RPM 07 0325
6481-69-001 · let Mar 11, 2026 · Collin, Dallas · Routine Maintenance Project - Sealed
$214,195Low bid: THE CONFIDENCE GROUP, INC-40.9% vs estimate $362,560
$42,444Left on the table19.8% gap to the second bid
2BiddersSpread 20% low to high
6Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | THE CONFIDENCE GROUP, INC | $214,195 | -40.9% | $42,444 | 0 | 3-$604,475 | |
| 2 | TRP INFRASTRUCTURE SERVICES, LLC | $256,639 | +19.8% | -29.2% | 0 | 3-$602,476 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
THE CONFIDENCE GROUP, INC vs TRP INFRASTRUCTURE SERVICES, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 672-7006 REFL PAV MRKR TY II-C-R | 48,800 EA | $4.00 | $4.75 | $4.19 | $36,600 |
| 672-7004 REFL PAV MRKR TY II-A-A | 3,460 EA | $4.00 | $4.75 | $3.97 | $2,595 |
| 500-7001 MOBILIZATION | 1 LS | $1.00 | $2,000.00 | $523,850.32 | $1,999 |
| 672-7002 REFL PAV MRKR TY I-C | 1,250 EA | $4.00 | $5.00 | $4.04 | $1,250 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $1.00 | $1.00 | $11,585.04 | $0 |
| 505-7003 TMA (MOBILE OPERATION) | 150 DAY | $1.00 | $1.00 | $229.60 | $0 |
Positive: the low bidder was cheaper on that item. These 6 items account for $42,444 of the $42,444 gap.