6507-77-001 Median Cable Barrier
6507-77-001 · let Sep 8, 2026 · Ector, Odessa · Routine Maintenance Project - Sealed
$495,010Low bid: HJC FARMS, INC.+8.0% vs estimate $458,400
$151,790Left on the table30.7% gap to the second bid
2BiddersSpread 31% low to high
8Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | HJC FARMS, INC. | $495,010 | 8.0% | $151,790 | 1+$58,847 | 3-$41,818 | |
| 2 | AUSTIN BARRICADE COMPANY, L.L.C. | $646,800 | +30.7% | 41.1% | 6+$194,875 | 1-$29,992 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
HJC FARMS, INC. vs AUSTIN BARRICADE COMPANY, L.L.C., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 40 DAY | $0.0100 | $3,000.00 | $217.57 | $120,000 |
| 771-7018 CHECK / RE-TENSION CABLE (TL-4) | 20 EA | $0.0100 | $500.00 | $67.25 | $10,000 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 35 DAY | $0.0100 | $250.00 | $87.82 | $8,750 |
| 771-7016 REPLACE CABLE (TL-4) | 800 LF | $0.0100 | $10.00 | $2.15 | $7,992 |
| 771-7010 CABLE SPLICE / TURNBUCKLE (TL-4) | 10 EA | $0.0100 | $500.00 | $88.10 | $5,000 |
| 500-7002 MOBILIZATION (CALLOUT) | 50 EA | $0.0100 | $1.00 | $600.85 | $50 |
| 771-7007 REPLACE POSTS (TL-4)(TRINITY) | 1,500 EA | $250.00 | $250.00 | $144.70 | $0 |
| 771-7014 REPR OR REPLC CABLE BARR TERM SEC(TL-4) | 60 EA | $2,000.00 | $2,000.00 | $1,019.22 | $0 |
Positive: the low bidder was cheaper on that item. These 8 items account for $151,790 of the $151,790 gap.
HJC FARMS, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 771-7014 REPR OR REPLC CABLE BARR TERM SEC(TL-4) | 60 EA | $2,000.00 | $1,019.22 | 1.96x | $58,847 |
| 500-7002 MOBILIZATION (CALLOUT) | 50 EA | $0.0100 | $600.85 | 0.00x | -$30,042 |
| 505-7001 TMA (STATIONARY) | 40 DAY | $0.0100 | $217.57 | 0.00x | -$8,702 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 35 DAY | $0.0100 | $87.82 | 0.00x | -$3,073 |
AUSTIN BARRICADE COMPANY, L.L.C.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 40 DAY | $3,000.00 | $217.57 | 13.79x | $111,297 |
| 771-7014 REPR OR REPLC CABLE BARR TERM SEC(TL-4) | 60 EA | $2,000.00 | $1,019.22 | 1.96x | $58,847 |
| 771-7018 CHECK / RE-TENSION CABLE (TL-4) | 20 EA | $500.00 | $67.25 | 7.43x | $8,655 |
| 771-7016 REPLACE CABLE (TL-4) | 800 LF | $10.00 | $2.15 | 4.65x | $6,281 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 35 DAY | $250.00 | $87.82 | 2.85x | $5,676 |
| 771-7010 CABLE SPLICE / TURNBUCKLE (TL-4) | 10 EA | $500.00 | $88.10 | 5.68x | $4,119 |
| 500-7002 MOBILIZATION (CALLOUT) | 50 EA | $1.00 | $600.85 | 0.00x | -$29,992 |