FY27 - Brenham AO Emulsion - 09
6507-16-001 · let Sep 16, 2026 · Washington, Bryan · Material Maintenance Project
$150,600Low bid: ERGON ASPHALT & EMULSIONS, INC.-10.4% vs estimate $168,000
$20,400Left on the table13.5% gap to the second bid
2BiddersSpread 14% low to high
3Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ERGON ASPHALT & EMULSIONS, INC. | $150,600 | -10.4% | $20,400 | 0 | 0 | |
| 2 | WRIGHT ASPHALT PRODUCTS COMPANY LLC | $171,000 | +13.5% | 1.8% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
ERGON ASPHALT & EMULSIONS, INC. vs WRIGHT ASPHALT PRODUCTS COMPANY LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8003-7114 CRS-2P (DEL)(SITE 1) | 20,000 GAL | $2.51 | $2.85 | $2.78 | $6,800 |
| 8003-7139 CHFRS-2P (DEL)(SITE 2) | 20,000 GAL | $2.51 | $2.85 | $2.91 | $6,800 |
| 8003-7140 CHFRS-2P (DEL)(SITE 3) | 20,000 GAL | $2.51 | $2.85 | $2.54 | $6,800 |
Positive: the low bidder was cheaper on that item. These 3 items account for $20,400 of the $20,400 gap.