SS 348 at IH 35E NB
0581-02-156 · let Mar 4, 2026 · Dallas, Dallas · Bridge Replacement
$16,606,597Low bid: HIGHWAY 19 CONSTRUCTION LLC+2.7% vs estimate $16,165,949
$249,419Left on the table1.5% gap to the second bid
9BiddersSpread 50% low to high
184Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | HIGHWAY 19 CONSTRUCTION LLC | $16,606,597 | 2.7% | $249,419 | 5+$2,159,524 | 2-$452,794 | |
| 2 | R CONSTRUCTION CIVIL, LLC | $16,856,015 | +1.5% | 4.3% | $380,214 | 7+$2,725,582 | 1-$92,495 |
| 3 | INDUS ROAD & BRIDGE, INC. | $17,236,229 | +3.8% | 6.6% | $91,188 | 5+$3,156,655 | 0 |
| 4 | ALTUS CONSTRUCTION LLC | $17,327,418 | +4.3% | 7.2% | $1,198,524 | 7+$4,191,440 | 1-$209,922 |
| 5 | HARPER BROTHERS CONSTRUCTION LLC | $18,525,942 | +11.6% | 14.6% | $706,084 | 8+$4,870,471 | 1-$94,382 |
| 6 | RAGLE CONSTRUCTION, INC. | $19,232,026 | +15.8% | 19.0% | $719,703 | ||
| 7 | WEBBER, LLC | $19,951,728 | +20.1% | 23.4% | $1,463,677 | ||
| 8 | ED BELL CONSTRUCTION COMPANY | $21,415,405 | +29.0% | 32.5% | $3,415,918 | ||
| 9 | COPASA INC | $24,831,323 | +49.5% | 53.6% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
HIGHWAY 19 CONSTRUCTION LLC vs R CONSTRUCTION CIVIL, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 423-7001 RETAINING WALL (MSE) | 34,821 SF | $85.00 | $60.00 | $74.07 | -$870,525 |
| 4052-7001 STONE COLUMNS (30 IN) | 21,270 LF | $10.00 | $41.00 | $22.93 | $659,370 |
| 416-7007 DRILL SHAFT (42 IN) | 1,706 LF | $650.00 | $420.00 | $318.92 | -$392,380 |
| 496-7007 REMOV STR (PIPE) | 326 LF | $50.00 | $1,150.00 | $23.96 | $358,600 |
| 512-7005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) | 6,060 LF | $75.00 | $21.00 | $40.65 | -$327,240 |
| 403-7001 TEMPORARY SPL SHORING | 16,064 SF | $35.00 | $54.00 | $25.56 | $305,216 |
| 100-7002 PREPARING ROW | 30.1 STA | $10,000.00 | $3,000.00 | $6,072.92 | -$210,700 |
| 132-7010 EMBANK (FNL)(DC)(TY C2) | 37,062 CY | $18.00 | $22.00 | $22.38 | $148,248 |
| 420-7052 CL C CONC (RAIL FOUNDATION) | 274 CY | $1,000.00 | $460.00 | $552.17 | -$147,960 |
| 110-7001 EXCAV (ROADWAY) | 18,069 CY | $15.00 | $22.00 | $11.68 | $126,483 |
| 425-7006 PRESTR CONC GIRDER (TX62) | 3,061.8 LF | $277.00 | $240.00 | $189.94 | -$113,287 |
| 344-7007 SP MIXES SP-B PG76-22 | 6,896 TON | $134.00 | $150.00 | $134.00 | $110,336 |
| 247-7079 FL BS (CMP IN PLC)(TY D GR 1-2) (8") | 12,535 SY | $25.00 | $33.00 | $23.14 | $100,280 |
| 500-7001 MOBILIZATION | 1 LS | $1,700,000.00 | $1,600,000.00 | $523,850.32 | -$100,000 |
| 168-7001 VEGETATIVE WATERING | 5,873 TGL | $20.00 | $36.00 | $8.43 | $93,968 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 27 MO | $5,000.00 | $8,400.00 | $11,585.04 | $91,800 |
| 677-7004 ELIM EXT PM & MRKS (8") | 705 LF | $125.00 | $2.00 | $0.6468 | -$86,715 |
| 450-7025 RAIL (TY SSTR)(HPC) | 2,285.9 LF | $160.00 | $125.00 | $96.82 | -$80,007 |
| 556-7008 PIPE UNDERDRAINS (TY 8) (6") | 1,900 LF | $15.00 | $55.00 | $32.77 | $76,000 |
| 514-7017 PERM CTB (F-SHAPE) (MOD) | 336 LF | $180.00 | $400.00 | $180.00 | $73,920 |
Positive: the low bidder was cheaper on that item. These 20 items account for -$184,592 of the $249,419 gap.
HIGHWAY 19 CONSTRUCTION LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,700,000.00 | $523,850.32 | 3.25x | $1,176,150 |
| 416-7007 DRILL SHAFT (42 IN) | 1,706 LF | $650.00 | $318.92 | 2.04x | $564,824 |
| 512-7005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) | 6,060 LF | $75.00 | $40.65 | 1.85x | $208,176 |
| 420-7052 CL C CONC (RAIL FOUNDATION) | 274 CY | $1,000.00 | $552.17 | 1.81x | $122,706 |
| 677-7004 ELIM EXT PM & MRKS (8") | 705 LF | $125.00 | $0.6468 | 193.26x | $87,669 |
| 4052-7001 STONE COLUMNS (30 IN) | 21,270 LF | $10.00 | $22.93 | 0.44x | -$274,998 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 27 MO | $5,000.00 | $11,585.04 | 0.43x | -$177,796 |
R CONSTRUCTION CIVIL, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,600,000.00 | $523,850.32 | 3.05x | $1,076,150 |
| 403-7001 TEMPORARY SPL SHORING | 16,064 SF | $54.00 | $25.56 | 2.11x | $456,851 |
| 4052-7001 STONE COLUMNS (30 IN) | 21,270 LF | $41.00 | $22.93 | 1.79x | $384,372 |
| 496-7007 REMOV STR (PIPE) | 326 LF | $1,150.00 | $23.96 | 47.99x | $367,088 |
| 110-7001 EXCAV (ROADWAY) | 18,069 CY | $22.00 | $11.68 | 1.88x | $186,432 |
| 168-7001 VEGETATIVE WATERING | 5,873 TGL | $36.00 | $8.43 | 4.27x | $161,897 |
| 104-7001 REMOV CONC (PAV) | 2,799 SY | $45.00 | $11.85 | 3.80x | $92,792 |
| 100-7002 PREPARING ROW | 30.1 STA | $3,000.00 | $6,072.92 | 0.49x | -$92,495 |
INDUS ROAD & BRIDGE, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,721,285.98 | $523,850.32 | 3.29x | $1,197,436 |
| 132-7010 EMBANK (FNL)(DC)(TY C2) | 37,062 CY | $53.00 | $22.38 | 2.37x | $1,134,894 |
| 403-7001 TEMPORARY SPL SHORING | 16,064 SF | $50.00 | $25.56 | 1.96x | $392,595 |
| 100-7002 PREPARING ROW | 30.1 STA | $13,500.00 | $6,072.92 | 2.22x | $223,555 |
| 512-7005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) | 6,060 LF | $75.00 | $40.65 | 1.85x | $208,176 |
ALTUS CONSTRUCTION LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 30.1 STA | $56,991.20 | $6,072.92 | 9.38x | $1,532,640 |
| 500-7001 MOBILIZATION | 1 LS | $1,724,098.94 | $523,850.32 | 3.29x | $1,200,249 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 27 MO | $32,088.20 | $11,585.04 | 2.77x | $553,585 |
| 403-7001 TEMPORARY SPL SHORING | 16,064 SF | $47.16 | $25.56 | 1.84x | $346,892 |
| 508-7001 CONSTRUCTING DETOURS | 3,094 SY | $148.91 | $83.58 | 1.78x | $202,125 |
| 161-7002 COMPOST MANUF TOPSOIL (4") | 20,905 SY | $10.47 | $1.95 | 5.38x | $178,261 |
| 110-7001 EXCAV (ROADWAY) | 18,069 CY | $21.52 | $11.68 | 1.84x | $177,687 |
| 512-7005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) | 6,060 LF | $6.01 | $40.65 | 0.15x | -$209,922 |
HARPER BROTHERS CONSTRUCTION LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,850,000.00 | $523,850.32 | 3.53x | $1,326,150 |
| 132-7010 EMBANK (FNL)(DC)(TY C2) | 37,062 CY | $50.00 | $22.38 | 2.23x | $1,023,708 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 27 MO | $37,000.00 | $11,585.04 | 3.19x | $686,204 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $650,350.00 | $136,676.66 | 4.76x | $513,673 |
| 416-7007 DRILL SHAFT (42 IN) | 1,706 LF | $600.00 | $318.92 | 1.88x | $479,524 |
| 4052-7001 STONE COLUMNS (30 IN) | 21,270 LF | $45.00 | $22.93 | 1.96x | $469,452 |
| 512-7005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) | 6,060 LF | $85.00 | $40.65 | 2.09x | $268,776 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 4 EA | $35,000.00 | $9,253.78 | 3.78x | $102,985 |
| 505-7001 TMA (STATIONARY) | 662 DAY | $75.00 | $217.57 | 0.34x | -$94,382 |