7011 STORM SEWER CLEANING (PIPE)(37"-42"DIA) | 1,492 LF | $20.00 | $7.86 | 2.55x | $18,119 |
| 100-7002 PREPARING ROW | 118.36 STA | $100.00 | $6,072.92 | 0.02x | -$706,955 |
| 500-7001 MOBILIZATION | 1 LS | $124,500.00 | $523,850.32 | 0.24x | -$399,350 |
| 112-7002 SUBGR WIDEN (DC) | 84 STA | $180.00 | $1,009.03 | 0.18x | -$69,639 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $5,040.00 | $11,585.04 | 0.44x | -$39,270 |
HUNTER INDUSTRIES, LTD.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 118.36 STA | $303.05 | $6,072.92 | 0.05x | -$682,922 |
| 500-7001 MOBILIZATION | 1 LS | $202,544.31 | $523,850.32 | 0.39x | -$321,306 |
| 112-7002 SUBGR WIDEN (DC) | 84 STA | $244.20 | $1,009.03 | 0.24x | -$64,246 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $2,018.58 | $11,585.04 | 0.17x | -$57,399 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 5 EA | $541.25 | $9,253.78 | 0.06x | -$43,563 |
J. CARROLL WEAVER, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 118.36 STA | $110.00 | $6,072.92 | 0.02x | -$705,771 |
| 500-7001 MOBILIZATION | 1 LS | $111,406.10 | $523,850.32 | 0.21x | -$412,444 |
| 112-7002 SUBGR WIDEN (DC) | 84 STA | $127.99 | $1,009.03 | 0.13x | -$74,008 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $2,420.00 | $11,585.04 | 0.21x | -$54,990 |
| 250-7002 GEOGRID BASE REINFORCEMENT (TYPE 2) | 39,856 SY | $0.7800 | $1.65 | 0.47x | -$34,846 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 5 EA | $3,850.00 | $9,253.78 | 0.42x | -$27,019 |
J E CONSTRUCTION SERVICES, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 662-7008 WK ZN PAV MRK NON-REMOV (W)6"(SLD) | 21,662 LF | $1.00 | $0.2750 | 3.64x | $15,705 |
| 100-7002 PREPARING ROW | 118.36 STA | $650.00 | $6,072.92 | 0.11x | -$641,857 |
| 500-7001 MOBILIZATION | 1 LS | $243,000.00 | $523,850.32 | 0.46x | -$280,850 |
| 112-7002 SUBGR WIDEN (DC) | 84 STA | $310.00 | $1,009.03 | 0.31x | -$58,719 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $5,000.00 | $11,585.04 | 0.43x | -$39,510 |
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 316-7209 AGGR (TY-PB, GR-3 OR 3S)(SAC-B) | 1,191 CY | $196.13 | $88.78 | 2.21x | $127,851 |
| 764-7011 STORM SEWER CLEANING (PIPE)(37"-42"DIA) | 1,492 LF | $60.63 | $7.86 | 7.72x | $78,739 |
| 100-7002 PREPARING ROW | 118.36 STA | $265.46 | $6,072.92 | 0.04x | -$687,371 |
| 500-7001 MOBILIZATION | 1 LS | $260,726.26 | $523,850.32 | 0.50x | -$263,124 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $1,139.52 | $11,585.04 | 0.10x | -$62,673 |
| 112-7002 SUBGR WIDEN (DC) | 84 STA | $460.63 | $1,009.03 | 0.46x | -$46,066 |