Bid Tab X-ray: 6507-18-001

Sep 16, 2026 · Walker Sign up free
Set your company to personalize scores

FY27 - Walker/Madison Emulsion - 09

6507-18-001 · let Sep 16, 2026 · Walker, Bryan · Material Maintenance Project

$139,040Low bid: ERGON ASPHALT & EMULSIONS, INC.-9.5% vs estimate $153,600
$17,360Left on the table12.5% gap to the second bid
3BiddersSpread 37% low to high
4Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1ERGON ASPHALT & EMULSIONS, INC. $139,040-9.5% $17,360 0 0
2WRIGHT ASPHALT PRODUCTS COMPANY LLC $156,400+12.5%1.8% $34,400 0 0
3CLEVELAND ASPHALT PRODUCTS, INC. $190,800+37.2%24.2% 0 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.

Where the job was won

ERGON ASPHALT & EMULSIONS, INC. vs WRIGHT ASPHALT PRODUCTS COMPANY LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
8003-7114 CRS-2P (DEL)(SITE 1)20,000 GAL $2.54$2.85$2.78 $6,200
8003-7115 CRS-2P (DEL)(SITE 2)20,000 GAL $2.54$2.85$2.78 $6,200
8003-7087 CSS-1H (DEL)(SITE 1)8,000 GAL $2.34$2.65$2.49 $2,480
8003-7088 CSS-1H (DEL)(SITE 2)8,000 GAL $2.34$2.65$2.08 $2,480

Positive: the low bidder was cheaper on that item. These 4 items account for $17,360 of the $17,360 gap.