FY26 - Bryan AO Tree Removal -03
6497-66-001 · let Mar 10, 2026 · Grimes, Bryan · Routine Maintenance Project
$105,879Low bid: RHINO EQUITY, LLC-17.8% vs estimate $128,750
$529Left on the table0.5% gap to the second bid
4BiddersSpread 97% low to high
12Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | RHINO EQUITY, LLC | $105,879 | -17.8% | $529 | 1+$3,557 | 1-$8,818 | |
| 2 | AUSTIN BARRICADE COMPANY, L.L.C. | $106,408 | +0.5% | -17.4% | $54,942 | 1+$52,113 | 3-$28,398 |
| 3 | ABESCAPE GROUP LLC | $161,350 | +52.4% | 25.3% | $46,900 | 1+$94,613 | 1-$16,243 |
| 4 | GV LANDSCAPE AND CONSTRUCTION LLC | $208,250 | +96.7% | 61.7% | 6+$111,675 | 1-$2,693 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
RHINO EQUITY, LLC vs AUSTIN BARRICADE COMPANY, L.L.C., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 752-7005 TREE REMOVAL (4" - 12" DIA) | 500 EA | $100.00 | $165.00 | $60.77 | $32,500 |
| 752-7006 TREE REMOVAL (12" - 18" DIA) | 200 EA | $115.00 | $70.00 | $100.44 | -$9,000 |
| 505-7001 TMA (STATIONARY) | 75 DAY | $100.00 | $1.00 | $217.57 | -$7,425 |
| 752-7007 TREE REMOVAL (18" - 24" DIA) | 100 EA | $120.00 | $48.00 | $141.37 | -$7,200 |
| 752-7004 STUMP REMOVAL | 25 EA | $300.00 | $45.00 | $157.73 | -$6,375 |
| 752-7008 TREE REMOVAL (24" - 30" DIA) | 15 EA | $125.00 | $55.00 | $208.61 | -$1,050 |
| 752-7009 TREE REMOVAL (30" - 36" DIA) | 10 EA | $150.00 | $60.00 | $293.05 | -$900 |
| 752-7013 TREE REMOVAL (60" - 72" DIA) | 2 EA | $250.00 | $167.00 | $529.99 | -$166 |
| 752-7011 TREE REMOVAL (42" - 48" DIA) | 2 EA | $250.00 | $300.00 | $436.67 | $100 |
| 752-7012 TREE REMOVAL (48" - 60" DIA) | 2 EA | $250.00 | $300.00 | $450.06 | $100 |
| 752-7010 TREE REMOVAL (36" - 42" DIA) | 5 EA | $200.00 | $189.00 | $334.81 | -$55 |
| 500-7002 MOBILIZATION (CALLOUT) | 4 EA | $1.00 | $1.00 | $600.85 | $0 |
Positive: the low bidder was cheaper on that item. These 12 items account for $529 of the $529 gap.
RHINO EQUITY, LLC: unbalanced items
Placed 1AUSTIN BARRICADE COMPANY, L.L.C.: unbalanced items
Placed 2ABESCAPE GROUP LLC: unbalanced items
Placed 3GV LANDSCAPE AND CONSTRUCTION LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 752-7005 TREE REMOVAL (4" - 12" DIA) | 500 EA | $150.00 | $60.77 | 2.47x | $44,613 |
| 752-7006 TREE REMOVAL (12" - 18" DIA) | 200 EA | $250.00 | $100.44 | 2.49x | $29,912 |
| 752-7007 TREE REMOVAL (18" - 24" DIA) | 100 EA | $350.00 | $141.37 | 2.48x | $20,863 |
| 500-7002 MOBILIZATION (CALLOUT) | 4 EA | $3,000.00 | $600.85 | 4.99x | $9,597 |
| 752-7008 TREE REMOVAL (24" - 30" DIA) | 15 EA | $450.00 | $208.61 | 2.16x | $3,621 |
| 752-7009 TREE REMOVAL (30" - 36" DIA) | 10 EA | $600.00 | $293.05 | 2.05x | $3,070 |
| 752-7004 STUMP REMOVAL | 25 EA | $50.00 | $157.73 | 0.32x | -$2,693 |