FY27 - Brenham AO Cutback - 09
6506-99-001 · let Sep 16, 2026 · Washington, Bryan · Material Maintenance Project
$91,440Low bid: MARTIN RESOURCE MANAGEMENT CORPORATION+3.0% vs estimate $88,800
$11,760Left on the table12.9% gap to the second bid
3BiddersSpread 21% low to high
3Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | MARTIN RESOURCE MANAGEMENT CORPORATION | $91,440 | 3.0% | $11,760 | 0 | 0 | |
| 2 | WRIGHT ASPHALT PRODUCTS COMPANY LLC | $103,200 | +12.9% | 16.2% | $7,520 | 0 | 0 |
| 3 | CLEVELAND ASPHALT PRODUCTS, INC. | $110,720 | +21.1% | 24.7% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
MARTIN RESOURCE MANAGEMENT CORPORATION vs WRIGHT ASPHALT PRODUCTS COMPANY LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8003-7016 RC-250 (DEL)(SITE 1) | 8,000 GAL | $3.76 | $4.30 | $3.89 | $4,320 |
| 8003-7017 RC-250 (DEL)(SITE 2) | 8,000 GAL | $3.80 | $4.30 | $3.96 | $4,000 |
| 8003-7018 RC-250 (DEL)(SITE 3) | 8,000 GAL | $3.87 | $4.30 | $4.02 | $3,440 |
Positive: the low bidder was cheaper on that item. These 3 items account for $11,760 of the $11,760 gap.