BPM 6493-02-001
6493-02-001 · let Mar 10, 2026 · Fort Bend, Houston · Bridge Preventative Maintenance - Sealed
$329,415Low bid: ISI CONTRACTING, INC.-5.8% vs estimate $349,670
$92,160Left on the table28.0% gap to the second bid
5BiddersSpread 72% low to high
22Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ISI CONTRACTING, INC. | $329,415 | -5.8% | $92,160 | 1+$6,340 | 2-$23,785 | |
| 2 | AAD CONTRACTING INC. | $421,575 | +28.0% | 20.6% | $8,125 | 8+$132,028 | 2-$40,123 |
| 3 | GARRET SHIELDS INFRASTRUCTURE | $429,700 | +30.4% | 22.9% | $1,050 | 4+$41,455 | 0 |
| 4 | MC2 CIVIL, LLC | $430,750 | +30.8% | 23.2% | $136,950 | 3+$31,043 | 1-$7,161 |
| 5 | STRUCTURAL INTEGRITY GROUP LLC | $567,700 | +72.3% | 62.4% | 6+$193,085 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
ISI CONTRACTING, INC. vs AAD CONTRACTING INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 200 SF | $174.00 | $350.00 | $192.68 | $35,200 |
| 438-7007 CLEANING AND SEALING EXIST JOINTS (CL7) | 600 LF | $50.00 | $95.00 | $38.57 | $27,000 |
| 454-7006 SEALED EXPANSION JOINT (4 IN) (SEJ - B) | 100 LF | $100.00 | $285.00 | $158.57 | $18,500 |
| 361-7005 FULL - DEPTH REPAIR CRCP (10") | 20 CY | $1,300.00 | $510.00 | $1,202.68 | -$15,800 |
| 361-7010 FULL - DEPTH REPAIR CRCP (15") | 25 CY | $1,200.00 | $625.00 | $1,044.24 | -$14,375 |
| 400-7010 CEM STABIL BKFL | 100 CY | $118.00 | $250.00 | $138.14 | $13,200 |
| 361-7007 FULL - DEPTH REPAIR CRCP (12") | 20 CY | $1,200.00 | $560.00 | $905.39 | -$12,800 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 150 SF | $175.00 | $250.00 | $150.68 | $11,250 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 200 SF | $148.00 | $200.00 | $95.74 | $10,400 |
| 438-7008 CLEANING EXISTING JOINTS | 1,000 LF | $20.00 | $10.00 | $16.75 | -$10,000 |
| 500-7002 MOBILIZATION (CALLOUT) | 13 EA | $265.00 | $1,000.00 | $600.85 | $9,555 |
| 432-7055 RIPRAP (CONC)(CL B)(RR8&RR9) | 50 CY | $337.00 | $200.00 | $725.38 | -$6,850 |
| 3010-7001 RAIS AND UNDERSEAL CONC SLBS W FOAM SYS | 2,000 LB | $7.00 | $10.00 | $3.83 | $6,000 |
| 432-7033 RIPRAP (STONE COMMON)(DRY)(18 IN) | 50 CY | $178.00 | $280.00 | $187.68 | $5,100 |
| 505-7001 TMA (STATIONARY) | 32 DAY | $200.00 | $350.00 | $217.57 | $4,800 |
| 432-7031 RIPRAP (STONE COMMON)(DRY)(12 IN) | 50 CY | $86.00 | $175.00 | $152.41 | $4,450 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 21 DAY | $170.00 | $350.00 | $87.82 | $3,780 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 100 CY | $30.00 | $55.00 | $13.19 | $2,500 |
| 401-7001 FLOWABLE BACKFILL | 50 CY | $295.00 | $250.00 | $298.77 | -$2,250 |
| 500-7033 MOBILIZATION (EMERGENCY) | 2 EA | $500.00 | $1,500.00 | $844.81 | $2,000 |
Positive: the low bidder was cheaper on that item. These 20 items account for $91,660 of the $92,160 gap.
ISI CONTRACTING, INC.: unbalanced items
Placed 1AAD CONTRACTING INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 438-7007 CLEANING AND SEALING EXIST JOINTS (CL7) | 600 LF | $95.00 | $38.57 | 2.46x | $33,857 |
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 200 SF | $350.00 | $192.68 | 1.82x | $31,464 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 200 SF | $200.00 | $95.74 | 2.09x | $20,851 |
| 454-7006 SEALED EXPANSION JOINT (4 IN) (SEJ - B) | 100 LF | $285.00 | $158.57 | 1.80x | $12,643 |
| 3010-7001 RAIS AND UNDERSEAL CONC SLBS W FOAM SYS | 2,000 LB | $10.00 | $3.83 | 2.61x | $12,340 |
| 400-7010 CEM STABIL BKFL | 100 CY | $250.00 | $138.14 | 1.81x | $11,186 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 21 DAY | $350.00 | $87.82 | 3.99x | $5,506 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 100 CY | $55.00 | $13.19 | 4.17x | $4,181 |
| 432-7055 RIPRAP (CONC)(CL B)(RR8&RR9) | 50 CY | $200.00 | $725.38 | 0.28x | -$26,269 |
| 361-7005 FULL - DEPTH REPAIR CRCP (10") | 20 CY | $510.00 | $1,202.68 | 0.42x | -$13,854 |
GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 400-7010 CEM STABIL BKFL | 100 CY | $300.00 | $138.14 | 2.17x | $16,186 |
| 438-7008 CLEANING EXISTING JOINTS | 1,000 LF | $30.00 | $16.75 | 1.79x | $13,248 |
| 3010-7001 RAIS AND UNDERSEAL CONC SLBS W FOAM SYS | 2,000 LB | $8.00 | $3.83 | 2.09x | $8,340 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 100 CY | $50.00 | $13.19 | 3.79x | $3,681 |
MC2 CIVIL, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 361-7007 FULL - DEPTH REPAIR CRCP (12") | 20 CY | $1,675.00 | $905.39 | 1.85x | $15,392 |
| 3010-7001 RAIS AND UNDERSEAL CONC SLBS W FOAM SYS | 2,000 LB | $10.00 | $3.83 | 2.61x | $12,340 |
| 500-7033 MOBILIZATION (EMERGENCY) | 2 EA | $2,500.00 | $844.81 | 2.96x | $3,310 |
| 500-7002 MOBILIZATION (CALLOUT) | 13 EA | $50.00 | $600.85 | 0.08x | -$7,161 |
STRUCTURAL INTEGRITY GROUP LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 454-7006 SEALED EXPANSION JOINT (4 IN) (SEJ - B) | 100 LF | $1,085.00 | $158.57 | 6.84x | $92,643 |
| 454-7004 SEALED EXPANSION JOINT (4 IN) (SEJ - M) | 50 LF | $1,230.00 | $221.89 | 5.54x | $50,405 |
| 400-7010 CEM STABIL BKFL | 100 CY | $310.00 | $138.14 | 2.24x | $17,186 |
| 3010-7001 RAIS AND UNDERSEAL CONC SLBS W FOAM SYS | 2,000 LB | $12.00 | $3.83 | 3.13x | $16,340 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 100 CY | $100.00 | $13.19 | 7.58x | $8,681 |
| 432-7031 RIPRAP (STONE COMMON)(DRY)(12 IN) | 50 CY | $309.00 | $152.41 | 2.03x | $7,829 |