SS 261, IH 45 to W Crosstimbers St
0110-06-151 · let Sep 2, 2026 · Harris, Houston · Rehabilitation of Existing Road
$1,196,118Low bid: ISI CONTRACTING, INC.-6.9% vs estimate $1,284,248
$74,971Left on the table6.3% gap to the second bid
6BiddersSpread 125% low to high
53Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ISI CONTRACTING, INC. | $1,196,118 | -6.9% | $74,971 | 2+$309,671 | 3-$537,369 | |
| 2 | STRUCTURAL INTEGRITY GROUP LLC | $1,271,089 | +6.3% | -1.0% | $192,041 | 1+$78,012 | 3-$513,870 |
| 3 | DIGG COMMERCIAL, LLC | $1,463,130 | +22.3% | 13.9% | $36,356 | 3+$139,147 | 1-$398,850 |
| 4 | MC2 CIVIL, LLC | $1,499,485 | +25.4% | 16.8% | $727,962 | 2+$33,621 | 2-$509,361 |
| 5 | SELECT MAINTENANCE, L.L.C. | $2,227,447 | +86.2% | 73.4% | $462,949 | 3+$909,692 | 1-$303,850 |
| 6 | EMERY SAPP & SON'S INC. | $2,690,397 | +124.9% | 109.5% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
ISI CONTRACTING, INC. vs STRUCTURAL INTEGRITY GROUP LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 75 DAY | $4,150.00 | $200.00 | $217.57 | -$296,250 |
| 361-7004 FULL - DEPTH REPAIR CRCP (9") | 700 CY | $565.00 | $849.00 | $704.20 | $198,800 |
| 720-7003 SPALLING REPAIR (POLYMERIC) (SEMIRIGID) | 286 GAL | $25.00 | $345.00 | $72.23 | $91,520 |
| 3017-7001 CONTINUOUS GRINDING-CONCRETE PAVEMENT | 17,034 SY | $4.00 | $8.29 | $6.23 | $73,076 |
| 500-7001 MOBILIZATION | 1 LS | $50,000.00 | $90,000.00 | $523,850.32 | $40,000 |
| 666-7221 RE PM TY II (Y)(CURB) | 37,430 LF | $2.10 | $2.88 | $1.82 | $29,195 |
| 505-7003 TMA (MOBILE OPERATION) | 46 DAY | $550.00 | $1.00 | $229.60 | -$25,254 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $3,250.00 | $1.00 | $11,585.04 | -$19,494 |
| 668-7103 PREFAB PM TY C (W)(WORD) | 101 EA | $299.83 | $195.00 | $249.54 | -$10,588 |
| 668-7089 PREFAB PM TY C (W)(24")(SLD) | 7,769 LF | $13.68 | $15.00 | $13.72 | $10,255 |
| 668-7091 PREFAB PM TY C (W)(ARROW) | 101 EA | $231.45 | $195.00 | $201.69 | -$3,681 |
| 666-7239 RE PM TY III (W)(8")(SLD) | 9,636 LF | $1.42 | $1.10 | $1.06 | -$3,084 |
| 672-7006 REFL PAV MRKR TY II-C-R | 1,771 EA | $6.31 | $5.00 | $4.19 | -$2,320 |
| 666-7262 RE PM TY III (BLK)(6")(SHADOW) | 20,730 LF | $0.9500 | $0.8500 | $0.7183 | -$2,073 |
| 678-7008 PAV SURF PREP FOR MRK (24") | 5,084 LF | $0.5300 | $0.1500 | $0.9416 | -$1,932 |
| 678-7002 PAV SURF PREP FOR MRK (6") | 31,698 LF | $0.0500 | $0.0100 | $0.0662 | -$1,268 |
| 666-7237 RE PM TY III (W)(6")(BRK) | 20,730 LF | $0.7900 | $0.8500 | $0.7099 | $1,244 |
| 666-7241 RE PM TY III (W)(8")(DOT) | 1,928 LF | $1.58 | $1.10 | $1.31 | -$925 |
| 678-7016 PAV SURF PREP FOR MRK (WORD) | 101 EA | $18.94 | $10.00 | $21.20 | -$903 |
| 666-7252 RE PM TY III (Y)(12")(SLD) | 607 LF | $3.84 | $5.00 | $3.78 | $704 |
Positive: the low bidder was cheaper on that item. These 20 items account for $77,022 of the $74,971 gap.
ISI CONTRACTING, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 75 DAY | $4,150.00 | $217.57 | 19.07x | $294,932 |
| 505-7003 TMA (MOBILE OPERATION) | 46 DAY | $550.00 | $229.60 | 2.40x | $14,739 |
| 500-7001 MOBILIZATION | 1 LS | $50,000.00 | $523,850.32 | 0.10x | -$473,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $3,250.00 | $11,585.04 | 0.28x | -$50,010 |
| 720-7003 SPALLING REPAIR (POLYMERIC) (SEMIRIGID) | 286 GAL | $25.00 | $72.23 | 0.35x | -$13,508 |
STRUCTURAL INTEGRITY GROUP LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 720-7003 SPALLING REPAIR (POLYMERIC) (SEMIRIGID) | 286 GAL | $345.00 | $72.23 | 4.78x | $78,012 |
| 500-7001 MOBILIZATION | 1 LS | $90,000.00 | $523,850.32 | 0.17x | -$433,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $1.00 | $11,585.04 | 0.00x | -$69,504 |
| 505-7003 TMA (MOBILE OPERATION) | 46 DAY | $1.00 | $229.60 | 0.00x | -$10,515 |
DIGG COMMERCIAL, LLC: unbalanced items
Placed 3MC2 CIVIL, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 75 DAY | $500.00 | $217.57 | 2.30x | $21,182 |
| 505-7003 TMA (MOBILE OPERATION) | 46 DAY | $500.00 | $229.60 | 2.18x | $12,439 |
| 500-7001 MOBILIZATION | 1 LS | $60,000.00 | $523,850.32 | 0.11x | -$463,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $4,000.00 | $11,585.04 | 0.35x | -$45,510 |
SELECT MAINTENANCE, L.L.C.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 361-7004 FULL - DEPTH REPAIR CRCP (9") | 700 CY | $1,650.00 | $704.20 | 2.34x | $662,060 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $42,000.00 | $11,585.04 | 3.63x | $182,490 |
| 720-7003 SPALLING REPAIR (POLYMERIC) (SEMIRIGID) | 286 GAL | $300.00 | $72.23 | 4.15x | $65,142 |
| 500-7001 MOBILIZATION | 1 LS | $220,000.00 | $523,850.32 | 0.42x | -$303,850 |