Bid Tab X-ray: 6495-68-001

Apr 15, 2026 · Collin Sign up free
Set your company to personalize scores

Hot Mix FY27

6495-68-001 · let Apr 15, 2026 · Collin, Dallas · Material Maintenance Project

$558,250Low bid: REYNOLDS ASPHALT & CONSTRUCTION COMPANY-3.1% vs estimate $576,000
$55,750Left on the table10.0% gap to the second bid
2BiddersSpread 10% low to high
4Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1REYNOLDS ASPHALT & CONSTRUCTION COMPANY $558,250-3.1% $55,750 0 0
2AUSTIN ASPHALT, INC. $614,000+10.0%6.6% 0 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.

Where the job was won

REYNOLDS ASPHALT & CONSTRUCTION COMPANY vs AUSTIN ASPHALT, INC., biggest item swings
ItemQtyLow2ndMarket2nd minus low
8017-7019 SP MIXTURES SP-D PG64-22 (PICKUP)4,500 TON $92.95$103.00$96.97 $45,225
8017-7010 SP MIXTURES SP-C PG70-22 (PICKUP)900 TON $93.50$101.00$104.70 $6,750
8011-7055 D-GR HMA TY D PG 64-22 (PICKUP)500 TON $92.95$99.00$89.12 $3,025
8011-7127 D-GR HMA TY C PG 70-22 (PICKUP)100 TON $93.50$101.00$120.25 $750

Positive: the low bidder was cheaper on that item. These 4 items account for $55,750 of the $55,750 gap.