SL 8, Briar Forest to Briar Hill
3256-01-122 · let Mar 4, 2026 · Harris, Houston · Pedestrian, Sidewalks & Curb Ramps
$2,049,391Low bid: FORDE CONSTRUCTION COMPANY, INC.-45.8% vs estimate $3,780,772
$1,856Left on the table0.1% gap to the second bid
9BiddersSpread 64% low to high
36Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | FORDE CONSTRUCTION COMPANY, INC. | $2,049,391 | -45.8% | $1,856 | 8+$313,327 | 3-$426,455 | |
| 2 | MBN ENTERPRISES LLC | $2,051,247 | +0.1% | -45.7% | $237,123 | 5+$736,430 | 4-$817,504 |
| 3 | ICOS MANAGEMENT, LLC | $2,288,369 | +11.7% | -39.5% | $185,494 | 12+$968,699 | 4-$443,888 |
| 4 | ISI CONTRACTING, INC. | $2,473,863 | +20.7% | -34.6% | $262,172 | 12+$1,047,196 | 3-$600,505 |
| 5 | MC2 CIVIL, LLC | $2,736,035 | +33.5% | -27.6% | $30,702 | 10+$1,021,284 | 1-$161,599 |
| 6 | GARRET SHIELDS INFRASTRUCTURE | $2,766,737 | +35.0% | -26.8% | $229,935 | ||
| 7 | JFO SERVICES, LLC | $2,996,672 | +46.2% | -20.7% | $216,097 | ||
| 8 | CASTILLO ARANDA LLC | $3,212,769 | +56.8% | -15.0% | $158,386 | ||
| 9 | ROMAN EMPERORS ROAD, LLC | $3,371,155 | +64.5% | -10.8% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
FORDE CONSTRUCTION COMPANY, INC. vs MBN ENTERPRISES LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 481-7028 PIPE (PVC) (SCH 80) (8 IN) | 3,685 LF | $38.00 | $200.00 | $38.74 | $596,970 |
| 100-7002 PREPARING ROW | 51 STA | $7,700.00 | $1,000.00 | $6,072.92 | -$341,700 |
| 194-7020 RDSIDE AMENITY (REMOV & RESET) | 195 EA | $975.00 | $100.00 | $848.71 | -$170,625 |
| 556-7008 PIPE UNDERDRAINS (TY 8) (6") | 1,950 LF | $35.00 | $80.00 | $32.77 | $87,750 |
| 531-7001 CONC SIDEWALKS (4") | 2,992 SY | $75.00 | $95.00 | $70.57 | $59,840 |
| 110-7001 EXCAV (ROADWAY) | 462 CY | $145.00 | $20.00 | $11.68 | -$57,750 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 557 CY | $124.00 | $30.00 | $16.96 | -$52,358 |
| 400-7003 STRUCT EXCAV (PIPE) | 541 CY | $89.00 | $10.00 | $5.29 | -$42,739 |
| 104-7007 REMOV CONC (RIPRAP) | 120 CY | $400.00 | $150.00 | $26.91 | -$30,000 |
| 506-7034 CONSTRUCTION PERIMETER FENCE | 5,100 LF | $2.00 | $7.00 | $4.68 | $25,500 |
| 100-7010 PREP ROW (TREE PRUNE AND TRIM) | 6 STA | $6,500.00 | $3,000.00 | $1,185.58 | -$21,000 |
| 459-7007 GABION MATTRESSES (GALV)(12 IN) | 279 SY | $275.00 | $200.00 | $135.96 | -$20,925 |
| 400-7010 CEM STABIL BKFL | 97 CY | $350.00 | $140.00 | $138.14 | -$20,370 |
| 459-7005 GABION MATTRESSES (GALV)(6 IN) | 153 SY | $260.00 | $150.00 | $192.99 | -$16,830 |
| 162-7002 BLOCK SODDING | 3,695 SY | $7.00 | $11.00 | $4.39 | $14,780 |
| 104-7013 REMOV CONC (SIDEWALK, RAMP OR SUP) | 2,422 SY | $21.00 | $15.00 | $17.88 | -$14,532 |
| 506-7041 TEMP SEDMT CONT FENCE (REMOVE) | 11,040 LF | $2.00 | $1.00 | $1.02 | -$11,040 |
| 479-7003 ADJUSTING MANHOLES & INLETS | 7 EA | $750.00 | $2,000.00 | $1,535.11 | $8,750 |
| 432-7001 RIPRAP (CONC)(4 IN) | 125 CY | $765.00 | $820.00 | $573.24 | $6,875 |
| 506-7039 TEMP SEDMT CONT FENCE (INSTALL) | 11,040 LF | $4.50 | $5.00 | $3.92 | $5,520 |
Positive: the low bidder was cheaper on that item. These 20 items account for $6,116 of the $1,856 gap.
FORDE CONSTRUCTION COMPANY, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 110-7001 EXCAV (ROADWAY) | 462 CY | $145.00 | $11.68 | 12.41x | $61,593 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 557 CY | $124.00 | $16.96 | 7.31x | $59,619 |
| 400-7003 STRUCT EXCAV (PIPE) | 541 CY | $89.00 | $5.29 | 16.83x | $45,288 |
| 104-7007 REMOV CONC (RIPRAP) | 120 CY | $400.00 | $26.91 | 14.86x | $44,771 |
| 459-7007 GABION MATTRESSES (GALV)(12 IN) | 279 SY | $275.00 | $135.96 | 2.02x | $38,793 |
| 100-7010 PREP ROW (TREE PRUNE AND TRIM) | 6 STA | $6,500.00 | $1,185.58 | 5.48x | $31,886 |
| 400-7010 CEM STABIL BKFL | 97 CY | $350.00 | $138.14 | 2.53x | $20,550 |
| 506-7041 TEMP SEDMT CONT FENCE (REMOVE) | 11,040 LF | $2.00 | $1.02 | 1.96x | $10,826 |
| 500-7001 MOBILIZATION | 1 LS | $200,000.00 | $523,850.32 | 0.38x | -$323,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 11 MO | $3,500.00 | $11,585.04 | 0.30x | -$88,935 |
| 506-7034 CONSTRUCTION PERIMETER FENCE | 5,100 LF | $2.00 | $4.68 | 0.43x | -$13,669 |
MBN ENTERPRISES LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 481-7028 PIPE (PVC) (SCH 80) (8 IN) | 3,685 LF | $200.00 | $38.74 | 5.16x | $594,251 |
| 556-7008 PIPE UNDERDRAINS (TY 8) (6") | 1,950 LF | $80.00 | $32.77 | 2.44x | $92,089 |
| 162-7002 BLOCK SODDING | 3,695 SY | $11.00 | $4.39 | 2.51x | $24,432 |
| 104-7007 REMOV CONC (RIPRAP) | 120 CY | $150.00 | $26.91 | 5.57x | $14,771 |
| 100-7010 PREP ROW (TREE PRUNE AND TRIM) | 6 STA | $3,000.00 | $1,185.58 | 2.53x | $10,886 |
| 500-7001 MOBILIZATION | 1 LS | $200,000.00 | $523,850.32 | 0.38x | -$323,850 |
| 100-7002 PREPARING ROW | 51 STA | $1,000.00 | $6,072.92 | 0.16x | -$258,719 |
| 194-7020 RDSIDE AMENITY (REMOV & RESET) | 195 EA | $100.00 | $848.71 | 0.12x | -$145,999 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 11 MO | $3,500.00 | $11,585.04 | 0.30x | -$88,935 |
ICOS MANAGEMENT, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 194-7020 RDSIDE AMENITY (REMOV & RESET) | 195 EA | $4,280.00 | $848.71 | 5.04x | $669,101 |
| 480-7001 CLEAN EXIST CULVERTS | 7 EA | $12,840.00 | $1,712.97 | 7.50x | $77,889 |
| 104-7013 REMOV CONC (SIDEWALK, RAMP OR SUP) | 2,422 SY | $38.00 | $17.88 | 2.13x | $48,733 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 557 CY | $75.00 | $16.96 | 4.42x | $32,326 |
| 110-7001 EXCAV (ROADWAY) | 462 CY | $64.00 | $11.68 | 5.48x | $24,171 |
| 400-7003 STRUCT EXCAV (PIPE) | 541 CY | $43.00 | $5.29 | 8.13x | $20,402 |
| 479-7003 ADJUSTING MANHOLES & INLETS | 7 EA | $4,280.00 | $1,535.11 | 2.79x | $19,214 |
| 400-7010 CEM STABIL BKFL | 97 CY | $321.00 | $138.14 | 2.32x | $17,737 |
| 531-7010 CURB RAMPS (TY 7) | 3 EA | $8,560.00 | $2,829.94 | 3.02x | $17,190 |
| 104-7020 REMOV CONC (SAWCUT) | 333 LF | $64.00 | $17.64 | 3.63x | $15,439 |
| 100-7002 PREPARING ROW | 51 STA | $1,070.00 | $6,072.92 | 0.18x | -$255,149 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 11 MO | $1.00 | $11,585.04 | 0.00x | -$127,424 |
| 505-7001 TMA (STATIONARY) | 220 DAY | $1.00 | $217.57 | 0.00x | -$47,646 |
| 506-7034 CONSTRUCTION PERIMETER FENCE | 5,100 LF | $2.00 | $4.68 | 0.43x | -$13,669 |
ISI CONTRACTING, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 220 DAY | $1,000.00 | $217.57 | 4.60x | $172,134 |
| 400-7003 STRUCT EXCAV (PIPE) | 541 CY | $299.00 | $5.29 | 56.55x | $158,898 |
| 481-7028 PIPE (PVC) (SCH 80) (8 IN) | 3,685 LF | $75.00 | $38.74 | 1.94x | $133,626 |
| 194-7020 RDSIDE AMENITY (REMOV & RESET) | 195 EA | $1,500.00 | $848.71 | 1.77x | $127,001 |
| 550-7007 CHAIN LINK FENCE (REMOVE) | 200 LF | $450.00 | $5.45 | 82.64x | $88,911 |
| 550-7001 CHAIN LINK FENCE (INSTALL) (6') | 200 LF | $450.00 | $42.32 | 10.63x | $81,535 |
| 432-7001 RIPRAP (CONC)(4 IN) | 125 CY | $1,150.00 | $573.24 | 2.01x | $72,095 |
| 104-7007 REMOV CONC (RIPRAP) | 120 CY | $605.00 | $26.91 | 22.48x | $69,371 |
| 104-7013 REMOV CONC (SIDEWALK, RAMP OR SUP) | 2,422 SY | $40.60 | $17.88 | 2.27x | $55,031 |
| 459-7007 GABION MATTRESSES (GALV)(12 IN) | 279 SY | $300.00 | $135.96 | 2.21x | $45,768 |
| 500-7001 MOBILIZATION | 1 LS | $200,000.00 | $523,850.32 | 0.38x | -$323,850 |
| 100-7002 PREPARING ROW | 51 STA | $2,500.00 | $6,072.92 | 0.41x | -$182,219 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 11 MO | $3,000.00 | $11,585.04 | 0.26x | -$94,435 |
MC2 CIVIL, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 432-7001 RIPRAP (CONC)(4 IN) | 125 CY | $3,000.00 | $573.24 | 5.23x | $303,345 |
| 400-7003 STRUCT EXCAV (PIPE) | 541 CY | $325.00 | $5.29 | 61.46x | $172,964 |
| 459-7007 GABION MATTRESSES (GALV)(12 IN) | 279 SY | $750.00 | $135.96 | 5.52x | $171,318 |
| 481-7028 PIPE (PVC) (SCH 80) (8 IN) | 3,685 LF | $70.00 | $38.74 | 1.81x | $115,201 |
| 556-7008 PIPE UNDERDRAINS (TY 8) (6") | 1,950 LF | $80.00 | $32.77 | 2.44x | $92,089 |
| 400-7010 CEM STABIL BKFL | 97 CY | $600.00 | $138.14 | 4.34x | $44,800 |
| 104-7007 REMOV CONC (RIPRAP) | 120 CY | $320.00 | $26.91 | 11.89x | $35,171 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 557 CY | $80.00 | $16.96 | 4.72x | $35,111 |
| 110-7001 EXCAV (ROADWAY) | 462 CY | $75.00 | $11.68 | 6.42x | $29,253 |
| 506-7034 CONSTRUCTION PERIMETER FENCE | 5,100 LF | $9.00 | $4.68 | 1.92x | $22,031 |
| 194-7020 RDSIDE AMENITY (REMOV & RESET) | 195 EA | $20.00 | $848.71 | 0.02x | -$161,599 |