Hot Mix FY27
6495-68-001 · let Apr 15, 2026 · Collin, Dallas · Material Maintenance Project
$558,250Low bid: REYNOLDS ASPHALT & CONSTRUCTION COMPANY-3.1% vs estimate $576,000
$55,750Left on the table10.0% gap to the second bid
2BiddersSpread 10% low to high
4Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | REYNOLDS ASPHALT & CONSTRUCTION COMPANY | $558,250 | -3.1% | $55,750 | 0 | 0 | |
| 2 | AUSTIN ASPHALT, INC. | $614,000 | +10.0% | 6.6% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
REYNOLDS ASPHALT & CONSTRUCTION COMPANY vs AUSTIN ASPHALT, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8017-7019 SP MIXTURES SP-D PG64-22 (PICKUP) | 4,500 TON | $92.95 | $103.00 | $96.97 | $45,225 |
| 8017-7010 SP MIXTURES SP-C PG70-22 (PICKUP) | 900 TON | $93.50 | $101.00 | $104.70 | $6,750 |
| 8011-7055 D-GR HMA TY D PG 64-22 (PICKUP) | 500 TON | $92.95 | $99.00 | $89.12 | $3,025 |
| 8011-7127 D-GR HMA TY C PG 70-22 (PICKUP) | 100 TON | $93.50 | $101.00 | $120.25 | $750 |
Positive: the low bidder was cheaper on that item. These 4 items account for $55,750 of the $55,750 gap.