SH 171; Fr W Owen St to S of BB Fielder
0365-01-055 · let Mar 5, 2026 · Parker, Fort Worth · Rehabilitation of Existing Road
$1,234,417Low bid: O. TREVINO CONSTRUCTION, LLC-46.9% vs estimate $2,323,830
$158,014Left on the table12.8% gap to the second bid
4BiddersSpread 88% low to high
82Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | O. TREVINO CONSTRUCTION, LLC | $1,234,417 | -46.9% | $158,014 | 2+$63,038 | 2-$826,427 | |
| 2 | EMERY SAPP & SON'S INC. | $1,392,432 | +12.8% | -40.1% | $212,122 | 3+$56,206 | 3-$690,838 |
| 3 | SELECT MAINTENANCE, L.L.C. | $1,604,554 | +30.0% | -31.0% | $719,277 | 4+$188,708 | 4-$755,780 |
| 4 | DIAMOND SURFACE, INC. | $2,323,830 | +88.3% | 0.0% | 5+$582,876 | 1-$405,319 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
O. TREVINO CONSTRUCTION, LLC vs EMERY SAPP & SON'S INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $120,000.00 | $247,000.00 | $523,850.32 | $127,000 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $24,525.00 | $2,420.00 | $11,585.04 | -$66,315 |
| 3017-7001 CONTINUOUS GRINDING-CONCRETE PAVEMENT | 77,648 SY | $5.75 | $5.00 | $6.23 | -$58,236 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 31,378 LF | $2.45 | $3.60 | $15.92 | $36,085 |
| 361-7006 FULL - DEPTH REPAIR CRCP (11") | 125 CY | $972.00 | $1,240.00 | $731.43 | $33,500 |
| 361-7004 FULL - DEPTH REPAIR CRCP (9") | 125 CY | $989.00 | $1,220.00 | $704.20 | $28,875 |
| 720-7001 SPALLING REPAIR (HYDRAULIC CEMENT) | 100 CF | $305.00 | $480.00 | $206.00 | $17,500 |
| 505-7001 TMA (STATIONARY) | 28 DAY | $175.00 | $625.00 | $217.57 | $12,600 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 4 EA | $5,000.00 | $7,000.00 | $9,253.78 | $8,000 |
| 505-7003 TMA (MOBILE OPERATION) | 44 DAY | $780.00 | $625.00 | $229.60 | -$6,820 |
| 666-7244 RE PM TY III (W)(24")(SLD) | 4,560 LF | $7.50 | $8.40 | $7.96 | $4,104 |
| 666-7248 RE PM TY III (Y)(6")(SLD) | 27,379 LF | $0.7000 | $0.8000 | $0.7409 | $2,738 |
| 666-7257 RE PM TY III (W)(WORD) | 68 EA | $260.50 | $300.00 | $274.97 | $2,686 |
| 666-7347 PAVEMENT SLER 6" | 56,376 LF | $0.1100 | $0.1500 | $0.1841 | $2,255 |
| 678-7002 PAV SURF PREP FOR MRK (6") | 56,376 LF | $0.1100 | $0.1500 | $0.0662 | $2,255 |
| 666-7254 RE PM TY III (W)(ARROW) | 69 EA | $234.00 | $263.00 | $239.01 | $2,001 |
| 666-7236 RE PM TY III (W)(6")(SLD) | 15,338 LF | $0.7000 | $0.8000 | $0.6919 | $1,534 |
| 666-7262 RE PM TY III (BLK)(6")(SHADOW) | 6,828 LF | $1.25 | $1.40 | $0.7183 | $1,024 |
| 666-7239 RE PM TY III (W)(8")(SLD) | 10,095 LF | $1.10 | $1.20 | $1.06 | $1,010 |
| 666-7242 RE PM TY III (W)(12")(SLD) | 1,771 LF | $4.25 | $4.80 | $2.62 | $974 |
Positive: the low bidder was cheaper on that item. These 20 items account for $152,769 of the $158,014 gap.
O. TREVINO CONSTRUCTION, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $24,525.00 | $11,585.04 | 2.12x | $38,820 |
| 505-7003 TMA (MOBILE OPERATION) | 44 DAY | $780.00 | $229.60 | 3.40x | $24,218 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 31,378 LF | $2.45 | $15.92 | 0.15x | -$422,577 |
| 500-7001 MOBILIZATION | 1 LS | $120,000.00 | $523,850.32 | 0.23x | -$403,850 |
EMERY SAPP & SON'S INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 720-7001 SPALLING REPAIR (HYDRAULIC CEMENT) | 100 CF | $480.00 | $206.00 | 2.33x | $27,400 |
| 505-7003 TMA (MOBILE OPERATION) | 44 DAY | $625.00 | $229.60 | 2.72x | $17,398 |
| 505-7001 TMA (STATIONARY) | 28 DAY | $625.00 | $217.57 | 2.87x | $11,408 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 31,378 LF | $3.60 | $15.92 | 0.23x | -$386,492 |
| 500-7001 MOBILIZATION | 1 LS | $247,000.00 | $523,850.32 | 0.47x | -$276,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $2,420.00 | $11,585.04 | 0.21x | -$27,495 |
SELECT MAINTENANCE, L.L.C.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $45,000.00 | $11,585.04 | 3.88x | $100,245 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 4 EA | $23,750.00 | $9,253.78 | 2.57x | $57,985 |
| 720-7001 SPALLING REPAIR (HYDRAULIC CEMENT) | 100 CF | $425.00 | $206.00 | 2.06x | $21,900 |
| 677-7006 ELIM EXT PM & MRKS (12") | 3,147 LF | $4.00 | $1.27 | 3.14x | $8,579 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 31,378 LF | $4.00 | $15.92 | 0.25x | -$373,941 |
| 500-7001 MOBILIZATION | 1 LS | $160,000.00 | $523,850.32 | 0.31x | -$363,850 |
| 666-7347 PAVEMENT SLER 6" | 56,376 LF | $0.0100 | $0.1841 | 0.05x | -$9,815 |
| 666-7352 PAVEMENT SLER 24" | 4,679 LF | $0.0900 | $1.84 | 0.05x | -$8,174 |
DIAMOND SURFACE, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 3017-7001 CONTINUOUS GRINDING-CONCRETE PAVEMENT | 77,648 SY | $11.51 | $6.23 | 1.85x | $410,020 |
| 361-7004 FULL - DEPTH REPAIR CRCP (9") | 125 CY | $1,281.25 | $704.20 | 1.82x | $72,131 |
| 505-7003 TMA (MOBILE OPERATION) | 44 DAY | $1,800.00 | $229.60 | 7.84x | $69,098 |
| 720-7001 SPALLING REPAIR (HYDRAULIC CEMENT) | 100 CF | $393.75 | $206.00 | 1.91x | $18,775 |
| 505-7001 TMA (STATIONARY) | 28 DAY | $676.56 | $217.57 | 3.11x | $12,852 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 31,378 LF | $3.00 | $15.92 | 0.19x | -$405,319 |