Callout Cable Barrier Repair (N) FY '26
6496-94-001 · let Mar 18, 2026 · Bowie, Atlanta · Routine Maintenance Project
$634,438Low bid: H. V. CAVER, INC.+4.5% vs estimate $607,300
$104,033Left on the table16.4% gap to the second bid
2BiddersSpread 16% low to high
22Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | H. V. CAVER, INC. | $634,438 | 4.5% | $104,033 | 2+$53,033 | 5-$106,084 | |
| 2 | AUSTIN BARRICADE COMPANY, L.L.C. | $738,470 | +16.4% | 21.6% | 2+$81,905 | 6-$173,836 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
H. V. CAVER, INC. vs AUSTIN BARRICADE COMPANY, L.L.C., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 771-7002 REPLACE POSTS (TL-3)(NU-CABLE) | 2,000 EA | $127.75 | $200.00 | $121.06 | $144,500 |
| 771-7013 REPR OR REPLC CABLE BARR TERM SEC(TL-3) | 45 EA | $1,200.00 | $2,600.00 | $971.01 | $63,000 |
| 505-7001 TMA (STATIONARY) | 200 DAY | $200.00 | $1.00 | $217.57 | -$39,800 |
| 771-7007 REPLACE POSTS (TL-4)(TRINITY) | 250 EA | $251.00 | $100.00 | $144.70 | -$37,750 |
| 771-7003 REPLACE POSTS (TL-3)(TRINITY) | 250 EA | $223.00 | $100.00 | $60.40 | -$30,750 |
| 500-7002 MOBILIZATION (CALLOUT) | 25 EA | $50.00 | $1,000.00 | $600.85 | $23,750 |
| 771-7005 REPLACE POSTS (TL-4)(GIBRALTAR) | 250 EA | $147.50 | $77.00 | $159.54 | -$17,625 |
| 771-7019 REPLACE POST HARDWARE (TL-3) | 250 EA | $60.75 | $130.00 | $115.33 | $17,313 |
| 771-7020 REPLACE POST HARDWARE (TL-4) | 250 EA | $60.75 | $1.00 | $11.22 | -$14,938 |
| 771-7014 REPR OR REPLC CABLE BARR TERM SEC(TL-4) | 20 EA | $600.00 | $1.00 | $1,019.22 | -$11,980 |
| 505-7002 TMA (MOBILE OPERATION) | 100 HR | $50.00 | $150.00 | $64.00 | $10,000 |
| 771-7009 CABLE SPLICE / TURNBUCKLE (TL-3) | 25 EA | $300.00 | $100.00 | $217.53 | -$5,000 |
| 771-7015 REPLACE CABLE (TL-3) | 1,000 LF | $1.00 | $5.00 | $6.19 | $4,000 |
| 771-7010 CABLE SPLICE / TURNBUCKLE (TL-4) | 10 EA | $300.00 | $100.00 | $88.10 | -$2,000 |
| 771-7016 REPLACE CABLE (TL-4) | 500 LF | $1.00 | $5.00 | $2.15 | $2,000 |
| 771-7017 CHECK / RE-TENSION CABLE (TL-3) | 300 EA | $5.00 | $1.00 | $44.22 | -$1,200 |
| 771-7018 CHECK / RE-TENSION CABLE (TL-4) | 300 EA | $5.00 | $1.00 | $67.25 | -$1,200 |
| 771-7001 REPLACE POSTS (TL-3)(GIBRALTAR) | 250 EA | $125.75 | $129.00 | $116.37 | $813 |
| 771-7011 REPAIR CONCRETE FOUNDATION (TL-3) | 20 EA | $50.00 | $80.00 | $52.78 | $600 |
| 771-7012 REPAIR CONCRETE FOUNDATION (TL-4) | 10 EA | $50.00 | $80.00 | $68.08 | $300 |
Positive: the low bidder was cheaper on that item. These 20 items account for $104,033 of the $104,033 gap.
H. V. CAVER, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 771-7003 REPLACE POSTS (TL-3)(TRINITY) | 250 EA | $223.00 | $60.40 | 3.69x | $40,650 |
| 771-7020 REPLACE POST HARDWARE (TL-4) | 250 EA | $60.75 | $11.22 | 5.42x | $12,383 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 100 CY | $50.00 | $616.83 | 0.08x | -$56,683 |
| 771-7018 CHECK / RE-TENSION CABLE (TL-4) | 300 EA | $5.00 | $67.25 | 0.07x | -$18,676 |
| 500-7002 MOBILIZATION (CALLOUT) | 25 EA | $50.00 | $600.85 | 0.08x | -$13,771 |
| 771-7017 CHECK / RE-TENSION CABLE (TL-3) | 300 EA | $5.00 | $44.22 | 0.11x | -$11,765 |
| 771-7015 REPLACE CABLE (TL-3) | 1,000 LF | $1.00 | $6.19 | 0.16x | -$5,189 |
AUSTIN BARRICADE COMPANY, L.L.C.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 771-7013 REPR OR REPLC CABLE BARR TERM SEC(TL-3) | 45 EA | $2,600.00 | $971.01 | 2.68x | $73,304 |
| 505-7002 TMA (MOBILE OPERATION) | 100 HR | $150.00 | $64.00 | 2.34x | $8,600 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 100 CY | $50.00 | $616.83 | 0.08x | -$56,683 |
| 505-7001 TMA (STATIONARY) | 200 DAY | $1.00 | $217.57 | 0.00x | -$43,314 |
| 771-7005 REPLACE POSTS (TL-4)(GIBRALTAR) | 250 EA | $77.00 | $159.54 | 0.48x | -$20,634 |
| 771-7014 REPR OR REPLC CABLE BARR TERM SEC(TL-4) | 20 EA | $1.00 | $1,019.22 | 0.00x | -$20,364 |
| 771-7018 CHECK / RE-TENSION CABLE (TL-4) | 300 EA | $1.00 | $67.25 | 0.01x | -$19,876 |
| 771-7017 CHECK / RE-TENSION CABLE (TL-3) | 300 EA | $1.00 | $44.22 | 0.02x | -$12,965 |