Bid Tab X-ray: 0902-00-368

Sep 2, 2026 · Parker Sign up free
Set your company to personalize scores

FY 2027 Guardrail

0902-00-368 · let Sep 2, 2026 · Parker, Fort Worth · Safety Improvement Projects

$3,643,031Low bid: ODUM SERVICES, LLC-26.8% vs estimate $4,975,541
$163,201Left on the table4.5% gap to the second bid
11BiddersSpread 61% low to high
29Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1ODUM SERVICES, LLC $3,643,031-26.8% $163,201 1+$31,293 2-$542,381
23LW CIVIL LLC $3,806,232+4.5%-23.5% $531,801 3+$84,538 7-$1,017,690
3GARRET SHIELDS INFRASTRUCTURE $4,338,033+19.1%-12.8% $9,466 2+$79,170 2-$192,554
4T&L CLEANING SERVICES LLC $4,347,498+19.3%-12.6% $9,291 1+$42,719 1-$74,024
5HJC FARMS, INC. $4,356,790+19.6%-12.4% $121,368 0 4-$298,616
6DIGG COMMERCIAL, LLC $4,478,158+22.9%-10.0% $119,979
7SHORT-LINE, LLC $4,598,137+26.2%-7.6% $27,385
8ICOS MANAGEMENT, LLC $4,625,522+27.0%-7.0% $185,773
9ALTUS CONSTRUCTION LLC $4,811,296+32.1%-3.3% $450,457
10ROADWAY SPECIALTIES, INC. $5,261,753+44.4%5.8% $610,677
11RAGLE CONSTRUCTION, INC. $5,872,430+61.2%18.0%

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.

Where the job was won

ODUM SERVICES, LLC vs 3LW CIVIL LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
432-7013 RIPRAP (MOW STRIP)(4 IN)2,309.1 CY $585.00$917.27$616.83 $767,245
540-7001 MTL W-BEAM GD FEN (TIM POST)38,705 LF $22.50$16.00$25.60 -$251,583
506-7039 TEMP SEDMT CONT FENCE (INSTALL)36,419 LF $3.50$0.1000$3.92 -$123,825
505-7001 TMA (STATIONARY)346 DAY $250.00$0.1000$217.57 -$86,465
542-7001 REMOVE METAL BEAM GUARD FENCE40,162.5 LF $2.00$0.1000$2.84 -$76,309
500-7001 MOBILIZATION1 LS $100,000.00$54,000.00$523,850.32 -$46,000
503-7002 PORTABLE CHANGEABLE MESSAGE SIGN4 EA $10,000.00$0.1000$9,253.78 -$40,000
540-7005 MTL BEAM GD FEN TRANS (THRIE-BEAM)73 EA $1,700.00$2,210.00$2,218.70 $37,230
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING18 MO $5,000.00$3,087.53$11,585.04 -$34,424
506-7041 TEMP SEDMT CONT FENCE (REMOVE)36,419 LF $1.00$0.1000$1.02 -$32,777
132-7003 EMBANK (FNL)(OC)(TY B)259 CY $35.00$133.59$16.96 $25,535
104-7005 REMOV CONC (MOWSTRIP)1,050 LF $10.00$30.00$9.49 $21,000
542-7003 REMOVE DOWNSTREAM ANCHOR TERMINAL153 EA $150.00$255.33$216.49 $16,115
162-7002 BLOCK SODDING1,869 SY $8.00$0.1000$4.39 -$14,765
544-7001 GUARDRAIL END TREATMENT (INSTALL)139 EA $2,875.00$2,965.00$3,190.07 $12,510
168-7001 VEGETATIVE WATERING223 TGL $50.00$0.1000$8.43 -$11,128
540-7029 MTL BM GD FEN TRANS (ANCHOR PLATE)65 EA $650.00$768.24$757.97 $7,686
542-7004 RM MTL BM GD FENCE TRANS (THRIE-BEAM)52 EA $150.00$273.10$284.77 $6,401
540-7015 DOWNSTREAM ANCHOR TERMINAL SECTION54 EA $1,525.00$1,430.86$1,297.32 -$5,084
164-7004 BROADCAST SEED (PERM_URBAN_CLAY)3,588 SY $1.50$0.1000$0.5051 -$5,023

Positive: the low bidder was cheaper on that item. These 20 items account for $166,340 of the $163,201 gap.

ODUM SERVICES, LLC: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
540-7039 TL-3 31" SHORT RADIUS (COMPLETE)3 EA $23,500.00$13,068.911.80x$31,293
500-7001 MOBILIZATION1 LS $100,000.00$523,850.320.19x-$423,850
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING18 MO $5,000.00$11,585.040.43x-$118,531

3LW CIVIL LLC: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
540-7039 TL-3 31" SHORT RADIUS (COMPLETE)3 EA $24,000.00$13,068.911.84x$32,793
132-7003 EMBANK (FNL)(OC)(TY B)259 CY $133.59$16.967.88x$30,206
104-7005 REMOV CONC (MOWSTRIP)1,050 LF $30.00$9.493.16x$21,538
500-7001 MOBILIZATION1 LS $54,000.00$523,850.320.10x-$469,850
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING18 MO $3,087.53$11,585.040.27x-$152,955
506-7039 TEMP SEDMT CONT FENCE (INSTALL)36,419 LF $0.1000$3.920.03x-$138,971
542-7001 REMOVE METAL BEAM GUARD FENCE40,162.5 LF $0.1000$2.840.04x-$110,170
505-7001 TMA (STATIONARY)346 DAY $0.1000$217.570.00x-$75,245
503-7002 PORTABLE CHANGEABLE MESSAGE SIGN4 EA $0.1000$9,253.780.00x-$37,015
506-7041 TEMP SEDMT CONT FENCE (REMOVE)36,419 LF $0.1000$1.020.10x-$33,484

GARRET SHIELDS INFRASTRUCTURE: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
542-7003 REMOVE DOWNSTREAM ANCHOR TERMINAL153 EA $500.00$216.492.31x$43,377
540-7039 TL-3 31" SHORT RADIUS (COMPLETE)3 EA $25,000.00$13,068.911.91x$35,793
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING18 MO $5,000.00$11,585.040.43x-$118,531
542-7001 REMOVE METAL BEAM GUARD FENCE40,162.5 LF $1.00$2.840.35x-$74,024

T&L CLEANING SERVICES LLC: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
168-7001 VEGETATIVE WATERING223 TGL $200.00$8.4323.71x$42,719
542-7001 REMOVE METAL BEAM GUARD FENCE40,162.5 LF $1.00$2.840.35x-$74,024

HJC FARMS, INC.: unbalanced items

Placed 5
ItemQtyTheir priceMarketx market$ vs market
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING18 MO $2,500.00$11,585.040.22x-$163,531
540-7015 DOWNSTREAM ANCHOR TERMINAL SECTION54 EA $17.50$1,297.320.01x-$69,110
540-7039 TL-3 31" SHORT RADIUS (COMPLETE)3 EA $1,000.00$13,068.910.08x-$36,207
540-7029 MTL BM GD FEN TRANS (ANCHOR PLATE)65 EA $300.00$757.970.40x-$29,768