Bid Tab X-ray: 6497-66-001

Mar 10, 2026 · Grimes Sign up free
Set your company to personalize scores

FY26 - Bryan AO Tree Removal -03

6497-66-001 · let Mar 10, 2026 · Grimes, Bryan · Routine Maintenance Project

$105,879Low bid: RHINO EQUITY, LLC-17.8% vs estimate $128,750
$529Left on the table0.5% gap to the second bid
4BiddersSpread 97% low to high
12Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1RHINO EQUITY, LLC $105,879-17.8% $529 1+$3,557 1-$8,818
2AUSTIN BARRICADE COMPANY, L.L.C. $106,408+0.5%-17.4% $54,942 1+$52,113 3-$28,398
3ABESCAPE GROUP LLC $161,350+52.4%25.3% $46,900 1+$94,613 1-$16,243
4GV LANDSCAPE AND CONSTRUCTION LLC $208,250+96.7%61.7% 6+$111,675 1-$2,693

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.

Where the job was won

RHINO EQUITY, LLC vs AUSTIN BARRICADE COMPANY, L.L.C., biggest item swings
ItemQtyLow2ndMarket2nd minus low
752-7005 TREE REMOVAL (4" - 12" DIA)500 EA $100.00$165.00$60.77 $32,500
752-7006 TREE REMOVAL (12" - 18" DIA)200 EA $115.00$70.00$100.44 -$9,000
505-7001 TMA (STATIONARY)75 DAY $100.00$1.00$217.57 -$7,425
752-7007 TREE REMOVAL (18" - 24" DIA)100 EA $120.00$48.00$141.37 -$7,200
752-7004 STUMP REMOVAL25 EA $300.00$45.00$157.73 -$6,375
752-7008 TREE REMOVAL (24" - 30" DIA)15 EA $125.00$55.00$208.61 -$1,050
752-7009 TREE REMOVAL (30" - 36" DIA)10 EA $150.00$60.00$293.05 -$900
752-7013 TREE REMOVAL (60" - 72" DIA)2 EA $250.00$167.00$529.99 -$166
752-7011 TREE REMOVAL (42" - 48" DIA)2 EA $250.00$300.00$436.67 $100
752-7012 TREE REMOVAL (48" - 60" DIA)2 EA $250.00$300.00$450.06 $100
752-7010 TREE REMOVAL (36" - 42" DIA)5 EA $200.00$189.00$334.81 -$55
500-7002 MOBILIZATION (CALLOUT)4 EA $1.00$1.00$600.85 $0

Positive: the low bidder was cheaper on that item. These 12 items account for $529 of the $529 gap.

RHINO EQUITY, LLC: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
752-7004 STUMP REMOVAL25 EA $300.00$157.731.90x$3,557
505-7001 TMA (STATIONARY)75 DAY $100.00$217.570.46x-$8,818

AUSTIN BARRICADE COMPANY, L.L.C.: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
752-7005 TREE REMOVAL (4" - 12" DIA)500 EA $165.00$60.772.71x$52,113
505-7001 TMA (STATIONARY)75 DAY $1.00$217.570.00x-$16,243
752-7007 TREE REMOVAL (18" - 24" DIA)100 EA $48.00$141.370.34x-$9,337
752-7004 STUMP REMOVAL25 EA $45.00$157.730.29x-$2,818

ABESCAPE GROUP LLC: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
752-7005 TREE REMOVAL (4" - 12" DIA)500 EA $250.00$60.774.11x$94,613
505-7001 TMA (STATIONARY)75 DAY $1.00$217.570.00x-$16,243

GV LANDSCAPE AND CONSTRUCTION LLC: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
752-7005 TREE REMOVAL (4" - 12" DIA)500 EA $150.00$60.772.47x$44,613
752-7006 TREE REMOVAL (12" - 18" DIA)200 EA $250.00$100.442.49x$29,912
752-7007 TREE REMOVAL (18" - 24" DIA)100 EA $350.00$141.372.48x$20,863
500-7002 MOBILIZATION (CALLOUT)4 EA $3,000.00$600.854.99x$9,597
752-7008 TREE REMOVAL (24" - 30" DIA)15 EA $450.00$208.612.16x$3,621
752-7009 TREE REMOVAL (30" - 36" DIA)10 EA $600.00$293.052.05x$3,070
752-7004 STUMP REMOVAL25 EA $50.00$157.730.32x-$2,693