Callout Cable Barrier Repair (N) FY '26

6496-94-001 · let Mar 18, 2026 · Bowie, Atlanta · Routine Maintenance Project

$634,438Low bid: H. V. CAVER, INC.+4.5% vs estimate $607,300
$104,033Left on the table16.4% gap to the second bid
2BiddersSpread 16% low to high
22Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1H. V. CAVER, INC. $634,4384.5% $104,033 2+$53,033 5-$106,084
2AUSTIN BARRICADE COMPANY, L.L.C. $738,470+16.4%21.6% 2+$81,905 6-$173,836

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.

Where the job was won

H. V. CAVER, INC. vs AUSTIN BARRICADE COMPANY, L.L.C., biggest item swings
ItemQtyLow2ndMarket2nd minus low
771-7002 REPLACE POSTS (TL-3)(NU-CABLE)2,000 EA $127.75$200.00$121.06 $144,500
771-7013 REPR OR REPLC CABLE BARR TERM SEC(TL-3)45 EA $1,200.00$2,600.00$971.01 $63,000
505-7001 TMA (STATIONARY)200 DAY $200.00$1.00$217.57 -$39,800
771-7007 REPLACE POSTS (TL-4)(TRINITY)250 EA $251.00$100.00$144.70 -$37,750
771-7003 REPLACE POSTS (TL-3)(TRINITY)250 EA $223.00$100.00$60.40 -$30,750
500-7002 MOBILIZATION (CALLOUT)25 EA $50.00$1,000.00$600.85 $23,750
771-7005 REPLACE POSTS (TL-4)(GIBRALTAR)250 EA $147.50$77.00$159.54 -$17,625
771-7019 REPLACE POST HARDWARE (TL-3)250 EA $60.75$130.00$115.33 $17,313
771-7020 REPLACE POST HARDWARE (TL-4)250 EA $60.75$1.00$11.22 -$14,938
771-7014 REPR OR REPLC CABLE BARR TERM SEC(TL-4)20 EA $600.00$1.00$1,019.22 -$11,980
505-7002 TMA (MOBILE OPERATION)100 HR $50.00$150.00$64.00 $10,000
771-7009 CABLE SPLICE / TURNBUCKLE (TL-3)25 EA $300.00$100.00$217.53 -$5,000
771-7015 REPLACE CABLE (TL-3)1,000 LF $1.00$5.00$6.19 $4,000
771-7010 CABLE SPLICE / TURNBUCKLE (TL-4)10 EA $300.00$100.00$88.10 -$2,000
771-7016 REPLACE CABLE (TL-4)500 LF $1.00$5.00$2.15 $2,000
771-7017 CHECK / RE-TENSION CABLE (TL-3)300 EA $5.00$1.00$44.22 -$1,200
771-7018 CHECK / RE-TENSION CABLE (TL-4)300 EA $5.00$1.00$67.25 -$1,200
771-7001 REPLACE POSTS (TL-3)(GIBRALTAR)250 EA $125.75$129.00$116.37 $813
771-7011 REPAIR CONCRETE FOUNDATION (TL-3)20 EA $50.00$80.00$52.78 $600
771-7012 REPAIR CONCRETE FOUNDATION (TL-4)10 EA $50.00$80.00$68.08 $300

Positive: the low bidder was cheaper on that item. These 20 items account for $104,033 of the $104,033 gap.

H. V. CAVER, INC.: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
771-7003 REPLACE POSTS (TL-3)(TRINITY)250 EA $223.00$60.403.69x$40,650
771-7020 REPLACE POST HARDWARE (TL-4)250 EA $60.75$11.225.42x$12,383
432-7013 RIPRAP (MOW STRIP)(4 IN)100 CY $50.00$616.830.08x-$56,683
771-7018 CHECK / RE-TENSION CABLE (TL-4)300 EA $5.00$67.250.07x-$18,676
500-7002 MOBILIZATION (CALLOUT)25 EA $50.00$600.850.08x-$13,771
771-7017 CHECK / RE-TENSION CABLE (TL-3)300 EA $5.00$44.220.11x-$11,765
771-7015 REPLACE CABLE (TL-3)1,000 LF $1.00$6.190.16x-$5,189

AUSTIN BARRICADE COMPANY, L.L.C.: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
771-7013 REPR OR REPLC CABLE BARR TERM SEC(TL-3)45 EA $2,600.00$971.012.68x$73,304
505-7002 TMA (MOBILE OPERATION)100 HR $150.00$64.002.34x$8,600
432-7013 RIPRAP (MOW STRIP)(4 IN)100 CY $50.00$616.830.08x-$56,683
505-7001 TMA (STATIONARY)200 DAY $1.00$217.570.00x-$43,314
771-7005 REPLACE POSTS (TL-4)(GIBRALTAR)250 EA $77.00$159.540.48x-$20,634
771-7014 REPR OR REPLC CABLE BARR TERM SEC(TL-4)20 EA $1.00$1,019.220.00x-$20,364
771-7018 CHECK / RE-TENSION CABLE (TL-4)300 EA $1.00$67.250.01x-$19,876
771-7017 CHECK / RE-TENSION CABLE (TL-3)300 EA $1.00$44.220.02x-$12,965